Client Alert: Restaurant Owed Duty of Care to Driver Killed by Third-Party on Street Adjacent to Restaurant Parking Lot
January 07, 2015 —
R. Bryan Martin, Lawrence S. Zucker II, & Kristian B. Moriarty – Haight, Brown, & Bonesteel, LLPIn Annocki v. Peterson Enterprise, LLC, (Filed 11/14/2014, Certified for Publication 12/5/2014, No. B251434) the Court of Appeal, Second District, held a restaurant owed a duty of care to the driver of a motorcycle who died as a result of the negligent driving of a third party exiting the restaurant’s parking lot.
Decedent, Joseph M. Annocki, was driving his motorcycle on Pacific Coast Highway in Malibu, when it collided with the vehicle operated by Terry Allen Turner, who was exiting the parking lot of “Geoffrey’s" restaurant, which was owned and operated by the Defendant, Peterson Enterprise, LLC (“Peterson”).
The parents of the decedent (“Plaintiffs”) filed suit against Peterson, alleging Peterson failed to adequately staff the restaurant parking lot, which caused Turner to become confused and make an illegal left turn onto Pacific Coast Highway, thereby causing the accident that killed decedent. Plaintiffs further alleged Peterson knew, or should have known, that its parking lot and driveway were designed and in such condition as to create a danger of decreased visibility of the adjacent highway, and failed to adequately provide signage directing patrons that only right turns could be made onto Pacific Coast Highway.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
R. Bryan Martin,
Lawrence S. Zucker II and
Kristian B. Moriarty
Mr. Martin may be contacted at bmartin@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Are We Headed for a Work Shortage?
June 17, 2015 —
Craig Martin – Construction Contractor AdvisorA recent Wall Street Journal article, Worker Shortage Hammers Builders, noted that construction industry employers are facing a tight labor market.
“U.S. builders shed more than 2 million jobs during and after the housing bust. Now they say they can’t find enough carpenters, electricians, plumbers and other craftsmen for a growing pipeline of work.”
That is certainly consistent with everything that I’ve heard and read about construction companies in the Midwest. Unfortunately, it seems as though the problem is only going to get worse.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Tokyo's Skyline Set to See 45 New Skyscrapers by 2020 Olympics
April 20, 2017 —
Gareth Allan & Katsuyo Kuwako - BloombergTokyo’s skyline is set to welcome 45 new skyscrapers by the time city hosts the Olympics in 2020, as a surge of buildings planned in the early years of Abenomics near completion.
Japan’s capital will see nearly 50 percent more new high-rise space in the next three years than it did in the preceding three, Toyokazu Imazeki, chief analyst at office leasing and consulting firm Sanko Estate Co Ltd., said in an interview. He said the increase was fueled by the fiscal expansion and monetary easing under Abe’s economic program, launched after his election in late 2012.
“This marks the timing for completion of buildings planned from about 2013 when developers were expecting the economy to expand,” said Imazeki. The increase in building was supported not only by Abe’s expansionary policies but also Japan’s ultra-low interest rates, he said.
Reprinted courtesy of
Gareth Allan, Bloomberg and
Katsuyo Kuwako, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Again Rejects Coverage for Faulty Workmanship
January 13, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the District of Hawaii continued its longstanding pattern of finding no coverage for claims based upon construction defects. Am. Auto. Ins. Co. v. Haw. Nut & Bolt, 2016 U.S. Dist. LEXIS 174243 (D. Haw. Dec. 16, 2016).
Safeway filed a complaint against Hawaii Nut & Bolt (HNB). The complaint involved issues pertaining to the construction of the roof deck at a Safeway store. HNB was a subcontractor hired to supply a coating system on the roof of the store to make it waterproof. The product was manufactured by VersaFlex. After the store opened, there were water leaks from the roof. This disrupted business operations and caused damage to Safeway's business and reputation. HNB tendered the claims to its CGL carrier, Fireman's Fund Insurance Corporation (FFIC). FFIC defended the underlying lawsuit for six years under a reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Stocks Fall as Small Shares Tumble Amid Home Sales
September 24, 2014 —
Joseph Ciolli and Callie Bost – BloombergU.S. stocks fell, led by a plunge among small companies, as sales of existing homes unexpectedly dropped and China’s finance minister damped stimulus hopes.
The Russell 2000 Index of small-cap stocks sank 1.6 percent, the most since July. Yahoo! Inc. (YHOO) dropped 2.3 percent to lead the Dow Jones Internet Composite Index to a one-month low. Alibaba Group Holding Ltd. slid 2.1 percent after surging in its trading debut Sept. 19.
The Standard & Poor’s 500 Index dropped 0.7 percent to 1,997.37 at 11:24 a.m. in New York, after closing at a record Sept. 18. The benchmark gauge hasn’t had a four-day slide this year and hasn’t fallen 10 percent in three years. The Dow Jones Industrial Average slid 58.40 points, or 0.3 percent, to 17,221.34.
Mr. Ciolli may be contacted at jciolli@bloomberg.net; Ms. Bost may be contacted at cbost2@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Joseph Ciolli and Callie Bost, Bloomberg
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
It Has Started: Supply-Chain, Warehouse and Retail Workers of Essential Businesses Are Filing Suit
June 22, 2020 —
Robert G. Devine, James Burger & Douglas Weck - White and Williams LLPSupply-chain businesses that are appropriately characterized as “essential” have remained open for the delivery of critical supplies while everyone else has been told to close up shop and stay home. Now essential-business employees are contracting COVID-19 and filing suit. Following up on our earlier piece — “Is a Violation of a COVID-19 Order the Basis For Civil Liability?” — it is important to recognize that government directives, oftentimes couched as “recommendations,” can come to define what it means to provide a reasonably safe workplace that protects employees from COVID-19. While common law negligence defenses consider the reasonableness of conduct, these directives will likely become the standard.
The cases that have been filed are overwhelmingly premised upon the timeless negligence construct. The negligence construct, simply put, imposes a duty to act as a reasonable person would under the circumstances. Nonetheless, while the negligence construct lives in the ordinary world of “reasonableness,” infection-control guidance lives in the rapidly developing world of the science of COVID-19. Guidance on seemingly basic questions, such as the methods of transmission (e.g., personal contact, mucus membrane only, airborne transmission) or even the virus’s shelf life on different surfaces, of particular interest packaging and material handling equipment, can change by the day. All of this provides challenges for the supply-side business looking to protect its workforce.
Reprinted courtesy of White and Williams LLP attorneys
James Burger,
Robert Devine and
Douglas Weck
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Weck may be contacted at weckd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of