"My Bad, I Thought It Was in Good Faith" is Not Good Enough - Contractor Ordered to Pay Prompt Payment Penalties
February 23, 2016 —
David A. Harris & Jesse M. Sullivan – Haight Brown & Bonesteel LLPRetention clauses are almost always included in California construction contracts and permit an Owner to withhold a portion of what is owed to the General Contractor as security to ensure the proper completion of the work. General Contractors pass the withholding of retention down to the subcontractors. Thus, if the subcontractor fails to complete its work, or fails to correct deficiencies, the Owner/General Contractor can use the retention to pay the costs of completing or correcting the subcontractor’s work.
The contractor must release any retention it receives from the owner within ten days unless a “good faith dispute exists between the direct contractor and the subcontractor.” (Civil Code section 8814.) Where there is a good faith dispute, the contractor “may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.” (Civil Code section 8814(c).) If the contractor wrongfully withholds retention, it must not only pay the retention but must also pay the subcontractor “a penalty of 2 percent per month on the amount wrongfully withheld.” The contractor must also pay the subcontractor’s costs and reasonable attorney’s fees incurred in collecting the retention. (Civil Code section 8818.)
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Design-Assist Collaboration/Follow-up Post
March 16, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCShortly after posting the blog article “Design-Assist an Ambiguous Term Causing Conflict in the Construction Industry,” I received an email from Brian Perlberg, the Executive Director and Senior Counsel for ConsensusDocs. He brought two ConsensusDocs forms to my attention: ConsensusDocs 541 Design Assist Addendum and ConsensusDocs 300 Integrated Form of Agreement (IFOA). In the ConsensusDocs model of “design-assist,” the lead design professional retains design responsibility but benefits from input and consultation from the construction team during design development. By contrast, in the design-build project delivery method, the constructor assumes design responsibility and liability for either the entire project design (design-build) or just a component of the design (delegated design).
The ConsensusDocs 541 document goal is to provide “accurate information concerning program, quality, cost, constructability and schedule from all parties.” It provides a range of standard and optimal services during design development that essentially shifts the curve of selecting the construction manager (CM) and most importantly, special trade contractors, to much earlier in the process, perhaps as soon as the owner’s program is developed. This opens a world of possibilities for the design and construction team to collaborate early and often. The design professional, however, does not abdicate its design responsibility or authority in this process. The ultimate goal is to end the all-too-common wasteful cycle of design and redesign that is common in construction projects.[1]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Attorneys Fees Under California’s Prompt Payment Statutes. Contractor’s “Win” Fails the Sniff Test
October 02, 2015 —
Roger Hughes – California Construction Law BlogThis past month, the California Court of Appeals for the Third District, in James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., Case No. C072169 (August 27, 2015), handed down a decision in a construction contract battle that has raged since 2007. And, once again, the winner is . . . in the words of Justice Andrea Lynn Hoch who authored the opinion . . . . “no prevailing party in [the] case” and hence “no prevailing party attorney’s fees [ ] awarded.”
Background
In Harris, subcontractor James L. Harris Painting & Decorating, Inc. (“Harris”) sued general contractor West Bay Builders, Inc. (“West Bay”) for extra work performed on a school construction project in Stockton, California. Among its claims, Harris asserted that West Bay was liable under California’s prompt payment statutes for failure to timely pay Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Homeowners Sued for Failing to Disclose Defects
December 30, 2013 —
CDJ STAFFThe Madison-St. Clair Record reports that a Wisconsin homeowner has sued the former owners of her home, alleging that they failed to disclose a defect. According to the lawsuit, David and Doris Stephens informed Jennifer Davies that a basement window well had previously leaked, but that the problem had been fixed and not recurred in three years. Ms. Davies had problems with the leaks after she moved in.
And while the window was the only defect the Stepehenses reported, Ms. Davies found problems with the home’s heating and air conditioning as well. Though she paid only $112,000 for the home, Ms. Davies is suing for $400,000 for the repairs, loss of property value, and the court fees.
Read the court decisionRead the full story...Reprinted courtesy of
Minimum Wage on Federal Construction Projects is $10.10
November 26, 2014 —
Craig Martin – Construction Contractor AdvisorThe Department of Labor issued its final regulations to implement President Obama’s Executive Order raising the minimum wage to $10.10 per hour for workers on federal construction projects. The new minimum wage will not be effective until January 1, 2015, and will apply to most workers and most federal projects.
Covered Contracts
Executive Order 13658 applies to four major categories of contractual agreements:
- procurement contracts for construction covered by the Davis-Bacon Act (DBA) that exceed $2,000;
- service contracts covered by the Service Contract Act (SCA) that exceed $2,500;
- concessions contracts, including any concessions contract excluded from the SCA by the Department of Labor’s regulations at 29 CFR 4.133(b); and
- contracts in connection with Federal property or lands and related to offering services for Federal employees, their dependents, or the general public.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Negligence Per Se Claim Based Upon Failure to Pay Benefits Fails
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit affirmed the district court's issuance of the insurer's motion for summary judgment, thereby rejecting the insureds' negligence per se claim for failure to pay benefits. Braun-Salinas v. Am Family Ins. Group, 2016 U.S. App. LEXIS 19555 (9th Cir. Oct. 28, 2016).
The insureds argued that Oregon recognized a negligence per se claim based on an insurer's failure to pay benefits in violation of the statutory standard under state law. Oregon appellate courts, however, only allowed a negligence per se claim only where a negligence claim otherwise existed. The Oregon courts had previously rejected a statutory theory, holding that a violation of the statute did not give rise to a tort action.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
What is a Personal Injury?
September 03, 2019 —
Bremer Whyte Brown & O'Meara LLPEssentially, a personal injury is when an individual is hurt during an accident. Whether driving on the road, walking down the street, or sitting in a chair, accidents happen. When there is an accident, medical treatment may be necessary. Individuals who sustain injuries usually seek compensation for their medical treatment and pain and suffering in the form of a personal injury lawsuit.
Personal injury lawsuits can result from a variety of claims including negligence, strict liability, or intentional torts. Yet, for the most part, personal injury lawsuits tend to arise from a claim of negligence. The individual or entity injured in the accident, “Plaintiff”, files a lawsuit against the individual or entity, “Defendant” who allegedly caused harm. Personal injury lawsuits resulting from claims of negligence tend to have two main components: liability and damages. Yet, in order to prevail in a suit for negligence, a Plaintiff must demonstrate the following: (1) a legal duty to use due care, (2) a breach of that duty, (3) a reasonably close, causal connection between that breach and Plaintiff’s resulting injury, and (4) actual loss or damage to Plaintiff. Wylie v. Gresch (1987) 191 Cal.App.3d 412.
First, a finding of negligence rests upon a determination that the actor has failed to perform a duty of care owed to the injured party. Ronald S. v. County of San Diego (1993) 16 Cal.App.4th 887. This means that an individual or entity must act reasonably to avoid injuring others. When an injury occurs, a Plaintiff will generally argue that an individual or entity breached a duty owed to them.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP