Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Colorado Rejects Bill to Shorten Statute of Repose
May 07, 2015 —
Jesse Howard Witt – Acerbic WittThe House State, Veterans, and Military Affairs committee voted today to postpone Senate Bill 15-091 indefinitely, effectively killing the bill for the 2015 session.
As originally drafted, the bill would have given Colorado the shortest statute of repose in the United States. Senate amendments softened the impact of the bill somewhat, but it still would have reduced the amount of time that the owners of single-family homes would have to discover construction defects. Proponents argued that this was necessary because Colorado’s harsh weather conditions make it difficult for construction to last longer than five years. Opponents countered that construction defect laws only provide relief when a builder has violated a code or standard, which is unrelated to the expected lifespan of a product.
One of the Representatives noted that states like Alaska have much harsher weather patterns yet allow homeowners to bring claims up to ten years after construction is complete. Another questioned whether the bill would do anything to encourage affordable housing, a topic that has generated substantial media attention in recent months.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, Acerbic WittMr. Witt welcomes comments at www.wittlawfirm.net
New Executive Order: Revitalizing Our Nation’s Commitment to Environmental Justice for All
May 08, 2023 —
Anthony B. Cavender - Gravel2GavelThe White House has released the text of the President’s new Executive Order strengthening the Federal Government’s commitment to taking new actions to enhance and promote environmental justice. The Order was published in the Federal Register on April 26, 2023 at 88 FR 25251. President Clinton’s pioneering 1994 Executive Order remains effective, but the Federal Government must, as part of a whole-of-government approach to environmental justice, “build upon and strengthen its commitment to deliver environmental justice to all communities across America.”
Unlike that Order, this Order defines “environmental justice.” For purposes of this new Order, “environmental justice” takes into account all adverse human health and environmental effects and hazards, including those related to climate change, the cumulative impacts of environmental and other burdens, and the legacy of racism or other structural or systematic barriers, and ensures equitable access to a healthy, sustainable and resilient environment in which to live, play, work, learn, worship and engage in cultural and subsistence practices.
“Federal activity” is now broadly defined as “any agency rulemaking, guidance, policy, program, practice or action that affects or has the potential to affect human health and the environment, including any agency action related to climate change.” This Order references the seven previous Executive Orders devoted to climate change, clean energy and the Inflation Reduction Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Message from the Chair: Kelsey Funes (Volume I)
November 06, 2023 —
Marissa L. Downs - The Dispute ResolverI am so honored to assume the Division 1 mantle from my friend, Tom Dunn, and look forward to carrying on his good work.
For those of you who don’t know me, I’d like to take this opportunity to share a bit about my background. I grew up in New Orleans and went to LSU for undergraduate and law school. (Geaux Tigers!) I started my practice in 1997 at Phelps Dunbar LLP in Baton Rouge, where I still practice today. I manage the litigation group in the Baton Rouge office of the firm. I practice as a construction lawyer full time and serve on the Construction Panel of the American Arbitration Association and serve as a mediator in construction cases.
I am married to Dr. Chris Funes (the world’s best pediatrician) and we are the parents to two high schoolers. My son is a high school senior and my daughter is a sophomore. So, when I am not lawyering, I have been spending my time lately touring colleges, prepping for homecoming, and helping to teach my daughter to drive (all very relaxing!!). We also have a very sweet (and very hairy) rescue dog, Maggie, who makes sure we get lots of walks.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
2011 West Coast Casualty Construction Defect Seminar – Recap
June 01, 2011 —
CDJ STAFF |
Event exhibitors and sponsors contribute to an informative and engaging environment |
This year’s meeting was the best yet for the industry-leading construction defect and claims event.
This year’s seminar concluded on May 13, 2011 with the Construction Defect Community Charitable Foundation Golf Tournament, held at Strawberry Farms Golf Course.
The Disneyland Hotel in Anaheim, California was the place where more than 1,500 attendees convened for two days of professional development activities and seminars that included CLE workshops and panel discussions of special interest to legal and insurance professionals concerned with construction defect and claims litigation. Key events included “Challenges for Experts in Construction Defect Claims and Litigation,” “Keeping Up with Construction Defect Coverage,” and “Tips for Avoiding the ‘Perfect Storm’ in Handling of Wrap Claims.”
|
Supporting the golf tournament at the 15th hole |
This year’s Ollie award was given to George D. Calkins II, Esq. The West Coast Casualty Jerrold S. Oliver Award of Excellence was named in honor of the late Judge Jerrold S. Oliver, and recognizes an individual who is outstanding or has contributed to the betterment of the construction community.
In addition to being the most comprehensive professional development seminar in the area of construction defects, this year’s seminar was equally valuable as a networking opportunity for members of the industry. People participated in professional development events during the day and then continued networking in the evening at numerous social events. The Lawn Party as well as the legendary Wood, Smith, Henning & Berman events were very well attended. Additional valuable networking events were hosted by a number of industry professionals at the House of Blues, and Tortilla Joe’s.
