Proving & Defending Lost Profit Damages
June 09, 2016 —
David Adelstein – Florida Construction Legal UpdatesI have written numerous articles regarding the challenge in proving
lost profit damages. Yes,
lost profits are a form of damages in business disputes, but they are a form of damages that are subject to a certain degree of
conjecture and speculation. For this reason,
lost profit evidence is oftentimes precluded from being presented at trial or lost profit damages are reversed on appeal. This is why it is imperative to ensure i’s are dotted and t’s are crossed when it comes to proving lost profit damages. It is also imperative, when defending a lost profit claim, to put on evidence and establish the speculative nature of the lost profit damages.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
ASHRAE Approves Groundbreaking Standard to Reduce the Risk of Disease Transmission in Indoor Spaces
July 10, 2023 —
ASHRAEATLANTA, June 27, 2023 (GLOBE NEWSWIRE) -- ASHRAE announced the approval for publication of its highly anticipated standard to reduce the risk of airborne infectious aerosol transmission in buildings, bringing numerous benefits to occupants and promoting healthier environments.
ASHRAE Standard 241, Control of Infectious Aerosols establishes minimum requirements to reduce the risk of disease transmission by exposure to infectious aerosols in new buildings, existing buildings, and major renovations. Infectious aerosols are tiny, exhaled particles that can carry pathogens that cause infections or disease. These particles are so small that they can remain in the air for long periods of time. Use of this standard could reduce exposure to the SARS-COVID-2 virus, which causes COVID-19, the flu virus and other pathogens. Standard 241 provides requirements for many aspects of air system design, installation, operation, and maintenance.
Standard 241 available now for
presale in the ASHRAE Bookstore.
About ASHRAE
Founded in 1894, ASHRAE is a global professional society committed to serve humanity by advancing the arts and sciences of heating ventilation, air conditioning, refrigeration, and their allied fields.
For more information and to stay up-to-date on ASHRAE, visit ashrae.org and connect on
Instagram,
LinkedIn,
Facebook,
Twitter and
YouTube.
Read the court decisionRead the full story...Reprinted courtesy of
Seven Proactive Steps to Avoid Construction Delay Disputes
September 29, 2021 —
Michael Pink - Construction ExecutiveDelays, cost overruns and disputes have long been part of the commercial construction industry, making the work of reactive forensic analysis by consultants and attorneys a necessary component. Yet many internal practices and issues within construction companies strongly correlate with projects that result in legal disputes and financial losses. There are seven proactive steps that can help companies minimize losses and claims.
Prepare a Cost- and Resource-Loaded Critical Path Method Schedule
This is the first step any contractor can take to establish and document a manpower plan, a timeline and an intended flow for its work. Doing so is beneficial for two reasons: it will become the basis for measuring impacts and variances to both cost and schedule in a delay, dispute or claim setting; and it will serve as a great project management resource or tool. Without thinking through manpower, durations and workflow in great detail at the beginning of the project, contractors put themselves at risk of becoming delayed and blowing the budget.
Reprinted courtesy of
Michael Pink, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Needs Collaborative Planning
January 20, 2020 —
Aarni Heiskanen - AEC BusinessWhat makes construction different from manufacturing is its dynamic nature. Unlike a systemized production plant, a construction site is a mesh of interconnected processes that are far from optimized. The traditional top-down planning practice does not solve problems on the construction site, as recent research reveals. Making planning collaborative is a necessary step in making construction less wasteful.
Everybody in the industry has felt frustration with inefficiencies in construction, but seeing the data is still disconcerting. I’ve had the pleasure of attending several workshops organized by the Finnish Aalto University’s research teams. These eye-opening events both revealed how much waste we have in construction today and suggested solutions to this problem.
Four Aalto University graduate students shared insights from their research at a workshop of the Waste Workgroup of the Building 2030 consortium. They focused on projects where takt production, a lean construction method, had been used. Takt production breaks the work down into equally timed work batches and typically shortens project lead time considerably—up to 50%. However, even these well-planned projects included waste and unnecessary movement, as the researchers found out.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Timely Written Notice to Insurer and Cooperating with Insurer
June 21, 2017 —
David Adelstein - Florida Construction Legal UpdatesI harp on notifying a liability insurer in writing once a claim is asserted against you. As soon as possible. I harp on this because as an insured you want to remove any doubt or argument that the insurer was prejudiced due to a lack of timely notice.
