Challenging Enforceability of Liquidated Damages (In Federal Construction Context)
March 11, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent summary judgment opinion from the Armed Services Board of Contract Appeals (ASBCA), Appeals Of – BCI Construction USA, Inc.,ASBCA No. 6257, 2024 WL 773324 (2024), contains a worthy discussion regarding a contractor’s challenge to the government’s assessment of liquidated damages, specifically the enforceability of the liquidated damages rate. Although this challenge is in the federal context, this discussion would be more expansive and apply outside of the federal context.
When dealing with the enforceability of a liquidated damages, the ASBCA “examines whether the liquidated damages amount ‘is extravagant, or disproportionate to the amount of property loss, as to show that compensation was not the object aimed at or as to imply fraud, mistake, circumvention or oppression.” Appeals of – BCI Construction USA, Inc. (citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Home Building Up in Kansas City
November 20, 2013 —
CDJ STAFFIt’s been a good year for home builders in Kansas City, Missouri. In fact, it’s the best year since 2007. The total number of home permits issued through October exceeds the number issued in 2012 by 164, having reached 3,463. Sara Corless, executive vice president of the Builders Association, focused more on the growth, though she noted that some builders were hoping the year’s total would exceed 4,000, which she described as “a psychological victory at a minimum.”
The Kansas City metropolitan area lead the state in the number of building permits issued.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado’s Workers’ Compensation Act and the Construction Industry
June 20, 2022 —
Jordan Kaplan - Colorado Construction LitigationIn general, issues relating to employment law occur in all industries. However, some issues are more likely to be raised in certain employment contexts. For example, office work environments tend to give rise to harassment and discrimination claims while wage and hour disputes and workplace safety claims are common in the oil and gas industry. In the construction industry, employers must be especially cognizant of discrimination and harassment claims, employee misclassification claims, workplace safety issues, and wage and hour claims. In the context of workers’ compensation claims, construction projects often create unusual situations due to the contractual relationships between the parties.
Even relatively simple construction of a single-family residence involves several levels of contracting, including between the owner and general contractor, between the owner or general contractor and design team, between the general contractor and subcontractors, and between the prime subcontractors and lower tiered sub-subcontractors. In most circumstances, this would not be an issue. However, when an injured worker makes a workers’ compensation claim, the contractual relationships among the various entities involved in a project can have a significant impact on which party or parties could be liable for the injury.
Read the court decisionRead the full story...Reprinted courtesy of
Jordan Kaplan, Higgins, Hopkins, McLain & Roswell, LLCMr. Kaplan may be contacted at
kaplan@hhmrlaw.com
Pay Loss Provision Does Not Preclude Assignment of Post-Loss Claim
July 30, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that a policy's loss payment provision did not bar a post-loss assignment. One Call Prop. Servs. v. Sec. First Ins. Co., 2015 Fl. App. LEXIS 7643 (Fla. Ct. App. May 20, 2015).
After One Cell performed emergency water removal for the insured, the insured assigned his rights to policy proceeds as payment. One Cell alleged that Security First refused to reimburse the insured adequately for the services provided. One Cell filed suit, and Security First moved to dismiss. The trial court granted the motion based upon the policy's non-assignment provision.
One Cell appealed. One Cell argued post-loss assignments were valid under Florida law even when the policy contained an anti-assignment provision, and the right to payment accrued on the date of the loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Alabama Supreme Court Finds No Coverage for Construction Defect to Contractor's own Product
October 21, 2013 —
Tred Eyerly — Insurance Law HawaiiThe Alabama Supreme Court followed prior precedent and found that the contractor's faulty workmanship causing damage to his own product did not arise from an occurrence. Owners Ins. Co. v. Jim Carr Homebuilder, LLC, 2013 Ala. LEXIS 122 (Ala. Sept. 20, 2013).
The plaintiffs contracted with Carr to construct a new home. After completion of the home and taking occupancy, the plaintiffs noted several problems with the house related to water leaking through the roof, walls and floors, resulting in water damage to various areas of the house. The plaintiffs sued Carr and the case eventually went to arbitration. The arbitrator entered an award in favor of plaintiffs for $600,000.
Owners filed an action against Carr for a declaratory judgment seeking to establish there was no coverage because the property damage did not arise from an occurrence. The trial court granted summary judgment to Carr.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Traub Lieberman Partner Greg Pennington Wins Summary Judgment in Favor of Property Owner
September 12, 2022 —
Gregory S. Pennington - Traub LiebermanIn a case brought before the Superior Court of New Jersey, Traub Lieberman Partner Greg Pennington won a motion for summary judgment in favor of their client, the owner of a residential property (“Property Owner”) in Atlantic City, New Jersey. The Property Owner had retained a Construction Company (“Construction Company” or “Contractor”) to perform renovations to the residence, which included building a new staircase. The Plaintiff alleged that while walking down a set of temporary wooden steps on the property, the third step broke, which caused him to fall and resulted in the alleged injuries. The Plaintiff brought suit against the Property Owner and Construction Company for personal injuries as a result of the alleged fall.
