Documenting Contract Changes in Construction
December 07, 2020 —
J.D. Holzheauser - Construction ExecutiveConstruction projects are almost inevitably subject to changes in the contract. A fundamental understanding of construction changes, how those changes are governed and what is necessary to ensure a complete change are of paramount importance to all parties involved in a construction project. This article is not a treatise on construction contract changes; rather, it provides advice on actions a contractor can take during construction that will help the contractor recover time or money when a contract’s schedule or scope of work needs to be changed.
Changes Defined
Changes to a construction project affect two broad spheres—timing and scope of work. Changes usually present themselves as either a change order or a change directive. Each may go by a different name depending on the contractual scheme in the project’s prime contract, but they essentially have the same characteristics.
The difference between a change order and a change directive is one of agreement. A change order (in the owner-prime contractor context) occurs when the contractor and the owner agree to a change in the timing or scope of work in the contract. Normally, the change order is a written agreement to change the contract and is executed by the contractor and owner.
Reprinted courtesy of
J.D. Holzheauser, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Holzheauser may be contacted at jdholzheauser@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Avoiding Wage Claims in California Construction
November 25, 2024 —
Garret Murai - California Construction Law BlogFor both private works projects and state and local public works projects in California, higher-tiered contractors can find themselves opening up their wallets if their lower-tiered subcontractors fail to pay their workers. And if you think this is just another one of those crazy California things, think again. Higher-tiered parties on federal public works projects can also be asked to open up their wallets if their lower-tiered subcontractors stiff their workers.
While we’re coming upon the season of giving, here’s a Scrooge-like guide on things you can do to avoid finding yourselves on the hook for your lower-tiered subcontractor’s even more Scrooge-like failure to pay their workers.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Insurer Sued for Altering Policies after Claim
January 13, 2014 —
CDJ STAFFA lawsuit alleges that Fidelity National Property & Casualty Insurance Co. retroactively cancelled policies, substituting policies that covered less after claims were made due to damages from Hurricane Sandy. Insurance Journal reports that Dayton Towers Corp., which owns seven high-rises in Queens, New York City, has sued the insurer.
According to Dayton, the policies covered the buildings for amounts from $2.5 to $2.7 million. The total coverage for all seven buildings was $18.5 million. Under new policies, the buildings were covered for $250,000 each, for a total of $1,750,000, which is the amount that Fidelity paid Dayton.
The lawsuit alleges that the policy does not allow for the terms to be rewritten when claims are pending.
Read the court decisionRead the full story...Reprinted courtesy of
Venue for Suing Public Payment Bond
June 15, 2017 —
David Adelstein - Florida Construction Legal UpdatesPublic payment bonds (excluding FDOT payment bonds) are governed under Florida statute s. 255.05. As it pertains to venue—the location to sue a public payment bond–the statute provides in relevant portion:
(5) In addition to the provisions of chapter 47, any action authorized under this section may be brought in the county in which the public building or public work is being construction or repaired.
***
(1)(e) Any provision in a payment bond…which restricts venue of any proceeding relating to such bond…is unenforceable.
Now, what happens if a subcontractor sues only a payment bond but its subcontract with the general contractor contains a mandatory venue provision? For example, what if the general contractor is located in Lee County and the subcontract contains a venue provision for Lee County, the project is located in Collier County, the subcontractor is located in Miami-Dade County, and the surety issues bonds in Miami-Dade County? Does venue have to be in Lee County per the mandatory venue provision?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
This New Indicator Shows There's No Bubble Forming in U.S. Housing
April 01, 2015 —
Michelle Jamrisko and Nina Glinski – BloombergWhen a parking space in Manhattan costs $136,000 and only 15 percent of San Francisco's homes are affordable for the middle class, it's easy to worry that another housing bubble is around the corner.
The vast majority of American homeowners have little to fear: A new gauge from Nationwide Insurance in Columbus, Ohio, suggests the national market is in its best shape since 2001 and there's no reason to fear a national downturn, no less a bursting bubble.
