ACS Obtains Overwhelming Jury Trial Victory for General Contractor Client
March 28, 2022 —
Scott R. Sleight - Ahlers Cressman & Sleight PLLCACS is pleased to share news of our recent $19.2 million victory for a general contractor client after a lengthy virtual jury trial involving the Nexus condominium project in downtown Seattle. On Tuesday March 22, 2022, ACS obtained a jury verdict awarding significant damages to our general contractor client and denying nearly all damages claimed against our client by the project owner. The 28-day jury trial commenced via Zoom on January 24 and involved testimony from more than two dozen witnesses on more than 185 discrete change issues and subcontractor pass-through claims as well as counterclaims from the owner for liquidated damages and other damages. Amazingly, after only two days of deliberating the jury reached a verdict resolving all claims overwhelmingly in favor of our general contractor client.
Our client was awarded $19.5 million on its claims totaling $20.6 million and largely defeated the owner’s counterclaims of $4.3 million, with the jury awarding only $318,000 to the owner. This results in a net judgment of $19.2 million in favor of our client. The ACS team, along with the client, worked incredibly hard on this case. The team includes lawyers Scott Sleight, Saki Yamada, Kristina Southwell, Cam Sheldon and paralegals Christina Granquist, Cydney Fermstad, Auzree Hightower, Amy Capell, Samina Helsley and Bernadette Bresee.
Read the court decisionRead the full story...Reprinted courtesy of
Scott R. Sleight, Ahlers Cressman & Sleight PLLCMr. Sleight may be contacted at
scott.sleight@acslawyers.com
Architect, Engineer, and Design Professional Liens in California: A Different Animal than the Mechanics’ Lien
August 15, 2022 —
William L. Porter - Porter Law GroupMost in the construction industry are familiar with the rules governing California mechanics’ liens. They know that the Preliminary Notice of Civil Code Section 8034 and 8200-8216 is an important foundational prerequisite document and that the deadline to record a mechanics’ lien is generally triggered by events occurring at the end of construction, including completion of the work of improvement and/or the recording of the notice of completion or notice of cessation. Most of these rules are found in California Civil Code sections 8160-8494.
While architects, engineers and other design professionals are certainly entitled to pursue a mechanics’ lien at the end of a construction project when they are unpaid for their work, unless they also consider the remedy available to them under the California “design professional lien,” they are missing a powerful opportunity to preserve the right to payment only available to architects, engineers, and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Homebuilders Go Green in Response to Homebuyer Demand
May 10, 2012 —
CDJ STAFFMcGrawHill Construction reports that 17 percent of new homes and remodels in 2011 were done with green building practices. Their report estimates that by 2016, this will rise to 29 to 38 percent of the market for home construction and remodeling.
Consumers see the green buildings as more desirable, particularly where they are more energy efficient. Two thirds of builders noted their customers were interested in features that would lower the energy use of their homes. Consumers also feel that green building materials are more durable and see green homes as higher quality.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
America’s Infrastructure Gets a D+
March 16, 2017 —
Garret Murai – California Construction Law BlogThe American Society of Civil Engineers (ASCE) has issued their 2017 Infrastructure Report Card, which assigns a letter grade to the nation’s infrastructure.
Our country’s grade in 2017? A disappointing D+.
Although, if you’re a glass half full kind of person (bless your soul) at least our grade didn’t fall since the last report card was issued in 2013, when our grade was a D+ as well.
In short, we suck. Although, apparently, we don’t suck evenly across the board.
ASCE has divided its cumulative GPA into grades for specific courses, if you will. Our transit systems received a grade of D-; our airports, dams, drinking water and waste water plants, inland waterways, levees and roads received a grade of D; our power plants, hazardous waste plants, public parks and schools received a grade of D+; our bridges, ports and solid waste plants a grade of C+, and our rail systems received a grade of B.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Neighbors Fight to Halt Construction after Asbestos found on Property
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFSI Live reported that residents spoke out at the Staten Island, New York community board meeting to try to halt “construction taking place at former Mount Manresa Jesuit Retreat House property in Fort Wadsworth.” Barbara Sanchez, secretary of the Committee to Save Mount Manresa, stated that halting the construction is urgent now that asbestos has been discovered on the property.
"We want a full stop-work order ... Everything being done around those buildings is being blown into our homes,” Sanchez said in the meeting, according to SI Live. “So I want testing for ... everything touched by the asbestos -- and our homes, before the work continues at Mount Manresa!"
