Florida Appellate Court Holds Four-Year Statute of Limitations Applicable Irrespective of Contractor Licensure
June 22, 2016 —
Clay Whittaker – Florida Construction Law UpdateIn Brock v. Garner Window & Door Sales, Inc.,[1] Florida’s Fifth District Court of Appeal rejected a novel attempt to circumvent Florida’s well-established four-year statute of limitations for all actions founded on the construction of an improvement to real property. Plaintiff filed a lawsuit alleging breach of contract as a result of water intrusion damage following the installation of windows.[2] It was undisputed that Plaintiff commenced the litigation more than four years following the discovery of the allegedly latent defect in the window installation.[3] Plaintiff’s counsel argued that the window contractor could not rely on the four-year statute of limitations because the window subcontractor was not a licensed contractor and, therefore, the five-year statute of limitations for actions founded on written contracts should apply.
Read the court decisionRead the full story...Reprinted courtesy of
Clay Whittaker, Cole, Scott, & Kissane, P.A.Mr. Whittaker may be contacted at
clay.whittaker@csklegal.com
Useful Life: A Valuable Theory for Reducing Damages
March 29, 2017 —
Brooke E. Beebe, Esq. - Florida Construction Law NewsThe situation is one all too familiar to construction defect litigants. A homeowner contracts with a roofing contractor to install a new roof with a life expectancy of ten years.[1] After only five years, the homeowner brings a claim for construction defects in the roof alleging that the roof requires complete replacement due to water intrusion. The homeowner seeks damages for the full replacement cost of the roof. However, under a “useful life” theory, the homeowner would not be entitled to damages for the full amount of the replacement cost. Instead, the homeowner would be entitled to one-half of the cost of the replacement roof, taking into account the fact that he or she had been deprived of only five, rather than ten, years of use. “Useful life” is best understood as the expected length of time that a newly built construction element can be reasonably anticipated to last, subject to routine maintenance and ordinary wear and tear. The “useful life” theory holds that granting the homeowner damages for the full replacement cost of the roof would result in unjust enrichment to the homeowner, who had contracted for a roof with a ten-year, rather than a fifteen-year, useful life.
Read the court decisionRead the full story...Reprinted courtesy of
Brooke E. Beebe, Cole, Scott & Kissane, P.A.Ms. Beebe may be contacted at
brooke.beebe@csklegal.com
A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Ownership is Not a Conclusive Factor for Ongoing Operations Additional Insured Coverage
November 15, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Management Services v. Financial Pacific Ins. Co. (No. D069814, filed 11/14/17), a California appeals court held that an insurer had a duty to defend a general contractor under an “ongoing operations” additional insured (AI) endorsement for damage occurring after the named insured subcontractor completed its work, because the endorsement did not limit coverage solely to liability during the subcontractors’ ongoing operations, but rather, broadly provided coverage for liability “arising out of” such operations.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Judicial Council Votes to Rescind Prohibitions on Eviction and Foreclosure Proceedings
September 28, 2020 —
David Rao & Lyndsey Torp - Snell & Wilmer Real Estate Litigation BlogThe California Judicial Council’s emergency rules staying evictions and judicial foreclosures are coming to an end.
On March 27, 2020, the Governor of California issued executive order N-38-20, giving the Judicial Council emergency authority to act in response to the COVID-19 pandemic. On April 6, 2020, the Judicial Council of California voted to approve temporary emergency rules of court. Rule 1 prohibited the issuance of a summons, or the entering of a default, in an eviction action for both residential and commercial properties except as necessary to protect public health and safety. Rule 1 also continued all pending unlawful detainer trials for at least 60 days, with no new trials being set until at least 60 days after a request was filed. Rule 2 stayed all pending judicial foreclosure actions, tolled the statute of limitations, and extended the deadlines for responding to such actions.
Rule 1 and Rule 2 were to remain in effect until 90 days after the Governor declared the state of emergency resulting from the COVID-19 pandemic lifted, or until repealed by action of the Judicial Council. On August 13, 2020, the Judicial Council voted 19-1 to sunset Rule 1 and Rule 2 as of September 1, 2020. Beginning September 2, 2020, California state courts are authorized to issue summons on unlawful detainer actions, enter defaults, and set trial dates on request. Stays on pending judicial foreclosure actions will be lifted.
Reprinted courtesy of
David Rao, Snell & Wilmer and
Lyndsey Torp, Snell & Wilmer
Mr. Rao may be contacted at drao@swlaw.com
Ms. Torp may be contacted at ltorp@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Builders Can’t Rely on SB800
October 01, 2013 —
CDJ STAFFIn coming to their ruling on SB800, the California Court of Appeals looked to the legislative intent behind the law. Valentine Hoy, Timothy Hutter, and Erin Sedloff of Allen Matkins, in an article on the ruling, note that SB800 was written in response to Aas v. Superior Court, in which the court found that there was no remedy for construction defects that had not resulted in property damage. In the latest ruling, Liberty Mutual v. Brookfield Crystal Cove, LLC, the court concluded that SB800 was passed to give homeowners a way to address defects that had not lead to damage. However, the court also concluded that the legislature did not intend for SB800 to be the only remedy.
In Liberty Mutual, the insurance company sought reimbursement for claims it had paid on a homeowner’s claim after a fire sprinkler pipe burst. Liberty Mutual had insured the homeowner and sought repayment from the builder. Escrow had closed on the home in 2004, the pipe burst in 2008, and Liberty Mutual filed their claim in 2011, seven years after the close of escrow. But for plumbing issues, SB800 has a four-year statute of limitations.
The writers describe California as “a hotbed for construction defect litigation.” Due to the Liberty Mutual ruling, developers now “cannot rely on the statutes of limitation set forth in SB800.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com