Dispute Resolution in Your Construction Contract
February 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are important provisions in your construction contract that are geared towards dispute resolution. These are provisions you want to understand – not when a dispute arises, but BEFORE the dispute ever occurs.
Many times, dispute resolution provisions are cast aside or not appreciated until a dispute rears its ugly head. This can put you in a reactive stance versus a proactive stance, which you want to be in, because you want to proactively make sure all rights are preserved relative to the dispute. You want to proactively make strategic decisions based on the dispute resolution provisions and process in your contract.
Before your contract even gets signed, you may want to negotiate aspects of the dispute resolution process for many reasons. The process could be one-sided. It could be onerous. It could be complex. It could be unfavorable or costly with respect to how you want to progress a dispute. If you appreciate the dispute resolution process from the get-go, you will be in a more effective position to navigate the process while ensuring you are preserving your rights moving forward.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Giant Floating Solar Flowers Offer Hope for Coal-Addicted Korea
March 21, 2022 —
Heesu Lee - BloombergMore than 92,000 solar panels in the shape of plum blossoms, floating on the surface of a reservoir in South Korea, offer a vision of how land-scarce developed nations can overcome local resistance to giant renewable-energy projects.
The 17 giant flowers on the 12-mile-long reservoir in the southern county of Hapcheon are able to generate 41 megawatts, enough to power 20,000 homes, according to Hanwha Solutions Corp., which built the plant.
It’s one of the biggest floating solar plants in the world, and it’s in a nation that has been a laggard in adopting renewable energy, even though South Korea’s industrialized economy relies heavily on imported fossil fuels.
Read the court decisionRead the full story...Reprinted courtesy of
Heesu Lee, Bloomberg
20 Wilke Fleury Attorneys Featured in Sacramento Magazine 2020 Top Lawyers!
August 24, 2020 —
Wilke FleuryCongratulations to Wilke Fleury’s featured attorneys who made the Sacramento Magazine’s Top Lawyer List for 2020!
Each attorney has been awarded an accolade in the following practice areas:
Kathryne Baldwin – Insurance
Dan Baxter – Business Litigation & Government Contracts
Adriana Cervantes – Medical Malpractice
Heather Claus – Health Care
Aaron Claxton – Health Care
Dan Egan – Bankruptcy and Creditor/Debtor
Samson Elsbernd – Employment & Labor
Danny Foster – Litigation Insurance
David Frenznick – Construction & Construction Litigation
George Guthrie – Real Estate & Construction Litigation
Ron Lamb – Medical Malpractice
Neal Lutterman – Medical Malpractice
Steve Marmaduke – Business/Corporate & Real Estate
Gene Pendergast – Estate Planning & Probate
Mike Polis – Health Care
Matthew Powell – Business Litigation
Bianca Samuel – Employment & Labor
Shannon Smith-Crowley – Legislative & Governmental Affairs
Spencer Turpen – Medical Malpractice
Steve Williamson – Business Litigation & Bankruptcy and Creditor/Debtor
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury
Governor Signs AB5 Into Law — Reshaping California's Independent Contractor Classification Landscape
December 02, 2019 —
Eric C. Sohlgren & Matthew C. Lewis - Payne & Fears Legal AlertToday, Governor Gavin Newsom signed California Assembly Bill 5 (“AB5”), controversial legislation which will have a substantial impact on California employers when it goes into effect on January 1, 2020.
AB5 enacts into a statute last year’s California Supreme Court decision in Dynamex Operations West, Inc. v. Superior Court, 4 Cal. 5th 903 (2018), and the Court’s three-part standard (the “ABC test”) for determining whether a worker may be classified as an employee or an independent contractor.
Under the ABC test established in Dynamex and now under AB5, a worker may be properly considered an independent contractor only if the hiring entity establishes all three of the following: (A) that the worker is free from the control and direction of the hirer in connection with the performance of the work, both under the contract for the performance of such work and in fact; (B) that the worker performs work that is outside the usual course of the hiring entity’s business; and (C) that the worker is customarily engaged in an independently established trade, occupation, or business of the same nature as the work performed for the hiring entity.
Reprinted courtesy of
Eric C. Sohlgren, Payne & Fears and
Matthew C. Lewis, Payne & Fears
Mr. Sohlgren may be contacted at ecs@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Cities' Answer to Sprawl? Go Wild.