In a recent opinion, Zurich American Insurance Co. v. European Tile and Floors, Inc., 2017 WL 2427172 (M.D.Fla. 2017), the insurer moved for summary judgment in a coverage action arguing that its insured failed to provide it timely written notice. Specifically, the insurer argued that the insured violated the clause in the liability policy that states:
2. Duties in the Event of Occurrence, Offense, Claim or Suit
b. If a claim is made or “suit” is brought against any insured, you must:
- Immediately record the specifics of the claim or “suit” and the date received; and
- Notify us as soon as practicable.
You must see to it that we receive written notice of the claim or “suit” as soon as practicable.
c. You and any other insured must:
- Immediately send us copies of any demands, notices, summonses or legal papers received in connection with the claim or “suit”;
- Authorize us to obtain records and other information;
- Cooperate with us in the investigation, settlement or defense of the claim or “suit”; and
- Assist us, upon our request, in the enforcement of any right against any person or organization which may be liable to the insured because of injury or damage to which this insurance may also apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Sometimes you Need to Consider the Coblentz Agreement
January 19, 2017 —
David Adelstein – Florida Construction Legal UpdatesSince insurance, particularly liability insurance, is such an important component when it comes a construction project, understanding certain nuances such as a
Coblentz Agreement (a what kind of agreement agreement?!?—keep reading) becomes helpful.
If there is a construction defect claim / lawsuit, the implicated parties (e.g., contractor, design professional, subcontractor, sub-consultants) are going to tender the claim / lawsuit to their respective liability insurer. This is what they should be doing – notifying the insurer so that the insurer can defend them from the claim / lawsuit and indemnify them from covered damages associated with the claim / lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Boots on the Ground- A Great Way to Learn and Help Construction Clients
May 02, 2022 —
Christopher G. Hill - Construction Law MusingsThis past week, I attended the Construction Law and Public Contracts seminar in Charlottesville, VA and also a breakfast meeting of the Richmond chapter of the Associated General Contractors of Virginia. Reflecting on this past week, I realized that my membership and participation in both of these great organizations (I am a member of the Board of Governors for the state bar section and the Executive Committee for the Richmond District of AGC-VA) not only provides great marketing and friendship opportunities, participation helps my construction clients in ways that a singular online marketing and interactive path would not (even with the growth of social media).
Among other benefits (including case digests and the insightful newsletter), being a member of the Construction Law and Public Contracts section helps my clients in numerous ways, not the least of which is the ability to network and gain the perspective of many of the great construction attorneys here in Virginia. The ability to bounce legal thoughts off of others for their perspectives gives me the benefit of their experiences and, importantly to my clients, allows me to be more efficient in my research and arguments because of their insight.
Additionally, as a solo construction attorney, knowing other attorneys in other parts of the Commonwealth of Virginia gives me a network of trusted lawyers to whom I can safely and confidently refer a case where a conflict exists or other factors (like geography) make such a referral a benefit to a construction firm in need of legal assistance on a particular matter.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Expect the Unexpected (Your Design Contracts in a Post-COVID World)
April 18, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHave you adapted your post-COVID practice to better plan for the “unexpected” ? In particular, have you looked at–and revised– your professional services contracts to give yourself a little more breathing room for unaccounted issues that may arise? If not, no time like the present.
Don’t like that saying? How about ” a stitch in time saves nine?” No? Still nothing? What about a picture of something so completely unexpected it shocks you– say, a fireman commuting home, in fire-fighting regalia, on a tricycle? Okay, here you go…
Now that I have your attention– you should make it a practice to regularly review and update your professional services agreements, and you should consider issues such as:
- Does your agreement provide for extra compensation if you have to spend more time or a longer period providing construction administration services for material delays or labor shortages? If not, it should.
- Does your agreement have a well-written “act of God” provision– one that includes pandemic/epidemics as part of the “act of God” conditions in which a term may become void? If not, add it now!
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at