Breach Of Duty of Good Faith And Fair Dealing Packaged With Contract Disputes Act Claim
March 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting opinion on a motion to dismiss came out of the United States Court of Federal Claims dealing with the claim that the government breached its duty of good faith and fair dealing in administering the prime contract. The contractor’s argument was that the government breached its duty of good faith and fair dealing by denying the contractor’s claim under the Contract Disputes Act (CDA). This was a creative claim and argument that deserves consideration because it tied in the contracting officer’s denial of the CDA claim for additional money with a breach of the duty of good faith and fair dealing.
In this case, Aries Construction Corp. v. U.S., 2023 WL 2146598 (Fed. Cl. 2023), a prime contractor was hired for a water pipeline construction project. The contractor encountered unexpected difficult site conditions that required additional equipment and labor. The contractor informed the contracting officer and alleged it was instructed to proceed with the additional equipment and labor. The contractor submitted a claim under the CDA but the contracting officer denied the claim. The contractor pursued the claim in the United States Court of Federal Claims arguing the government breached the contract and, of interest, breached its duty of good faith and fair dealing.
The government moved to dismiss the breach of good faith and fair dealing claim arguing that besides failing to state a cause of action the Court of Federal Claims had no jurisdiction because the breach of the duty of good faith and fair dealing was not properly presented to the contracting officer under the CDA. The Court of Federal Claims denied the government’s motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Blackouts Require a New Look at Backup Power
April 06, 2020 —
John McBride - Construction ExecutiveRecent blackouts on both East and West coasts are causing commercial property owners to reassess their need for backup power. The likelihood of more-frequent blackouts means backup power must evolve from ensuring the safe exit of office workers to enabling core business functions to continue uninterrupted. That’s a major shift in preparedness that construction executives should consider in future planning.
In New York City on July 13, 2019, a Con Edison blackout left 72,000 customers in Manhattan and Queens without power primarily because of a flawed connection at an electrical substation. Eight days later, a second Con Edison blackout left more than 50,000 customers, mostly in Brooklyn, without power due to high usage during a heat wave. These events occurred even though, as Con Edison stated, the New York City grid is one of the most complex and technologically advanced in the world and contains multiple layers of redundancy.
In northern and central California in late October, 2019, intentional blackouts were implemented by Pacific Gas and Electric (PG&E) on a massive scale in response to out-of-control wildfires. “Never before in California history have more than 2 million people gone five days without electrical power because of the intentional safety policy of a utility,” reported the Los Angeles Times. It was the second massive blackout in California in two weeks, after PG&E had earlier shut off power to almost 2 million people in rolling blackouts.
The blackouts on both coasts are remarkable not only for their breadth but for the range of causes—from limiting wildfires sparked in part by faulty, above-ground, power lines to a flawed connection at a substation to overuse during a heat wave. The conditions creating those causes are not likely to subside, and Con Edison warned this summer of more service outages to come. In California, The Washington Post writes, “blackouts are redefining the prosperous state.”
Reprinted courtesy of
John McBride, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Tiny Houses Big With U.S. Owners Seeking Economic Freedom
July 16, 2014 —
Nina Glinski – BloombergDoug Immel recently completed his custom-built dream home, sparing no expense on details like cherry-wood floors, cathedral ceilings and stained-glass windows -- in just 164 square feet of living space including a loft.
The 57-year-old schoolteacher’s tiny house near Providence, Rhode Island, cost $28,000 -- a seventh of the median price of single-family residences in his state.
“I wanted to have an edge against career vagaries,” said Immel, a former real estate appraiser. A dwelling with minimal financial burden “gives you a little attitude.” He invests the money he would have spent on a mortgage and related costs in a mutual fund, halving his retirement horizon to 10 years and maybe even as soon as three. “I am infinitely happier.”
Dramatic downsizing is gaining interest among Americans, gauging by increased sales of plans and ready-made homes and growing audiences for websites related to the niche. A+E Networks Corp. will air, beginning today, “Tiny House Nation” a series on FYI that “celebrates the exploding movement.”
Read the court decisionRead the full story...Reprinted courtesy of
Nina Glinski, BloombergMs. Glinski may be contacted at
nglinski@bloomberg.net
California Contractor License Bonds to Increase in 2016
December 02, 2015 —
Garret Murai – California Construction Law BlogThe post, which originally appeared on
The Surety Bond Insider, was written by Jon Gottschalk, a member of the SuretyBonds.com Educational Outreach team. on
SuretyBonds.com helps contractors fulfill their bonding requirements.
The Contractors State License Board (CSLB) is requiring all California contractors to purchase a $15,000 bond by January 1, 2016— a $2,500 increase from the $12,500 amount that was previously required. The additional $2,500 was previously accounted for by an additional requirement to obtain a contractor’s license. Those applying for the license had to post the $12,500 surety bond and proof of financial solvency in the amount of $2,500. Essentially, contractors were required to show that their current assets were greater than their liabilities by no less than $2,500. By increasing the bond amount to include that additional $2,500, the CSLB has removed the burden of proving financial solvency from those who wish to obtain their license.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Will Colorado Pass a Construction Defect Reform Bill in 2016?
December 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to blogger Jill Jamieson-Nichols of the Colorado Real Estate Journal, another construction defects bill may be debated in Colorado next year. Representative Dan Pabon told Jamieson-Nichols that “the answer lies in ‘thinking about the insurance piece’ so condominium developers can afford insurance against litigation that might arise.” She also stated that the city of Denver is considering ways to increase funding to increase affordable housing in the area.
Read the court decisionRead the full story...Reprinted courtesy of
New Orleans Reviews System After Storm Swamps Pumps
August 17, 2017 —
Pam Radtke Russell - Engineering News-RecordThe city of New Orleans will hire an independent team of engineers to evaluate the problems that led to severe flooding following an Aug. 5 rainfall of up to 10 in. The decision followed the revelation that 16 of the city’s pumps were not working, despite claims the system was at capacity. Further, the power system that operates those pumps was severely crippled.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
February 16, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Oregon Bridge Closed to Inspect for Defects
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Oregonian, the Morrison Bridge in Multnomah county, Oregon will be closed Sunday, February 23rd “so county crews can inspect the decking that has caused problems since it was installed” in 2012. The “southernmost eastbound lane has been closed for weeks while crews conducted inspections.”
The defects appeared “almost immediately after the project” was completed, reported The Oregonian. Drivers have “dealt with a bumpy, noisy ride as the loose decking panels flopped beneath them.”
Multnomah county has sued “Conway Construction, the company the installed the decking, as well as Strongwell Corp., the company that supplied Conway with the decking materials, and Zellcomp, the company that made the decking materials, to determine who should foot the bill for extensive repairs or outright replacement of the decking.”
Read the court decisionRead the full story...Reprinted courtesy of