Construction Lien Waiver Provisions Contractors Should Be Using
January 06, 2020 —
Jason Lambert - Construction ExecutiveIt is common in construction for a subcontractor or material supplier of any tier to be required to provide a lien waiver when receiving payment. But not all lien waivers are created equal. While at a minimum, a lien waiver, by definition, needs to include a release of liens, it can also include many other terms that can tie up loose ends or resolve potential problems before they begin.
Additional Releases
A typical lien release is going to release any liens and right to claim liens on the subject property. But a lien waiver can also include releases of any claims against surety bonds, other statutory rights or claims, and at its broadest, claims against the paying party. One example of a provision that could help accomplish this is a release of “any right arising from a payment bond that complies with a state or federal statute, any common law payment bond right, any claim for payment, and any rights under any similar ordinance, rule, or statute related to claim or payment rights.” Broad release language can also be used to effectively preclude any claims arising prior to the date of the release.
Payment Representations and Warranties
A typical lien release has no representations or warranties about payment to subcontractors or material suppliers of a lower tier. But contractors can include language requiring the company receiving payment to represent and warrant that all subcontractors of a lower tier have been paid or will be paid within a certain timeframe using the funds provided and that these are material representations and inducements into providing payment. On a related note, if the contract requires subcontractors to provide lien releases from lower tier subcontractors in addition to their own release when seeking payment, contractors can require the sub-subcontractor releases to include representations that they have been paid by the subcontractor to try and tie up payment loose ends all around.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lambert may be contacted at
jason.lambert@nelsonmullins.com
A Third of U.S. Homebuyers Are Bidding Sight Unseen
February 28, 2018 —
Noah Buhayar – Bloomberg Thirty-five percent of homebuyers in the U.S. aren’t even visiting the property before they put in a bid, amid torrid competition in a tight market, according to the latest
survey by
Redfin Corp. Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, Bloomberg
A Lack of Sophistication With the Construction Contract Can Play Out In an Ugly Dispute
November 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are times where a lack of sophistication can come back to haunt you. This is not referring to a lack of sophistication of the parties. The parties, themselves, could be quite sophisticated. This is referring to a lack of sophistication with the construction contract forming the basis of the relationship. While parties don’t always want to buy into the contract drafting and negotiation process, it is oftentimes the first document reviewed. Because contract terms and conditions are important. They govern the relationship, the risk, scope, amount, and certain outcomes with disputes. However, a lack of sophistication can play out when that contract that should govern the relationship, the risk, the scope, the amount, and certain outcomes doesn’t actually do that, or if it does, it does it poorly. An example of how bad a dispute can play out when it comes to the lack of sophistication on the front end is Avant Design Group, Inc. v. Aquastar Holdings, LLC, 2022 WL 6852227 (Fla. 3d DCA 2022), where a cost-plus contract was treated as a lump sum contract.
Here, an owner planned to perform an extensive interior build-out to a residential unit. The owner had an out-of-country architect; because the architect was not licensed in Florida, the owner hired a local architect/designer to oversee construction and obtain goods and services for the residential interior build-out. The contract was nothing but a proposal of items and costs. The proposal stated the owner “would pay the cost of goods and services of the vendors, plus pay a ‘20% Interior Design & Administrative Fee’” to the local designer. Avant Design Group, 2022 WL at *1. The proposal further stated, “This preliminary budget of the Client’s construction costs include [sic] anticipated costs for construction materials, labor and sales tax. Any other cost, including but not limited to freight, cartage, shipping, receiving, storage and delivery are not included in the preliminary budget and will be invoiced separately.” Id., n.2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
TARP Funds Demolish Homes in Detroit to Lift Prices: Mortgages
March 07, 2014 —
Brian Louis and Jeff Green - BloombergIn Flint, once a thriving auto-industry hub, excavators with long metal arms and shovels have begun tearing down 1,500 dilapidated homes in an attempt to lift the housing market.
The demolitions in this Michigan city of about 100,000 people are part of the stepped up efforts by officials in several Midwestern states to rid their blighted neighborhoods of decayed housing that’s depressing prices. The funding for the excavator work comes from a surprising source -- the Hardest Hit Fund of the Troubled Asset Relief Program, or TARP, created in 2008 to stabilize to the financial system.
The $7.6 billion Hardest Hit Fund was intended to help troubled property owners avoid foreclosure and keep their homes. As foreclosures fall in most parts of the country, the fund is using the unspent $3.2 billion to remedy the crisis of abandoned homes. In Detroit alone, 70,000 dwellings, or about 19 percent of the total, may need to be torn down, according to the city.
Mr. Louis may be contacted at blouis1@bloomberg.net. Mr. Green may be contacted at jgreen16@bloomberg.net.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis and Jeff Green, Bloomberg
Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
The Administrative Procedure Act and the Evolution of Environmental Law
September 19, 2022 —
Anthony B. Cavender - Gravel2GavelEnacted in 1946, the Administrative Procedure Act (APA) has provided a lasting framework for federal agency rulemaking and adjudication, as well as establishing the power of the federal courts to exercise judicial review over these actions of the federal bureaucracy. The APA is codified at 5 U.S.C. §§ 551–559, and §§ 701-706. There have been very few amendments made to the APA over these years, which indicates that Congress is reasonably satisfied with its administration and implementation.
What follows is an overview of how the APA has been used by the courts to resolve disputes involving the federal agencies, with particular attention being paid to the development of environmental law and practice. While there have been very few amendments to the statute, the courts have been free to enlarge upon the sometimes-opaque text of the APA to, in effect, change the law, even in an era when “textual fidelity” to the language of the statute is the prevalent approach.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
More on Fraud, Opinions and Contracts
February 06, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I have discussed the interaction between fraud and contracts on many occasions. Recently, I got to put my advice into action. I am counsel for the plaintiff in the matter of Environmental Staffing Acquisition Corp. v. Beamon, et. al. in the Portsmouth, VA Circuit Court and recently got a great opinion (.pdf) right on point that was recently featured in Virginia Lawyers Weekly.
The basic facts are these. My client, Environmental Staffing (En-Staff) filed a Little Miller Act claim and a claim for breach of contract for Beamon’s failure to pay for temporary staffing that En-Staff provided it at the Jeffry Wilson housing project demolition in Portsmouth, VA. Beamon then counterclaimed for fraud and breach of contract claiming that some statements to the effect that a particular supervisor was qualified along with presentation of the individual’s resume constituted fraud. My client demurred to the two fraud counts (actual and constructive).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
FDOT Races to Re-Open Storm-Damaged Pensacola Bridge
April 12, 2021 —
Jim Parsons - Engineering News-RecordBuffeted by hurricanes, northwest Florida’s largest-ever infrastructure effort is finally seeing the light at the end of the storm. The three-mile-long bridge across Pensacola Bay is expected to reopen to traffic this spring after an ongoing replacement effort abruptly became an emergency repair job as well.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of