Triple Points to the English Court of Appeal for Clarifying the Law on LDs
July 01, 2019 —
Vincent C. Zabielski & Julia Kalinina Belcher - Gravel2GavelCan an employer recover liquidated damages (LDs) from a contractor if the contract terminates before the contractor completes the work?
Surprisingly, heretofore, English law provided no clear answer to this seemingly straightforward question, and inconsistent case law over the past century has left a trail of confusion. Given the widespread use of English law in international construction contracts, this uncertainty had gone on far too long.
The good news is that drafters of construction contracts throughout the world can now have a well-deserved good night’s sleep courtesy of the English Court of Appeal’s March 2019 decision in Triple Point Technology, Inc. v PTT Public Company Ltd [2019] EWCA Civ 230.
The Triple Point case concerned the delayed supply by Triple Point (the “Contractor”) of a new software system to employer PTT. The contract provided for payments upon achievement of milestones, however order forms incorporated into the contract set out the calendar dates on which fixed amounts were payable by PTT, resulting in an apparently contradictory requirements on when payment was due. Triple Point achieved completion (149 days late) of a portion of the work milestones, and were paid for that work. Triple Point then sought payment for the work which was not yet completed, relying on the calendar dates in the order forms rather than achievement of milestone payments. Things got progressively worse as PTT refused payment, Triple Point suspended the work for PTT’s failure to pay, PTT terminated the contract and then appointed a new contractor to complete the work.
Reprinted courtesy of
Vincent C. Zabielski, Pillsbury and
Julia Kalinina Belcher, Pillsbury
Mr. Zabielski may be contacted at vincent.zabielski@pillsburylaw.com
Ms. Belcher may be contacted at julia.belcher@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Green Investigations Are Here: U.S. Department of Justice Turns Towards Environmental Enforcement Actions, Deprioritizes Compliance Assistance
January 10, 2022 —
Karen C. Bennett, R. Morgan Salisbury, Sean P. Shecter & Rose Quam-Wickham - Lewis BrisboisWashington, D.C. (January 4, 2022) - Two high-ranking Department of Justice (DOJ) officials announced that the Biden Administration is prioritizing environmental regulatory enforcement over compliance assistance. Todd Kim, Assistant Attorney General for the DOJ’s Environment and Natural Resources Division (ENRD), and Deborah Harris of the DOJ’s Environmental Crimes Section, indicated in mid-December 2021 that companies and individuals should expect more “vigorous enforcement,” with an emphasis on criminal enforcement. This new policy is in contrast to the Environmental Protection Agency’s (EPA) Office of Enforcement and Compliance Assurance (OECA)'s previous emphasis on compliance and pollution mitigation instead of enforcement actions under the prior administration.
DOJ’s new policy of promoting enforcement actions is consistent with the Biden Administration’s overall efforts to prioritize environmental justice. In April 2021, as explained in a previous Lewis Brisbois Client Alert, OECA released two memoranda directing enforcement teams to consider a variety of tools to resolve enforcement actions, including increased inspections, restitution, and reparation for victims of environmental crimes and overstepping state regulators where necessary.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois,
R. Morgan Salisbury, Lewis Brisbois,
Sean P. Shecter, Lewis Brisbois and
Rose Quam-Wickham, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Mr. Salisbury may be contacted at Morgan.Salisbury@lewisbrisbois.com
Mr. Shecter may be contacted at Sean.Shecter@lewisbrisbois.com
Ms. Quam-Wickham may be contacted at Rose.QuamWickham@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Supreme Court Holds Fire Damage Resulted from Single Occurrence
November 21, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Secura Ins. v. Lyme St. Croix Forest Co., LLC 2018 WI 103 (Oct. 30, 2018), the Wisconsin Supreme Court had occasion to consider whether a forest fire that caused damage to several homes and properties should be considered a single or multiple occurrences.