Jeanna Massimi, a resident of Fort Wadsworth, stated that people in the community are already dealing with health problems due to the construction work: “A lot of people where I live [are having] X-rays and are being tested for asbestos exposure. They can't have their bedroom windows open anymore. The dust is like soot -- it's thick. It's everywhere in the home. People are coughing, wheezing and hoarse. You end up feeling lethargic.”
Mike Gilsenan, assistant deputy commissioner at the Department of Environmental Protection, said it was “highly unlikely any dust or fibers migrated off that site. That is the best I can tell you.” But SI Live reported that he added “that the process is ‘not foolproof.’”
Read the court decisionRead the full story...Reprinted courtesy of
How to Mitigate Lien Release Bond Premiums with Disappearing Lien Claimants
May 20, 2019 —
Scott MacDonald - Ahlers Cressman & Sleight PLLCIt is one of those dreaded business situations that plagues the construction industry, especially in times of economic downturn—what to do when a lower-tier entity files a lien against a property then disappears. It has happened to countless owners, general contractors, subcontractors, and even some particularly unlucky sub-tier subcontractors and suppliers. Here is how it arises: a project is moving along, then performance or payment issues arise, and a company that is over extended or unwilling to continue work stops performance, walks off the job, and files a lien against the property for whatever amounts were allegedly unpaid. Often, the allegedly unpaid sums were legitimately withheld due to a good faith dispute over payment/performance, and it is not unusual for the defaulting entity to not be entitled to any of the sums claimed in the lien. Regardless, the lien stays on the property, and pressure is applied from the “upstream” entities to the party who contracted with the defaulting entity to “deal” with the lien.
Oftentimes, a contract will require the parties to “deal” with a lien by obtaining a lien release bond (“release bond”). For those lucky enough to not have encountered this issue, a release bond is a nifty statutory device whereby a surety agrees to record a release bond for the full claimed amount of the lien, with the release bond substituting in for the liened property, effectively discharging the property from liability under the lien. In other words, the lien is released from the property and attaches to the release bond. If the lien claimant recovers on its lien, it is technically satisfied by the surety providing the release bond (or the party who agrees to indemnify and defend the release bond). In exchange for delivering the release bond, the surety demands yearly premiums be paid on the release bond amount
Read the court decisionRead the full story...Reprinted courtesy of
Scott MacDonald, Ahlers Cressman & Sleight PLLCMr. MacDonald may be contacted at
scott.macdonald@acslawyers.com
Construction Litigation Roundup: “Stop - In the Name of the Law!”
August 07, 2023 —
Daniel Lund III - LexologyIn a 5-4 decision, the United States Supreme Court settled a split among the federal appellate circuits on whether appeal of a district court refusal to compel arbitration stays the underlying litigation in the district court.
Having been denied relief by the district court on its motion to compel arbitration, plaintiff filed an interlocutory appeal to the Ninth Circuit under the Federal Arbitration Act, 9 U. S. C. §16(a), which authorizes an interlocutory appeal from the denial of a motion to compel arbitration. Plaintiff asked the district court to stay its proceedings pending resolution of the interlocutory appeal. The district court refused, and the Ninth Circuit also declined to stay the lower court proceedings pending appeal.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
District Court of Missouri Limits Whining About the Scope of Waiver of Subrogation Clauses in Wine Storage Agreements
May 01, 2019 —
Gus Sara - The Subrogation StrategistIn Netherlands Ins. Co. v. Cellar Advisors, LLC, 2019 U.S. Dist. Lexis 10655 (E.D. Mo.), the United States District Court for the Eastern District of Missouri considered the scope of a waiver of subrogation clause in two wine storage agreements. The court held that the subrogation waivers were limited in scope and, potentially, did not apply to the damages alleged in the pleadings. This case establishes that, in Missouri, waivers of subrogation are narrowly construed and cannot be enforced beyond the scope of the specific context in which they appear.
In 2005, Krista and Reid Buerger (the Buergers) contracted Marc Lazar (Lazar) to assist with purchasing, transporting and storing their wine. In 2006, the Buergers entered into a contract with Lazar’s company, Domaine StL, for the storage of their wine in St. Louis. In 2012, the Buergers contracted with Lazar’s other company, Domaine NY, for storage of their wine in New Jersey. The 2006 and 2012 contracts included subrogation waivers. Pursuant to the contracts, Lazar and the Domaine companies (collectively, Defendants) would buy wine for the Buergers by either using the Buergers’ credit card or invoicing them after a purchase.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com