Request for Stay Denied in Dispute Over Coverage for Volcano Damage
August 10, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAlthough there were concurrent state and federal proceedings regarding the insureds' claims for damage caused by Kilauea Volcano, the federal district court refused to dismiss or stay the federal action. Aqulina v Certain Underwriters at Lloyd's Syndicate #2003, 2020 U.S. District Ct. LEXIS 101832 (D. Haw. June 10, 2020).
Plaintiffs held homeowner's policies from Lloyd's that were brokered and underwritten by various defendants. Coverage from the May 2018 eruption of Kilauea Volcano was denied based upon an exclusion precluding coverage for lava-related damage.
Plaintiffs sued Lloyds and various brokers in federal court, alleging that defendants had engaged in a deceptive scheme to defraud plaintiffs and deprive them of meaningful coverage. Lawsuits were also filed in state court, with plaintiffs arguing their losses were covered by their policies and that defendants wrongfully relied solely on the lava exclusion to deny claims.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Nomos LLP Partner Garret Murai Recognized by Super Lawyers
August 03, 2022 —
Garret Murai - California Construction Law BlogNomos LLP Partner Garret Murai has been recognized as a 2022 Northern California Super Lawyers honoree in the area of Construction Litigation. This is the ninth consecutive year that he has been recognized by Super Lawyers.
Super Lawyers, an annual listing of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and personal achievement, is limited to no more than five percent (5%) of lawyers in a state who are selected through a multiphase process that includes a statewide survey of lawyers, independent research evaluation and peer reviews by practice area.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Federal Government Partial Shutdown – Picking Up the Pieces
February 27, 2019 —
Jacob W. Scott - Now that the partial shutdown has ended (though with the specter of another just around the corner), contractors are asking, “What now?” and “What did that cost me?” Although every case is fact-specific, following are some guidelines for moving forward after the shutdown.
Following up on our previous guidance, contractors should make sure that any court, board, or agency filings made during the shutdown were received and properly docketed. If there is any question whether a filing was received, file it again as soon as possible with proof of the earlier attempt to file. The busiest tribunals, such as the federal courts, the Court of Federal Claims, the Boards of Contract Appeals, and the Government Accountability Office, remained open, or at least open to accept filings, and all indications are that filings made during the shutdown were received and acknowledged. But for some of the other tribunals or agencies, such as the Small Business Administration (“SBA”) Office of Hearings and Appeals and the SBA Office of Government Contracting and Business Development, prudence dictates double-checking that all filings were received. In many cases, non-statutory deadlines have been or will be adjusted by the court, board, or agency.
Read the court decisionRead the full story...Reprinted courtesy of
Jacob W. Scott, Smith CurrieMr. Scott may be contacted at
jwscott@smithcurrie.com
The BUILDCHAIN Project Enhances Data Exchange and Transparency in the EU Construction Industry
January 23, 2023 —
Aarni Heiskanen - AEC BusinessTrace Labs, a WEB 3 developer, joins the EU’s efforts to create a smarter and more sustainable built environment with the
BUILDCHAIN project. With its 11 EU partners, Trace Labs aims to improve efficiency, reduce errors, and increase transparency and trust in construction.
Efficient, transparent, and trusted data exchange is a powerful tool for driving sustainability, resilience, and energy efficiency in construction. However, there are several obstacles to trusted data exchange in the industry today:
- Data silos: Construction projects involve multiple parties and stakeholders, each of which may have its systems for storing and sharing information. This can lead to data silos and a lack of coordination, making it difficult to access and trust the data.
- Lack of standardization: Construction projects may use different formats for storing and sharing data, leading to difficulties in comparing and combining information from various projects.
- Data security: Construction projects often involve sensitive information, such as building plans, materials lists, and inspection results. Ensuring this information is secure and protected from unauthorized access can be a significant challenge.
- Lack of incentives: There are often few incentives for construction companies and other stakeholders to share data and collaborate on projects, making establishing trust and transparency challenging.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Ninth Circuit Construes Known Loss Provision
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit reversed the district court's award of summary judgment to the insurer after analyzing the known loss provision in the insured subcontractor's policy. Kaady v. Mid-Continent Cas. Co., 2015 U.S. App. LEXIS 10754 (9th Cir. June 25, 2015).
The insured was awarded a subcontract to install manufactured stone at the residential project. The stone was affixed to the wall sheathing. The insured also wrapped deck posts with manufactured stone and installed masonry caps on the toe of the stone that was wrapped around the deck posts.
After construction was completed, the insured was called back to the project to inspect cracks in the manufactured stone and masonry caps he installed. The insured told the general contractor that the cracks were likely due to settling. Three months after inspecting the cracks, the insured purchased a CGL policy from Mid-Continent.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hunton Andrews Kurth Promotes Insurance Recovery Lawyer Andrea (Andi) DeField to Partner
April 05, 2021 —
Lorelie S. Masters - Hunton Insurance Recovery BlogEffective April 1, 2021, Hunton Andrews Kurth LLP has promoted insurance recovery lawyer,
Andi DeField, and six other attorneys, to
partner. “Andi has been a superstar in our practice since the day she arrived,” said insurance recovery practice head,
Walter Andrews, adding that “Andi’s promotion reflects the incredible hard work she has contributed to the practice and outstanding results she has achieved for our clients over the years.” A native of Miami, Andi ascended through the ranks at Hunton in its Miami office, joining the firm as a contract lawyer before earning promotions to associate, counsel and, now, partner. But Andi’s rapid ascension did not come without much hard work. Since joining the firm, “Andi has, year after year, consistently knocked the cover off the ball in terms of her tireless work ethic, the superior results she has achieved and her extraordinary aptitude for marketing herself, our practice and the firms many other practices,” said insurance recovery partner,
Mike Levine. Levine added, “Andi is an amazing lawyer and a true champion for her clients. I’m proud to now call her my partner.”
Read the court decisionRead the full story...Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews KurthMs. Masters may be contacted at
lmasters@HuntonAK.com
New York Philharmonic Will Open Geffen Hall Two Years Ahead of Schedule
April 11, 2022 —
James Tarmy - BloombergAfter decades of setbacks, the New York Philharmonic will finally perform in a gut-renovated concert hall in October.
“The key is—two years early—on budget and on schedule,” says a triumphant Deborah Borda, the president and chief executive officer of the New York Philharmonic, standing under a scaffold in what will be the completely revamped concert hall.
A happy ending was by no means guaranteed.
The venue, set at New York’s Lincoln Center, had problems almost as soon as its doors opened in 1962. Concertgoers and performers complained that the sound was muddy and deadening.
Read the court decisionRead the full story...Reprinted courtesy of
James Tarmy, Bloomberg
Another Las Vegas Tower at the Center of Construction Defect Claims
November 07, 2012 —
CDJ STAFFAccusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¼ inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the court decisionRead the full story...Reprinted courtesy of