Federal Court of Appeals Signals an End to Project Labor Agreement Requirements Linked to Development Tax Credits
October 20, 2016 —
Gregory R. Begg & Aaron C. Schlesinger – Peckar & Abramson, P.C.What Action Should Owners, Developers and Contractors Take in Anticipation of Successful Challenges to PLA Requirements?
Recently, a federal court in New Jersey issued a decision which very well may invalidate all Project Labor Agreements (“PLA’s”) entered into as a condition to receipt of tax incentives for private development. Tax incentives utilized to promote private development are different, according to the court, than typical public works projects where PLA requirements have generally been held valid. Owners, developers, contractors and governmental entities must assess the consequences of this decision upon contracts already and to be awarded in the future where tax benefits may be linked to a PLA requirement.
In 1993, in what has become known as the Boston Harbor Case, the United States Supreme Court held that state and local governmental entities may condition the award of public works contracts on the contractor’s agreement to enter into PLA’s.
That decision has been followed nationwide since then to uphold the validity of various state and local law bidding conditions requiring successful bidders to negotiate and enter into project labor agreements as a condition to the award of public works contracts. The rationale is that when the government, like any other private party, is participating in an economic market, it may exercise its discretion in setting terms and conditions it believes best suit its interests in the efficient procurement of goods and services in that market. Therefore, a PLA requirement by a governmental entity engaged in market activity is no more or less valid than a PLA requirement on a purely private project.
Reprinted courtesy of
Gregory R. Begg, Peckar & Abramson, P.C. Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Begg may be contacted at gbegg@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida Legislative Change Extends Completed Operations Tail for Condominium Projects
December 10, 2024 —
Holly A. Rice - Saxe Doernberger & Vita, P.C.The Florida Legislature recently passed House Bill 1021 which amended Florida Statute § 718.124. The July 1, 2024 amendment changes Florida’s statute of repose (“SOR”) trigger date for condominium projects. Now, the SOR trigger for existing condominium projects will be governed by Florida Statute §718.124, not Florida Statute § 95.11. Most critically, Florida Statute § 718.124 changes the trigger events for when the “clock” starts running and impacts how long the SOR runs. Notably, Florida Statute § 718.124 already governed the trigger event for the statute of limitations (“SOR”) for condominium projects.
One important overarching takeaway for contractors to carefully assess is that the change in the “trigger” event may result in the SOR concluding at a later date than originally planned – affecting time on the risk and, critically, the availability of insurance. The standard approach of using a static 10-year completed operations tail on a condominium construction insurance program may now be insufficient in certain circumstances.
Read the court decisionRead the full story...Reprinted courtesy of
Holly A. Rice, Saxe Doernberger & Vita, P.C.Ms. Rice may be contacted at
HRice@sdvlaw.com
6 Ways to Reduce Fire Safety Hazards in BESS
January 02, 2024 —
The Hartford Staff - The Hartford InsightsRenewable energy sources, such as solar and wind, are projected to generate 44% of all power in the U.S. by 2050, which is increasing the need for battery energy storage systems (BESS).1
BESS are electrochemical devices that collect energy from a power grid, power plant or renewable source, hold it, and then discharge that energy later to provide electricity on demand.
“A BESS does not itself create or produce energy, it is a storage system. The energy is produced by other means, including different types of renewable sources. Think of a cellphone – you charge it overnight and then it runs throughout the day off that battery power,” says Stacie Prescott, head of energy for middle and large commercial at The Hartford.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Insurer Must Defend Insured Against Construction Defect Claims
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiFinding various exclusions inapplicable, the Federal District Court ruled that the insurer owed a defense to the general contractor based upon Texas law. Mt. Hawley Ins. Co. v. Slay Engineering, 2018 U.S. Dist. LEXIS 139363 (W.D. Texas Aug. 15, 2018).
