Where Standing, Mechanic’s Liens, and Bankruptcy Collide
September 17, 2018 —
Christopher G. Hill - Construction Law MusingsI have spoken often about mechanic’s liens and the implications of such liens as they relate to bankruptcy here at Construction Law Musings. A recent case out of Loudoun County, Virginia added another wrinkle to this discussion, that of standing and what happens on conveyance of the property and what interest in the property is required to allow a party to seek removal of the mechanic’s lien.
In Leesburg Bldg. P’rs LLC v. Mike Berger Inc. the Loudoun County Circuit Court faced the following scenario. Leesburg Building Partners developed certain condominiums and hired Lansdowne Construction to perform the work as general contractor and paid Landsdowne in full for the work. Lansdowne hired Mike Berger, Inc. (“MBI”) to perform concrete work for the project. Landsdowne didn’t pay MBI approximately $48,000.00 and subsequently filed for bankruptcy. MBI, seeking to protect it’s interest in the money it was owed, recorded a mechanic’s lien on the property. Leesburg Building Partners filed an action to declare the lien invalid and have it removed from the property based upon its “payment defense” and the fact that it had paid Landsdowne in full. A relatively simple scenario and one that has been discussed before here at Musings. Not so fast. . .
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Is There Direct Physical Loss Under A Property Policy When COVID-19 is Present?
April 06, 2020 —
Tred R. Eyerly - Insurance Law HawaiiMost property policies provide coverage for property damage only when there is "direct physical loss" to covered property. Early indications are that COVID-19 remains on surfaces. The duration can last from a few hours to three weeks, depending on the type of surface material. If an employee is infected and the store or restaurant must closed because the virus may rest on surfaces within the building, is there direct physical loss, even though the building structure itself is unharmed?
To answer this question, cases from jurisdictions outside Hawaii may provide guidance. In a case from Louisiana, the homeowner had to move out of her home when excessive levels of organic lead were discovered in the kitchen, living room, master bedroom, and attic. Widder v. La. Citizens Prop. Ins. Corp., 82 So. 3d 294 (La. Ct. App. 2011). The insurer denied coverage because there was no direct physical loss. The trial court agreed; since the home was still intact, no direct physical loss had occurred, so there was no coverage under the policy. The appellate court reversed. It compared the presence of inorganic lead in the home to cases that found a direct physical loss from the existence of Chinese drywall, from which gaseous fumes were released, rendering the home unusable or uninhabitable. Physical damage was not necessary.
What if smoke from a nearby wildfire fills an outdoor theater, forcing cancellation of performances and loss of business income? This was the situation in Oregon Shakespeare Festival Ass'n v. Great Am. Inc. Co., 2016 U.S. DIst. LEXIS 74450 (D. Ore. Jun 7, 2016). Wildfires in the area caused smoke, soot, and ash to accumulate on the surface of seats and concrete ground of the open-air theater. The air quality was poor, but no federal, state or local agency ordered cancellation of the performances. Further, the theater did not suffer any permanent or structural damage to its property. The insurer denied coverage, contending that the loss or damage must be structural to the building itself. After all, the smoke in the air at the theater did not require any repairs to the structure of the property. The court disagreed. The theater sustained "physical loss or damage to property" when the wildfire smoke infiltrated the theater and rendered it unusable for its intended purpose. The decision in Oregon Shakespeare Festival was eventually vacated by a joint stipulation of the parties. Oregon Shakespeare Festival Ass'n v. Great Am. Ins.Co., 2017 U.S. Dist. LEXIS 33208 (D. Ore. March 6, 2017), but the reasoning is still sound.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Huh? Action on Construction Lien “Relates Back” Despite Notice of Contest of Lien
May 01, 2023 —
David Adelstein - Florida Construction Legal UpdatesNot every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues. It is, what you call, “the nature of the beast.” You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.
An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.
Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged. This is a specific complaint filed under
Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons. The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Common Construction Contract Provisions: Indemnity Provisions
January 19, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLP BlogUpcoming blog posts will focus on common contract provisions found in construction contracts. Such provisions are not solely limited to construction contracts and can be found in many other types of business contracts as well. This post will highlight indemnity clauses.
An indemnity clause is a common contract provision used to allocate risk between parties to a contract. The clause obligates one party (the Indemnitor) to protect the other party (the Indemnitee) from certain losses, typically arising from claims of third parties. It may require the Indemnitor to reimburse the Indemnitee for losses or expenses, or satisfy judgments, or even defend the Indemnitee in a lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Your Construction Contract
April 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesYour construction contract is an important topic. What’s even more important is YOUR process for reviewing and negotiating construction contracts.
