Not in My Kitchen – California Supreme Court Decertifies Golden State Boring Case
November 26, 2014 —
Roger Hughes – California Construction Law BlogOn November 11, 2014, the California Supreme Court rejected the recent California Court of Appeals decision Golden State Boring & Pipe Jacking, Inc. v Eastern Municipal Water District, 228 Cal.App.4th 273 (2014) which we wrote about earlier by “decertifying” it (meaning that lawyers cannot cite to the case as legal precedent) The decertification removed a decision that added substantially to the confusion as to when an action on a payment bond is timely filed. Even though the decision was determined in accordance with pre-2014 statutes, the case was relevant precedent for construction attorneys when determining time deadlines for filing a claim on a bond.
Background
In July of this year, the California Court of Appeals for the Fourth Appellate District upheld a trial court’s granting of summary judgment against a project subcontractor Golden State Boring & Pipe Jacking, Inc. (GSB) who sued Safeco Insurance Company (Safeco) for unpaid contract amounts on a project payment bond issued by Safeco. Both at the trial level and on appeal Safeco successfully argued that GSB’s action on its payment bond claim was time barred by former California Civil Code Sections 3249 (now Section 9558), because it was filed more than six month after the period in which stop notices may be filed as provided by California’s Civil Code Section 3184 (now Section 9558).
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Duty to Defend Negligent Misrepresentation Claim
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Kansas Court of Appeals determined that the insurer must defend claims of negligent misrepresentation against its insured. Central Power Sys. & Servs. v. Universal Underwriters Ins. Co., 2014 Kan. App. LEXIS 9 (Kan. Ct. App. Feb. 21, 2014).
Central Power contracted to furnish Eagle Well with 10 oil-rig engines and 10 oil-rig transmissions. Eagle Well alleged that Central Power informed them that the engines and transmissions would be operational without any additional components. As is turned out, the engines could not operate without a wiring harness. Eagle Well had to hire a third party to make wiring harnesses that would meet their needs and to install the wiring harnesses.
Eagle Wells sued Central Power, alleging damages in the form of lost profits for the time it took to make the engines independently operational. Further, damages were incurred due to money needed for the costs of purchasing the wiring harnesses from the third party and attaching the harnesses to the engines. Claims asserted against Central Power included breach of contract, negligence and negligent misrepresentation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Fourth Circuit Issues New Ruling on Point Sources Under the CWA
October 02, 2018 —
Anthony B. Cavender - Gravel2GavelThe Clean Water Act (CWA) authorizes citizen suits to enforce the provisions of the law which requires a permit to discharge a pollutant from a point source into navigable waters. Earlier this year, the U.S. Court of Appeals for the Fourth Circuit, in Upstate Forever v. Kinder Morgan Energy Partners, held that discharges into groundwater, not surface water, could also trigger the regulatory authority of the CWA if there was a hydrological connection between the groundwater and the navigable, surface, waters. In its a closely-watched case, Sierra Club v. Virginia Electric & Power Company (“VEPCO”), which also involved discharges into groundwater, the Fourth Circuit was bound by this this new and controversial precedent (a Supreme Court review is very likely), but the plaintiffs in the VEPCO case could not establish that the landfill and the settling ponds used by VEPCO were “point sources”—another important element that must be established.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
3D Printing: A New Era in Concrete Construction
April 11, 2022 —
Zoey Zhao - Construction ExecutiveThe construction of buildings using concrete has been around since the time of the Romans. In all those centuries, concrete structures have been built using essentially the same method: forms, reinforcement, mixing, pouring, setting, repeat.
The process is costly and time-consuming. The construction of the forms alone demands dozens of workers and requires a substantial amount of lumber, keeping labor and materials costs high. Builders might save some time using prefabricated concrete blocks, but such materials are not appropriate for every construction project and carry their own expenses.
For the first time in history, builders have an alternative to traditional concrete construction methods that are more cost-effective, less expensive, more environmentally friendly and allow for a wide range of possible construction projects. Three-dimensional concrete printing for construction has emerged in the building field as a viable and efficient alternative.
Reprinted courtesy of
Zoey Zhao, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Zhao may be contacted at
zoey@aictbuild.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Overruled Insured as Additional Insured on Subcontractor’s Commercial General Liability Policy
April 02, 2014 —
Beverley BevenFlorez-CDJ STAFFScott R. Murphy and Clifford J. Shapiro of Barnes & Thornburg LLP in the publication National Law Review analyzed the findings of the Mississippi case Carl E. Woodward, LLC v. Acceptance Indemnity Insurance: “the U.S. Court of Appeals for the Fifth Circuit overruled the district court’s determination that a general contractor was insured as an additional insured on its subcontractor’s commercial general liability (CGL) policy for claims arising out of the allegedly defective work performed by the subcontractor.”
“This case underscores the fact that many standard policy forms do not include completed operations coverage for additional insureds,” Murphy and Shapiro declared. “Owners and contractors that desire to have such coverage therefore need to check their contracts to be make sure the contract language requires completed operations coverage for additional insureds, and they also need to obtain and review the actual additional insured endorsement contained in their subcontractors’ insurance policies before work commences to make sure that the required completed operations insurance coverage is provided.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “I Never Had a Chance”
May 29, 2023 —
Daniel Lund III - Lexology“I never had a chance.”
Such was the plea of a general contractor to a Maryland federal court after having been terminated for failure to perform.
“The Agreement provides no express right to cure,” found the court, weighing in on the contractor’s wrongful termination claim. Indeed, the contract was also very clear on termination, allowing for termination for cause on numerous bases, including a common catchall: if the contractor “persistently fails to perform the provisions of this Agreement.”
In advance of the actual date of termination, the owner wrote to the contractor, in accordance with the contract: “Notice is also given that seven days from the date of this correspondence, [owner] will exercise its [termination] rights under Section 13.2.2.2 of the Contract." The communication from the owner contained no discussion of allowing the contractor an opportunity to cure its alleged default.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Concerns About On-the-job Safety Persist
August 13, 2019 —
Joanna Masterson - Construction ExecutiveNearly 40% of workers are more concerned with on-the-job safety this year than they were last year, according to a 360training.com survey of a thousand people across several manual labor-intensive industries. Additionally, a quarter of workers worry every day about getting injured because of their job. That number goes up to 27% for workers in the construction and oil industries.
Slips, trips and falls were the top workplace safety concern (36%), followed by electrical hazards (13%), ergonomic problems (9%), vehicle/equipment accidents (7%) and falling objects (6%). For the construction industry specifically, electrical hazards were identified as the leading cause of concern.
Reprinted courtesy of
Joanna Masterson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of