Garret Murai – California Construction Law BlogCalifornia is one of a handful of states (12 to be exact) which have statutory mandated waiver and release forms for construction projects.
So here’s what you need to know before you sign one (or two, or three).
What are California’s statutory waiver and release forms?
California has four statutory waiver and release forms for construction projects.
Which form applies depends on two things: (1) whether it is for progress payments or final payment; and (2) whether it is provided before or after you have been paid.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
You Don’t Have To Be a Consumer to Assert a FDUTPA Claim
February 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA few years ago, the Fourth District Court of Florida rendered an opinion in
Caribbean Cruise Line, Inc. v. Better Business Bureau of Palm Beach County, Inc., 169 So.3d 164 (Fla. 4th DCA 2015) regarding
Florida’s Deceptive and Unfair Trade Practices Act (referred as to “FDUTPA”) (Florida Statute s. 501.201et seq.).
This case held that a party can assert a FDUTPA claim even though the party is NOT a consumer. The party still has to prove there was an injury to consumers in filing such claim, but again, the party can bring the claim even though it is NOT a consumer. Caribbean Cruise Line, 169 So.3d at 169 (“[W]hile the claimant would have to prove that there was an injury or detriment to consumers in order to satisfy all of the elements of a FDUTPA claim, the claimant does not have to be a consumer to bring the claim.”).
See also Cemex Construction Materials Florida, LLC v. Armstrong World Industries, Inc., 2018 WL 905752, *15 (M.D.Fla 2018) (relying on
Caribbean Cruise Line to find that even though the plaintiff does not need to be a consumer, the plaintiff still must prove an injury to consumers to satisfy elements of a FDUTPA claim).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Be Strategic When Suing a Manufacturer Under a Warranty with an Arbitration Provision
October 02, 2023 —
David Adelstein - Florida Construction Legal UpdatesI’ve said this before, and I’ll say it again: arbitration is a creature of contract. If you don’t want to arbitrate, don’t agree to an arbitration provision as the means to resolve your dispute. Now, with that said, there are times you may not have a choice. An arbitration provision in a warranty from a manufacturer of a product is an example. If you are procuring the product, you are agreeing to the terms of the express warranty. Manufacturers are not negotiating their product warranty on a case-by-case basis considering they are not typically the ones selling the product directly to the end user. This does not mean that is a bad thing. It just means if you elect to sue the manufacturer directly for an alleged product defect or under the terms of the warranty, you should read the warranty and consider the strategic aspect that suing the manufacturer will have on your case.
In SICIS North America, Inc. v Sadie’s Hideaway, LLC, 48 Fla.L.Weekly D1581c (Fla. 1st DCA 2023), an owner elected to sue a tile manufacturer, a general contractor, the architect, and a window and door company. One of the arguments the owner raised was that exterior tiles installed were defective. The tiles were procured by the general contractor. The owner sued the general contractor under various theories and sued the tile manufacturer for breaches of warranty and negligence. The general contractor asserted a crossclaim for indemnification against the tile manufacturer. The tile manufacturer moved to compel the owner’s claim and the general contractor’s crossclaim to arbitration since there was an arbitration provision in the warranty documents and the general contractor’s indemnification claim arose from that transaction. The trial court denied the motion to compel arbitration. On appeal, the appellate court reversed:
First, because [the owner] was suing [the tile manufacturer] based upon the written warranty, it was bound by the arbitration provision contained in [the general contractor’s] agreement with [the tile manufacturer]. As the Florida Supreme Court has explained, “[W]hen a plaintiff sues under a contract to which the plaintiff is not a party . . . we will ordinarily enforce an arbitration clause contained in that contract, absent some other valid defense. . . .” . [The owner] had no valid defense against arbitration, a fact which it apparently realized when it voluntarily dismissed its express warranty claim after the notice of appeal and initial brief were filed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Good News on Prices for Some Construction Materials
June 28, 2021 —
ABC - Construction ExecutiveThe elevated price of softwood lumber, a major talking point during much of the pandemic, appears to have peaked in early May at more than $1,700 per thousand board feet. As of June 23, the price has fallen below $900 per board feet, down about 49% in less than two months.