In the contract between the Property Owner and the Construction Company, it is stated that “[the Contractor] shall be solely responsible for all construction methods and materials and for coordinating all portions of the Work….The Contractor warrants to [the Property Owner] that all materials and equipment incorporated are new and that all work shall be of good quality and free of defects or faults.” The contract continues to state that the Construction Company shall indemnify and hold harmless the Property Owner against all claims, which includes damages, losses, expenses, legal fees and other costs that might arise from the Construction Company’s performance of the work under the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory S. Pennington, Traub LiebermanMr. Pennington may be contacted at
gpennington@tlsslaw.com
Court Voids Settlement Agreement in Construction Defect Case
September 01, 2011 —
CDJ STAFFA U.S. District Court Judge in Florida has ruled in favor of a company that sought to void a settlement agreement. The case, Water v. HDR Engineering, involved claims of construction defects at Florida’s C.W. Bill Young Regional Reservoir. The Tampa Bay Water Authority attributed these to both HDR Engineering’s design and Bernard Construction Company which had built the embankment. Bernard Construction filed a complaint against their subcontractor, McDonald.
Tampa Bay Water settled with Bernard Construction and McDonald, in an agreement that set a minimum and maximum settlement, but also would “prohibit Barnard and McDonald from presenting any evidence on several claims and positions of TBW, to require Barnard to call certain witnesses at trial, to preclude Barnard and McDonald from calling other witnesses, and to restrict the filing of trial and post-trial motions.” HDR Engineering moved to void the agreement as collusive.
The judge that the agreement¬? contained “133 paragraphs of ‘Agreed Facts’ that the parties stipulated would survive any order declaring the Settlement Agreement void or unenforceable.” He characterized these as stipulating “that Barnard neither caused nor contributed to TBW’s damages.” HDR motioned that a summary judgment be given to Barnard Engineering.
The court found that “the evidence identified by TBW is patently insufficient to survive summary judgment.” Further, TBW’s expert initially held Barnard responsible for “lenses, pockets, streaks and layers within the embankment,” but then later withdrew this assigning the responsibility to HDR. Further, the court notes that, “TBW’s arguments that lenses, pockets, streaks, and layers in the soil wedge caused or contributed to its damages and that Barnard is liable for those damages have been foreclosed by the Agreed Facts.”
As TBW failed to provide sufficient evidence to withstand summary judgment, the court granted summary judgment, mooted the claim against McDonald, and terminated the agreement between TBW and the other parties.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Rooftop Owners Sue Cubs Consultant for Alleged False Statements
January 24, 2014 —
Beverley BevenFlorez-CDJ STAFFA disagreement over signage potentially blocking rooftop owner’s views has stalled Wrigley Field’s proposed $300 million renovation, reported the Chicago Tribune. However, a recently lawsuit filed between the two entities regarded allegedly false statements made by Marc Ganic, a Chicago sports business consultant, published in the Chicago Sun-Times: “In the story, Ganis is quoted as saying the rooftop clubs were ‘stealing’ the Cubs product for their own profit,” according to the Chicago Tribune.
The rooftop owners claimed in the suit that “they have a contractual arrangement with the team that allows them to sell tickets to people who want bird’s-eye views of the game.” The Chicago Tribune attempted to contact Ganis for comment, but he “did not return several messages.”
The rooftop owners and the Cubs entered into a “20-year agreement in 2004 in which the rooftop owners pay the Cubs 17 percent of the team's yearly profits in exchange for unobstructed views into the ballpark,” according to ESPN. “The Cubs dispute that notion, however, contending the unobstructed views were guaranteed through the landmarking of the bleachers not with the agreement they have with the rooftop owners.”
Business president Crane Kenney explained to ESPN that the city council amended the landmarking rule for the field: “[The council has] now recognized the outfield is not a historic feature. And above a 10-foot level we can have signage. That was the big win last summer, among many. That's what the rooftops would contest.”
According to ESPN the Cubs will not start the renovation project until they have an agreement with the rooftop owners “that includes a guarantee not to sue the Cubs for breach of contract, which would delay construction.”
Read the full story at the Chicago Tribune...
Read the full story at ESPN... Read the court decisionRead the full story...Reprinted courtesy of