Huser Construction had a CGL policy issued by Mt. Hawley Insurance Company. Huser contracted to design and construct a municipal sports complex with the City of Jourdanton. The project consisted of four baseball fields, a softball field, parking lots and swimming pool. Huser subcontracted with Cody Pools, Inc. to design and build the swimming pool. Huser also subcontracted with Q-Haul, Inc. to perform earth work, grading and storm drainage work at the site.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Wichita Condo Association Files Construction Defect Lawsuit
November 20, 2013 —
CDJ STAFFKey Construction, the contractor of a downtown Wichita, Kansas mixed-use development has been sued by the condominium association of the development’s condo building. The WaterWalk Place Owners Association claims that the balconies on the building do not drain properly. Additionally, the suit claims that the building has water intrusion problems due to inappropriate or missing sealant at windows, doors, and expansion joints.
Key Construction says that they are dealing with the problems and describe the suit as due to “a deadline pushing on” the residents. Wyatt Hock, the attorney for the residents, says that he hopes for a settlement.
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat – Case Law Update (February 2022)
March 06, 2022 —
Anthony B. Cavender - Gravel2GavelIt is already early in 2022, but several important environmental cases have already been decided by the federal district and federal appellate courts.
THE COURTS OF APPEAL
The U.S. Court of Appeals for the Fourth Circuit
West Virginia State University Board of Governors v. The Dow Chemical Company, et al.
On January 10, 2022, the court decided this case, in which Dow and the other defendants attempted to remove a state groundwater contamination lawsuit to federal court, citing the federal officer removal statute and the presence of a significant federal question. Both the federal district court and the appellate court rejected these arguments and remanded the lawsuit to the state court. For many years, Dow and other parties had been engaged in a RCRA hazardous waste cleanup at an industrial site located in Institute, West Virginia. RCRA permits and corrective action authorizations were issued or supervised by EPA. The plaintiffs complained that the groundwater cleanup, insofar as it affected their property, was deficient, which compelled them to supplement the ongoing federal cleanup with a lawsuit based on West Virginia causes of action and unique to their property. After a careful review of the record, the Fourth Circuit held that the defendants were not acting under the “subjection, guidance or control” of the EPA, and therefore the federal officer removal statute did not apply. Moreover, there was no federal question to resolve as the separate state lawsuit did not challenge a CERCLA cleanup nor did it arise from the RCRA remedial measures that had been taken.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Arbitration and Mediation: What’s the Difference? What to Expect.
September 09, 2019 —
Brittany Rupley Haefele - Porter Law GroupMediation
Mediation is a process in which a neutral person or persons facilitate communication between the disputants to assist them in reaching a mutually acceptable settlement agreement. During this process, a neutral third party, with no decision-making power, intervenes in the dispute to help the litigants voluntarily reach their own agreement. Through a series of discussions, statements and private caucuses between the parties and the mediator, the process lets both parties negotiate and agree to a resolution with which everyone can abide. It is an excellent method of bringing a dispute to a conclusion without the further uncertainty and expense of litigation.
Arbitration
Arbitration, in addition to mediation, is one of the most common methods of alternative dispute resolution (“ADR”), whereby the parties bring a dispute before a disinterested third party who is typically selected by both parties. An arbitrator hears evidence presented by the parties, makes legal rulings, determines facts and makes an arbitration award. Arbitration awards may be entered as judgments in accordance with the agreement of the parties or, where there is no agreement, in accordance with California statutes. Arbitrations can be binding or non-binding, as agreed by the parties in writing. In most cases, the arbitrator’s decision is binding and final.
When is it Appropriate to Engage in Mediation and/or Arbitration?
Mediation can be held at any time, before or during a lawsuit. It is a voluntary process, where both sides simply agree to go to mediation in an effort to get the case settled. Sometimes, it is a contractually required process for the parties to complete prior to going to litigation or arbitration. Typically, in this situation, if a party ignores this requirement and fails to participate in a contractually mandated mediation, they will lose their rights to recover attorneys’ fees and costs – even if they ultimately prevail. Other times, mediation is strongly encouraged by the judge if a lawsuit has already been filed, and some would even say, ordered by the court (though it is typically not called “mediation” but something very similar like a “Dispute Resolution Conference” or “Mandatory Settlement Conference”).
Read the court decisionRead the full story...Reprinted courtesy of