As of this writing the 2011, West Coast Casualty's Construction Defect Seminar has applied for or has already received the following continuing education accreditation in the following areas;
Read the full story…
For more information about next year’s event, visit West Coast Casualty.
Read the court decisionRead the full story...Reprinted courtesy of
The Right to Repair Act (Civ.C §895 et seq.) Applies and is the Exclusive Remedy for a Homeowner Alleging Construction Defects
February 07, 2018 —
Craig Wallace – Smith Currie McMillin Albany LLC v. Superior Court (01.18.18) ____ Cal.4th _____ (2018 WL 456728)
The California Supreme Court confirmed that the Right to Repair Act (CA Civil Code § 895, et seq. and often referred to by its legislative nomenclature as “SB800”) applies broadly to any action by a residential owner seeking recovery of damages for construction defects, regardless of whether such defects caused property damages or only economic losses. This includes the right in the Act of the builder to attempt repairs prior to the owner filing a lawsuit.
Background
Homeowners sued builder for construction defects. Included in their causes of action was a cause of action for violation of the Right To Repair Act. The Act requires that before filing litigation, a homeowner must give the builder notice and engage in a nonadversarial prelitigation process which gives the builder a right to repair the defects. The builder asked the court to stay the homeowners’ action so the prelitigaiton process could be undertaken. Rather than give the builder the repair right, the homeowners dismissed the particular cause of action from their case, leaving only other so-called common law and warranty causes of action. The common law claims sought recovery for property damage caused by the defects. The builder nonetheless asked to the Court to stay the action so it could exercise its right to repair.
The trial court, relying on
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, denied builder’s request to stay the action. The
Liberty Mutual Court concluded that certain common law construction defect claims fell outside the purview of the Act. Builder appealed. The Court of Appeal disagreed with
Liberty Mutual, so did not follow it, granted the builder’s request for a stay, and directed that the homeowners afford the builder the right to repair the claimed defects as provided under the Act.
The California Supreme Court affirmed, disapproving
Liberty Mutual and the subsequent cases relying on it.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Wallace, Smith CurrieMr. Wallace may be contacted at
swwallace@smithcurrie.com
Court Slams the Privette Door on Independent Contractor’s Bodily Injury Claim
May 06, 2019 —
Brett G. Moore, Michael C. Parme, Lindsey N. Ursua & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Johnson v. The Raytheon Company, Inc., Case No. B281411 (2019) WL 1090217, plaintiff Laurence Johnson (Johnson) was a maintenance engineer employed by an independent contractor that provided control room staff to defendant Raytheon Company, Inc. (“Raytheon”). Johnson was monitoring the computers in the control room when he received low water level alarms pertaining to the water cooling towers. Johnson went to the cooling tower wall in order to look over the wall and verify the water level. Johnson saw the upper half of an extension ladder leaning against the cooling tower’s wall. The ladder had a warning sign which said, “CAUTION” and “THIS LADDER SECTION IS NOT DESIGNED FOR SEPARATE USE.” Despite these warnings, Johnson used the ladder. As he was climbing the ladder it slid out causing him to fall and suffer injuries.
Johnson sued Raytheon, the hirer of the independent contractor, arguing the ladder, among other things, was unsafe and lead to Johnson’s injuries. Johnson believed that Raytheon’s course of conduct of leaving a platform ladder (as opposed to the extension ladder) at the wall constituted an implied agreement to always have one present, on which the independent contractor’s employees relied. Johnson further argued that Raytheon was negligent in providing a dangerous extension ladder, as opposed to a platform ladder, at the wall on the night of the accident.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Brett G. Moore,
Michael C. Parme,
Lindsey N. Ursua and
Lawrence S. Zucker II
Mr. Moore may be contacted at bmoore@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Ms. Lindsey may be contacted at lursua@hbblaw.com
Mr. Lawrence may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Guide to California’s Changes to Civil Discovery Rules
April 29, 2024 —
Lewis Brisbois NewsroomSan Diego, Calif. (April 10, 2024) - California legislators have changed the rules of discovery in civil cases through the passage of amendments to Code of Civil Procedure sections 2016.090 and 2023.050, effective January 1, 2024.
Section 2016.090 creates a new set of rules for civil litigators in cases filed on or after January 1, 2024, which permits any party to the litigation to demand initial disclosures be provided within 60-days. Such a demand can be made any time after a party has filed a responsive pleading, including a demurrer or motion to strike.
Notably, this rule requires production of all information relevant to any causes of action that are pled at the time of the demand, meaning the parties may be required to disclose information related to claims that are being challenged on demurrer or a motion to strike, such as claims for punitive damages. This statute is only implicated when one of the parties to the action makes a demand and may be modified by stipulation of the parties.
Read the court decisionRead the full story...Reprinted courtesy of