Secura insured Lyme St. Croix Forest Company under a general liability policy. Of relevance was the policy’s $500,000 sublimit of coverage for property damage due to fire arising from logging or lumbering operations, subject to a $2 million general policy aggregate limit. Lyme St. Croix sought coverage under the policy for a fire that resulted from its logging equipment. The fire lasted for three days, burning nearly 7,500 acres and causing damage to numerous homes and businesses.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Pancakes Decision Survives Challenge Before Hawaii Appellate Court
March 12, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn 1997, the Hawaii Intermediate Court of Appeals (ICA) decided Pancakes of Hawaii, Inc. v. Pomare Prop. Corp., 85 Haw. 286, 944 P.2d 83 (Haw. Ct. App. 1997). Although not an insurance coverage case, Pancakes addressed the duty to defend in terms of a contractual indemnity obligation. Under challenge in a recent appeal before the ICA, the Court reaffirmed the holding in Pancakes. Arthur v. State of Hawaii, Dept. of Hawaiian Home Lands, 2015 Haw. App. LEXIS 109 (Haw. Ct. App. Feb. 27, 2015).
The decision is long with detailed facts complicated and many indemnities running in favor of various parties. This post focuses on the decision's discussion of Pancakes.
A resident, Mona Arthur, of the Kalawahine Streamside Housing Development, was killed when she apparently slipped and fell from a hillside adjacent to the project. She was on the hillside tending to her garden there. At the bottom of the hill was a two foot fence in front of a drainage ditch, where Mona allegedly hit her head.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Leftover Equipment and Materials When a Contractor Is Abruptly Terminated
November 06, 2023 —
Brian Perlberg - ConsensusDocsTermination for cause is costly and adversarial and has been covered in this
article. But can a terminating party use equipment and tools left behind on the worksite (i.e., a crane)? The answer depends on what is in your contract.
Under
ConsensusDocs, a constructor must give its permission to use any equipment or supplies left at the worksite, such as a crane.
[i] Moreover, the owner must indemnify the constructor for using their equipment. This makes sense because even if a constructor were appropriately terminated for cause, using their equipment and materials they no longer possess or control unfairly creates additional liability exposure. At a minimum, the owner should take on the risk of using the equipment and materials since they benefit from such use.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Perlberg, ConsensusDocs CoalitionMr. Perlberg may be contacted at
bperlberg@ConsensusDocs.org
Florida Governor Signs Construction Defect Amendments into Law
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Jeffrey Gilbert and Anaysa Gallardo Stutzman of Cozen O’Connor, Rick Scott, governor of Florida, signed HB 87 into law, which “amends the notice and opportunity to cure provisions of Chapter 558, Florida’s Construction Defect Statute.” The amendments go into effect October first.
HB 87 requires “property owners to provide concrete details of the alleged defects.” Gilbert and Stutzman claimed, “Overall, these amendments seek to further the intended public policy purpose of Chapter 558, which is to provide an alternative dispute resolution mechanism and result in fewer lawsuits and lower litigation costs incurred by parties involved in construction defect matters.”
Read the court decisionRead the full story...Reprinted courtesy of
Performance Bond Surety Takeover – Using Terminated Contractor To Complete The Work
January 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work? Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under? The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).
In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings. The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form. During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:
4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or
4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Strict Liability or Negligence? The Proper Legal Standard for Inverse Condemnation caused by Water Damage to Property
March 30, 2016 —
Charles S. Krolikowski – Newmeyer & Dillion, LLPFiling a lawsuit against a government entity can be a daunting task given the complexities of tort claims requirements and governmental immunities. A recent decision by the Court of Appeal in Pacific Shores Property Owners Association v. Department of Fish & Wildlife, Case No. C07020 (Jan. 20, 2016), provided welcome clarification as to the proper legal standard for an inverse condemnation action based upon activities of a government entity which cause water damage to private property.
Read the court decisionRead the full story...Reprinted courtesy of
Charles S. Krolikowski, Newmeyer & Dillion, LLPMr. Krolikowski may be contacted at