In its first data release, the national Leading Index of Healthy Housing Markets rose to 109.8 in the fourth quarter. Values greater than 100 indicate a robust industry. The index uses local data in 373 metropolitan statistical areas that are underlying drivers of the housing market, including measures on employment changes, demographics and the mortgage market.
Reprinted courtesy of
Michelle Jamrisko, Bloomberg and
Nina Glinski, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Panama Weighs Another Canal Expansion at Centennial Mark
August 20, 2014 —
Michael McDonald – BloombergA century after the U.S. steamship Ancon first sailed through the Panama Canal, a $5.3 billion expansion delayed by bickering contractors and angry workers is nearing completion. The problem is it might not be big enough.
With the expansion 16 months behind schedule, canal administrator Jorge Quijano said officials are studying whether to dig a fourth set of locks to handle a growing fleet of super-sized ships. Those include the 400-meter-long “Triple E” vessels capable of carrying more than 18,000 containers, four times more than current ships passing through the canal.
“We are always analyzing the market and as soon as we can economically justify it we will begin,” said Manuel Benitez, deputy administrator of the Panama Canal Authority, adding that he thinks the current expansion is sufficient for now. “If that changes and the demand exists we are ready to begin.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael McDonald, BloombergMr. McDonald may be contacted at
mmcdonald87@bloomberg.net
Attorney's Erroneous Conclusion that Limitations Period Had Not Expired Was Not Grounds For Relief Under C.C.P. § 473(b)
February 27, 2019 —
David W. Evans & Stephen J. SquillarioIn Jackson v. Kaiser Foundation Hospitals, Inc. (2/8/19 No. A150833), the First District Court of Appeal affirmed the trial court’s denial of a motion for relief from a voluntary dismissal, without prejudice, filed by the plaintiff based on the erroneous conclusion of an attorney who she had consulted (but who had not yet appeared as counsel in her case) that the applicable statute of limitations had not yet expired. In reality, the limitations period had expired on the same date plaintiff had filed her complaint in propria persona. The plaintiff later retained the attorney on a limited basis to present the motion for relief pursuant to Code of Civil Procedure § 473(b) based on the attorney’s affidavit of fault. Therein, the attorney testified that he had advised the plaintiff to dismiss her action voluntarily based on a misinterpretation of the applicable limitations period, which the attorney characterized as having been based on his “mistake, inadvertence, surprise, or neglect.”
Section 473 provides two distinct provisions for relief from default or dismissal – one is discretionary, while the other is mandatory. Discretionary relief is available in the case of an attorney’s mistake, inadvertence, surprise, or excusable neglect. In contrast, mandatory relief is available where the resulting dismissal was caused by an attorney’s mistake, whether or not excusable. In denying the plaintiff’s motion, the trial court reasoned that the plaintiff could not rely upon Section 473(b) because (1) the attorney did not represent the plaintiff at the time and (2) this provision did not apply to the voluntary dismissal of an action without prejudice.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Commercial Construction Lenders Rejoice: The Pennsylvania Legislature Provides a Statutory fix for the “Kessler” Decision
July 16, 2014 —
Thomas C. Rogers – White and Williams LLPIn May 2012, the Pennsylvania Superior Court rendered its now infamous “Kessler” decision. The Kessler decision resulted in fundamental changes in the operation of the Pennsylvania Mechanics Lien Act as it applied to construction loans where the visible commencement of work on the project commenced before the recordation of the construction loan’s open-end mortgage.
Essentially, the Kessler decision held that if the visible commence of work on the project began prior to the recording of the open-end mortgage and any loan advances were made other than for what are commonly considered “hard construction” costs, then any unpaid contractors and subcontractors who later filed mechanics’ liens would have their liens take priority over the lien of all of the construction loan advances.
Subsequent to the Kessler decision, both the lending and title insurance communities in Pennsylvania have struggled mightily to structure deals around the problems created by Kessler and to provide lenders with title insurance coverage for construction loans when work commenced before the recordation of the open-end mortgage.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas C. Rogers, White and Williams LLPMr. Rogers may be contacted at
rogerst@whiteandwilliams.com