Are you simply acting as a riverboat gambler willing to assume undue risk because you don’t value the investment in understanding what you are signing? If so, it becomes hard to complain about what you agreed to and signed when you chose NOT to invest in the process. Investing in the process means you are working with a construction attorney, you have an insurance broker that understands your industry, you have resources in place to ensure risk is negotiated and allocated, and you understand what risk you are assuming to make sure you are properly protecting and perfecting your rights, and transferring risk downstream.
When it comes to construction contracts, there are really three approaches:
1. Riverboat Gambler. This is the “I’ll sign whatever you give me because I don’t want to lose the contract / revenue.” Under this approach, you are not worried about undue risk because you don’t value the investment in the next two approaches. Your thought process is that you’ll care about the risk when an issue pops up, i.e., the riverboat gambler. This is not an approach I’d recommend because it is contrary to the adage, “an ounce of prevention is worth a pound of cure.” This is simply a reactive approach to issues and risks. The other two approaches are more proactive and better suited to understand and manage risk.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Subcontractor Strength Will Drive Industry’s Ability to Meet Demand, Overcome Challenges
October 10, 2022 —
Anwar Ghauche - Construction ExecutiveOwners, developers and general contractors get a lot of notoriety for construction projects, especially in these infrastructure-focused times. However, the subcontractor is truly the one under the microscope, as this group requires the most care and attention to ensure the owners and operators are able to meet accelerating demand and public expectations.
The challenges in the current environment are many. Inflation and supply chain disruptions are highly detrimental to specialty trades in the mechanical, electrical, plumbing, drywall and other areas. Reports show that the construction industry, in particular, has seen an
increase of over 20% in the cost of supplies and building materials in the last year alone and, in some cases, over
90% since the start of the pandemic. While these costs are passed along to the owner, the subcontractor still retains significant cash flow risk. This truth is amplified in a volatile market. As if the cost was not enough, equipment and material shortages coupled with rising interest rates only compound the problem—and tenfold for small businesses.
Subcontractors are likely to feel the greatest pressure from supply-related issues. Inflation combined with supply chain shortages require subcontractors to prepare earlier for projects and, when possible, purchase materials upfront. However, the consequence of this preliminary preparation equates to further strains on cash flow. In an effort to remain aligned on schedules and budgets, subcontractors frequently buy all of a project’s materials as soon as a contract is signed—if not before.
Reprinted courtesy of
Anwar Ghauche, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Court Rules in Favor of Treasure Island Developers in Environmental Case
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFA California court ruled that the Environmental Impact Report (EIR) that had been approved by the city of San Francisco was adequate for the proposed 8,000-home development on Treasure Island, according to the San Francisco Business Times.
The suit had been brought by Citizens for a Sustainable Treasure Island back in 2011. However, in December of 2012, “a lower court affirmed the EIR and the citizens’ group appealed that decision.”
The project was proposed by partners Lennar Corp. and Wilson Meany. The development would “add thousands of new housing units along with retail, hotel and office space in addition to renovating historic buildings and creating 300 acres of open space.”
Read the court decisionRead the full story...Reprinted courtesy of
Federal Magistrate Judge Recommends Rescission of Policies
February 12, 2024 —
Craig Rokuson - Traub LiebermanIn the recent case of Union Mut. Fire Ins. Co. v. 142 Driggs LLC, 2023 U.S. Dist. LEXIS 220393, Magistrate Judge Lois Bloom of the United States District Court for the Eastern District of New York recommended granting the insurer's default judgment and holding that of three policies issued to 142 Driggs LLC ("Driggs") be rescinded ab initio.
Driggs had represented on its insurance applications that it did not provide parking to anyone other than itself, tenants, and its guests at the subject insured premises. However, Union Mutual learned that Driggs had been renting out three garages to non-tenants. Second, Driggs represented that the mercantile square footage was around 1,000 square feet, when in actuality, it was larger than allowed under the policies.
Union Mutual provided underwriting guidelines in connection with its default motion, which state that "parking provided for anyone other than the insured, tenants and their guests," presents an "unacceptable risk." The guidelines also state that answering yes to any "preliminary application questions (which presumably included those regarding mercantile square footage and parking) is an "unacceptable risk." The court held that these guidelines supported a finding that Driggs made material misrepresentation and that Union Mutual relied on these misrepresentations in issuing the policies. The court, as such, recommended that the policies at issue be rescinded from inception.
Read the court decisionRead the full story...Reprinted courtesy of