How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
"Your Work" Exclusion Bars Coverage
July 06, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the appellate court agreed there was property damage caused by an occurrence, the "your work" exclusion barred the insured contractor's claim. King's Cove Marina, LLC v. Lambert Commercial Construction. LLC, 2019 Minn. App. LEXIS 389 (Minn. Ct. App. Dec. 16, 2019).
King's Cover Marina sought to expand and remodel its main building. The marina hired Lambert to perform the remodeling project. Lambert hired Roehl Construction, Inc. as a subcontractor to install new concrete footings on the main level of the building and to provide concrete for the second-level mezzanine floor.
After completion, the marina sued Lambert for breach of contract and negligence. The marina alleged that the concrete floors on the first and second levels were not constructed in accordance with industry standards or with project plans and specifications, resulting in excessive movement and cracking of the new concrete floors. Lambert tendered its defense to its insurer, United Fire & Casualty Company. United Fire defended under a reservation of rights and later sued Lambert for declaratory judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hiring Subcontractors with Workers Compensation Insurance
January 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesYou want to hear more on the POWER of
statutory workers compensation immunity? Well, here it is, because as I have mentioned in the past,
workers compensation immunity is powerful reinforcing the importance for contractors to ensure the subcontractors they hire absolutely have workers compensation insurance. Likewise, subcontractors want to ensure the subcontractors they hire also have workers compensation insurance.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Bankruptcy on a Construction Project: Coronavirus Edition
May 25, 2020 —
Garret Murai - California Construction Law BlogExperts are warning of a wave of bankruptcies in the wake of the coronavirus pandemic. In some industries, such as the hard hit retail sector, that rising tide has already begun as J. Crew and Neiman Marcus filed for bankruptcy protection this past week.
While the federal government’s stimulus package, including the $660 billion Paycheck Protection Program which is part of the larger 2.2 trillion CARES Act, may help to stem the tide of bankruptcies, Chapter 11 bankruptcy filings increased 26% in April over the same period last year.
How the pandemic will impact the construction industry is uncertain. Anecdotally, we’ve been hearing from clients that some project owners are stalling projects that are still in the planning stages as they evaluate the situation, which suggests long term impacts that can be ridden out rather than short term impacts that can devastate on-going construction projects.
Nevertheless, with 24-7 coverage of the pandemic, project owners, contractors, material suppliers, and equipment lessors are understandably concerned with the impact a bankruptcy might have on a construction project. So, here’s a primer on bankruptcies on a construction project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Housing Affordability Down
November 20, 2013 —
CDJ STAFFIn what Rick Judson, the chairman of the National Association of Home Builders, describes as a “‘perfect storm’ scenario,” home prices and interest rates are up “at the same time that the cost of building homes is rising due to tightened supplies of building materials, developable lots and labor.” Residential housing is becoming less affordable.
David Crowe, the Chief Economist for the NAHB, attributes this to “higher mortgage rates and the more than year-long steady increase in home prices,” but he notes that “a family earning a median income can afford 65% of homes recently sold.”
For the last four quarters, the San Francisco-San Mateo-Redwood City area in California holds the dubious distinction of being the nation’s least affordable area. There, a family earning the area’s median income of $101,200 (nearly double the national median) could only afford 16% of the homes sold in the area.
Read the court decisionRead the full story...Reprinted courtesy of
Partner John Toohey is Nominated for West Coast Casualty’s Jerrold S. Oliver Award of Excellence!
March 11, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to share that Newport Beach Partner John Toohey is nominated for West Coast Casualty’s 2024 Jerrold S. Oliver Award of Excellence!
Every year, West Coast Casualty recognizes an individual who is committed, trustworthy, and has contributed years to the betterment of the construction defect community. The award is named after the late Judge Jerrold S. Oliver who is considered a “founding father” in the alternate resolution process in construction claims and litigation. Each year, members of the construction community are asked to nominate individuals who invoke the same spirit as Judge Oliver.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
The Right to Repair Act Means What it Says and Says What it Means
December 18, 2022 —
Garret Murai - California Construction Law BlogA rather short case for a short week.
In Gerlach v. K. Hovnanian’s Four Seasons at Beaumont, LLC, 82 Cal.App.5th 303 (2022), the 4th District Court of appeals examined provisions of the Right to Repair Act (Civ. Code §§895 et. seq), also known as “SB 800” after its original bill number, as it applies to roofs.
The Gerlach Case
Lynn Gerlach and Lola Seals are homeowners who purchased their homes in the Four Seasons at Beaumont adult community, for those 55 year old and older, located in Beaumont, California. Gerlach purchased her home when it was built in 2006. Seals purchased her home from the original owners in 2015.
In 2015 and 2016, Gerlach and Seals served the developer, K. Hovnanian’s Four Seasons at Beaumont, LLC, with claim notices under the Right to Repair Act. The Right to Repair Act, as its name implies, provides notice requirements and repair rights by developers of new single-family homes. The Right to Repair Act also includes construction standards, the violation of which, provides homeowners with a statutory basis for bringing construction defect claims.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com