December 06, 2021 —
Chris Malloy - BloombergIn a neighborhood of right-angled stone, stucco and brick buildings not far from Milan’s central train station, two thin towers stand out. Green and shaggy-edged, they look like they’re made of trees. In fact, they’re merely covered in trees — hundreds of them, growing up from the towers’ staggered balconies, along with 11,000 perennial and covering plants, and roughly 5,000 shrubs.
The greenery-festooned towers, called the Bosco Verticale, or Vertical Forest, are residential buildings in a broader-than-usual sense. The 18- and 26-story structures are “a home for trees that also houses humans and birds,” according to the website of architect Stefano Boeri, who has built tree-covered buildings elsewhere and is working on similar projects in Antwerp, Belgium, and Eindhoven in the Netherlands.
The Bosco Verticale is an example of urban rewilding, the growing global trend of introducing nature back into cities. There are consequences to the pace of today’s urban growth, which is the fastest in human history, including loss of biodiversity, urban heat islands, climate vulnerability, and human psychological changes. The U.S. Forest Service estimates that some 6,000 acres of open, undeveloped space become developed each day. Globally, past urban planning decisions like the prioritization of the car have given rise to cities that, but for scattered parks, tend to be divorced from nature. Rewilding aims to make cities better and more sustainable for people, plants, and animals.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Malloy, Bloomberg
Loose Bolts Led to Sagging Roof in Construction Defect Claim
February 10, 2012 —
CDJ STAFFThough the sagging roof is neither leaking nor a safety hazard, the town of Waynesville, North Carolina is suing the builder of its new fire station, as reported in the Smoky Mountain News. The engineers who examined the roof found a substantial number of loose bolts in the roof trusses. Additionally, the trusses themselves have become bent.
Tom Galloway, Waynesville’s Town Manager said “it needs to be remedied and fixed.” He said that the builder, Construction Logic, “never indicated a willingness to fix the roof.” The town is seeking the cost of repair, which Galloway estimated could be $400,000, and an additional $30,000 in damages. The suit states that Construction Logic failed to follow the plan specifications for the roof.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
English v. RKK. . . The Rest of the Story
December 04, 2018 —
Christopher G. Hill - Construction Law MusingsBack in February, I discussed a case relating to indemnity and ambiguity. The opinion in that case, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al., allowed a breach of contract and indemnity claim to move forward despite the fact that conflicting term sheets between the plaintiff and defendant could have been read to violate Virginia law by requiring indemnity for English’s own negligence. In other words, the ambiguity worked in English’s favor (though that is not something to count on). The Court did not however address whether there was any negligence on English’s part and if there was, what was the contractual effect.
I’ll bet you were wondering what happened later in that case. Well, here’s the answer. In a subsequent opinion, the Court looked at the same ambiguous and conflicting term sheets between and among those defendants that were required to provide quality assurance services for the construction of a bridge in western Virginia. For the full procedural and factual analysis, be sure to read the full memorandum opinion linked above.
Read the court decisionRead the full story...Reprinted courtesy of
Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Force Majeure Under the Coronavirus (COVID-19) Pandemic
March 08, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCAs COVID-19 disrupts work and life as we know it, the question many contractors have is what protections are available against the inevitable project impacts and delays? Generally, construction contracts require a contractor to timely perform work until project completion or potentially face damages (liquidated or actual) and possible termination. When events occur, however, that are beyond our control (such as a national pandemic), it is important to review and understand what contract provisions or avenues are available for potential relief.
1.
Review Your Contract For A Force Majeure Provision.
A
“force majeure” contract provision is commonly included in construction contracts, service agreements, purchase orders, etc. It typically covers events or conditions that can be neither anticipated nor controlled. These provisions, however, will vary greatly from contract to contract and may not include the language “force majeure” but rather may be included in general delay or impact clauses. For example, some common provisions include:
- Washington State Department of Transportation Clause (2018 Standard Specifications for Road, Bridge and Municipal Construction): The Contractor shall rebuild, repair, restore, and make good all damages to any portion of the permanent or temporary Work occurring before the Physical Completion Date and shall bear all the expense to do so, except damage to the permanent Work caused by: (a) acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or (b) acts of the public enemy or of governmental authorities; or (c) slides in cases where Section 2-03.3(11) is applicable; Provided, however, that these exceptions shall not apply should damages result from the Contractor’s failure to take reasonable precautions or to exercise sound engineering and construction practices in conducting the Work.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com