That’s still an unusually lofty price by historic standards—prices remain almost twice as high as in February 2020—but the trend is very much in the right direction. Builders that had been hoarding lumber have now begun to sell from their own inventory, other builders have delayed lumber purchases in anticipation of lower prices and sawmill operators have been adding shifts, as well as expanding capacity, all of which puts downward pressure on prices.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
You Cannot Always Contract Your Way Out of a Problem (The Case for Dispute Resolution in Mega and Large Complex Construction Projects)
September 16, 2024 —
Lisa D. Love - The Dispute ResolverMost experienced commercial transaction and construction attorneys strive to negotiate a concisely written and well-drafted contract that addresses all scenarios and issues that creative and highly contemplative professionals can conjure. Although contracts are extremely important in construction projects, “you can’t generally contract your way out of a problem,” states Michael Loulakis, a founder of Capital Project Strategies, LLC and a nationally recognized expert on project delivery systems in complex public sector design-build projects and public-private partnership programs. Loulakis adds, “the contract certainly matters. But particularly when the losses are big, litigators prosecuting the contractors often find effective ways to argue that facts and circumstances trump the contract.” However, “the difference between the best construction projects and the worst construction projects is not the written words of the contracts but how the parties have committed to engage collaboratively and with trust to complete the project,” notes Robynn Thaxton, an attorney and consultant with Thaxton Parkinson PLLC and Progressive Design-Build Consulting, LLC and one of the leading experts in construction law and alternative procurement on a national basis.[i]
In large, complex construction projects, the need for parties to collaboratively resolve disputes is highlighted by the judicial acceptance of the “Doctrine of the Contextual Contract”[ii] to interpret construction contracts. “As construction’s increasing technological and managerial complexity came to be recognized, some common law courts began turning away from strict interpretation of language within the four corners of a contract and moving toward recognizing in the enforcement of contracts the construction industry’s own experience, customs, practices and implied conditions and duties and the factual context underlying the contract. Courts [began the journey] along the road from ‘text’ to ‘context.’”[iii] Thus, the precise wording of the contract has become less important and industry practices and other conditions provide insight for resolving disputes. Consequently, despite the specific language of any construction contract and the clear allocation of responsibilities and risks, early dispute evaluation and resolution are critical to a successful project.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Los Angeles Could Be Devastated by the Next Big Earthquake
October 15, 2013 —
CDJ STAFFA group of scientists have made a list of about 1,500 concrete buildings in Los Angeles which could potentially collapse in an earthquake. They have offered to make the list available to Los Angeles officials, although the city has yet to take them up on the offer. In response, a group of Times reporters combed through records to identify which buildings were of the sort most likely to collapse in an earthquake. The group found more than 1,000 concrete buildings built before 1976 when Los Angeles increased the requirements for steel rebar.
Experts estimate that in a major earthquake, five percent of these buildings could collapse, which for Los Angeles would mean about 50 buildings. Many of these buildings could be seismically retrofitted, but the article notes that a retrofit starts with a $100,000 structural study. Carol Schatz of the Central City Association notes that the cost of retrofitting “would be greater than the value of the building.”
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (10/23/24) – Construction Backlog Rebounds, Real Estate Sustainability Grows, and Split Incentive Gap Remains Building Decarbonizing Barrier
November 18, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, construction output decreased, office utilization unchanged, September apartment starts fell 15% from a year ago as developers pulled permits, and more!
- Developers pulled permits for a seasonally adjusted rate of 398,000 apartments in buildings with five units or more, a 17.4% YOY drop and a 10.8% decrease compared to August 2024. (Leslie Shaver, Multifamily Dive)
- Construction input prices decreased 0.9% in September due to dips in two of three energy subcategories, reflecting the trend of overall material price stabilization over the past 12 months. (Sebastian Obando, Construction Dive)
- Thanks in part to the Federal Reserve’s lowering of the interest rate, construction backlog rebounded in September after slumping at the end of the summer. (Joe Bousquin, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Negligence Per Se Claim Based Upon Failure to Pay Benefits Fails
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit affirmed the district court's issuance of the insurer's motion for summary judgment, thereby rejecting the insureds' negligence per se claim for failure to pay benefits. Braun-Salinas v. Am Family Ins. Group, 2016 U.S. App. LEXIS 19555 (9th Cir. Oct. 28, 2016).
The insureds argued that Oregon recognized a negligence per se claim based on an insurer's failure to pay benefits in violation of the statutory standard under state law. Oregon appellate courts, however, only allowed a negligence per se claim only where a negligence claim otherwise existed. The Oregon courts had previously rejected a statutory theory, holding that a violation of the statute did not give rise to a tort action.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at