Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at
gazzolaj@pepperlaw.com
Wilke Fleury Secures Bid Protest Denial
March 16, 2020 —
Wilke Fleury LLPAfter the City of Vacaville, following a sealed bid process, awarded a significant well drilling contract to Roadrunner Drilling & Pump Company, second-place bidder Nor-Cal Pump and Well Drilling filed a protest with the City on January 30, claiming that Roadrunner’s bid failed to meet certain requirements of the proposed contract. Roadrunner hired Wilke Fleury to defend the bid protest. After Wilke Fleury partner Dan Baxter transmitted a letter to the City explaining why the disgruntled bidder’s protest was factually and legally unsupported, the City—a mere nine days after receiving Dan’s letter—rejected the bid protest, and maintained its award of the project to Roadrunner as the lowest responsive and responsible bidder.
Wilke Fleury LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Duty to Design and Maintain Reasonably Safe Roadways Extends to All Persons. (WA)
February 25, 2014 —
Natasha Khachatourians – Scheer & Zehnder LLP Liability NewsletterCase: Lowman v. Wilbur, et al., 178 Wn.2d 165, 309 P.3d 3.87 (2013).
Issue: If a passenger’s injuries are in fact caused by the placement of a utility pole too close to a roadway, can the injuries be deemed too remote for purposes of legal causation? NO.
Facts: Plaintiff was a passenger in a vehicle that lost control and collided with a utility pole that was 4.47 feet from the edge of the roadway. The vehicle’s driver was under the influence of alcohol. Plaintiff sued the driver as well as the utility company and Skagit County for negligence. The trial court granted the utility company and Skagit County’s summary judgment motion, finding that the negligent placement of the utility pole was not a legal cause of plaintiff’s injuries.
The issue before the Supreme Court was whether a negligently placed utility pole could be the legal cause of a resulting injury.
Read the court decisionRead the full story...Reprinted courtesy of
Natasha Khachatourians, Scheer & Zehnder LLP Ms. Khachatourians may be contacted at
natashak@scheerlaw.com
Defense Owed to Directors and Officers Despite Insured vs. Insured Exclusion
May 13, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found there the duty to defend a suit filed by the FDIC against officers and directors was not excluded by the insured versus insured provision in the policy. W Holding Co., Inc. v. AIG Ins. Co. - Puerto Rico, 2014 U.S. App. LEXIS 5943 (1st Cir. March 31, 2014).
Regulators ordered the closure of the insured bank and the Federal Deposit Insurance Corporation (FDIC) was appointed as receiver. FDIC concluded certain bank directors and officers had breached their fiduciary duty by jeopardizing the bank's financial soundness. The FDIC concluded these breaches had caused more than $367 million in losses and demanded reimbursement by the directors and officers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season
October 11, 2021 —
Tracy Alan Saxe, Kelly A. Johnson, Samantha M. Oliveira & R. G. Nelson - Saxe Doernberger & VitaSDV's Natural Disaster Recovery Group presents the Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season. This handbook intends to be a practical guide on policyholder issues, both homeowners and business owners alike, when preparing for hurricane season and handling claims after a loss due to a hurricane. The handbook is a living document that will evolve over time, as our Natural Disaster Recovery Group members continue to contribute new and expansive content on the complex issues arising in this area. Remember to check back for additional information and updated content regarding the Hurricane Season Policyholder’s Handbook.
I. Are You Adequately Insured for a Hurricane?
Understanding the various types of coverage policyholders can purchase is vital to weathering the financial storm following a natural disaster.
Reprinted courtesy of
Tracy Alan Saxe, Saxe Doernberger & Vita,
Kelly A. Johnson, Saxe Doernberger & Vita,
Samantha M. Oliveira, Saxe Doernberger & Vita and
R. G. Nelson, Saxe Doernberger & Vita
Mr. Saxe may be contacted at TSaxe@sdvlaw.com
Ms. Johnson may be contacted at KJohnson@sdvlaw.com
Ms. Oliveira may be contacted at SOliveira@sdvlaw.com
Ms. Nelson may be contacted at RNelson@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Defend Trade Secret Act of 2016–-Federalizing Trade Secret Law
October 07, 2016 —
Erin M. Stines and Reed Cahill - Ahlers & Cressman PLLCThe Defend Trade Secret Act of 2016 (DTSA) was signed into law on May 11, 2016, and became effective immediately. The DTSA allows an owner of a trade secret to sue in federal court for trade secret misappropriation. Previously, only state law governed civil misappropriation of trade secrets. While the DTSA largely mirrors the current state of the law under the Uniform Trade Secrets Act (UTSA), adopted by 48 states, including Washington,[1] there are some additions found in the new law.
The DTSA imposes the same three-year statute of limitations and authorizes remedies similar to those provided under the UTSA. The DTSA also offers new forms of relief, including a provision permitting ex parte seizure orders (that is, without a hearing or response from the opposing party) to prevent further misappropriation of the trade secret. The DTSA further provides for a new definition of trade secret. The UTSA's definition of a trade secret is a “formula, pattern, compilation, program, device, method, technique, or process.” Under the DTSA, the definition of a “trade secret” is broadened to include “all forms and types of financial, business, scientific, technical, economic, or engineering information...whether tangible or intangible...” [2]
Read the court decisionRead the full story...Reprinted courtesy of
Erin M. Stines & Reed Cahill, Ahlers & Cressman PLLCMs. Stines may be contacted at
erin.stines@ac-lawyers.com
Corps Releases Final Report on $29B Texas Gulf Coast Hurricane Defense Plan
October 11, 2021 —
James Leggate - Engineering News-RecordA $28.87 billion plan to protect the Texas Gulf Coast’s residents and infrastructure against hurricanes and storm surge with a series of coastal storm risk management and ecosystem restoration projects took a step closer to reality Sept. 10 with the release of a final feasibility report and final environmental impact statement from the U.S. Army Corps of Engineers and Texas General Land Office (GLO).
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at https://www.enr.com/leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Landlord’s Guide to the Center for Disease Control’s Eviction Moratorium
October 05, 2020 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogThe Center for Disease Control and Prevention (the “CDC”) and the Department of Health and Human Services (the “HHS”) has issued an order to temporarily halt a landlord’s right to evict certain residential tenants to prevent the further spread of COVID-19 (the “CDC Order”).
The CDC Order is effective through December 31, 2020.
Applicability of the CDC Order. The CDC Order does not apply in jurisdictions that have a moratorium on residential evictions in effect that provides the same or greater level of protection than the CDC Order, and the CDC Order permits local jurisdictions to continue to pass more restrictive eviction moratoriums. To invoke the protection provided by the CDC Order, a landlord’s tenants must deliver an executed declaration (a “CDC Declaration”) form to the landlord that includes the following statements: (i) the tenant has used best efforts to obtain all available government assistance for rent or housing; (ii) expects to earn no more than $99,000 in annual income in 2020 (or $198,000 if filing joint tax returns), was not required to report income in 2019, or received an Economic Impact Payment under the CARES Act; (iii) the tenant is unable to pay the full rent due to substantial loss of household income, loss of work or wages, or extraordinary out-of-pocket medical expenses; (iv) the tenant is using best efforts to make partial payments that are as close to the full rental payments as the tenant’s circumstances permit; and (v) the eviction would likely render the individual homeless or force the individual to move into and live in close quarters or shared living space.
Effect of the CDC Order The CDC Order prevents landlords from evicting tenants for the non-payment of rent or similar housing-related payments that have sent their landlord a CDC Declaration. The CDC Order does not relieve tenants of the obligation to pay rent or other charges owed under their leases and does not preclude a landlord from charging late fees, penalties, or interest for missed payments.
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at