Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Florida's New Pre-Suit Notification Requirement: Retroactive or Prospective Application?
February 05, 2024 —
Holly A. Rice - Saxe Doernberger & Vita, P.C.Florida’s newly formed Sixth District Court of Appeal (“Sixth DCA”) recently certified conflict with Florida’s Fourth District Court of Appeal on the issue of retroactive application of the pre-suit notice requirement contained in Florida Statute §627.70152.1 Earlier this year, the Fourth District Court of Appeal (“Fourth DCA”) held that the pre-suit notice provision applies retroactively, meaning, it applies to all suits filed after July 1, 2021, regardless when the insurance policy was issued.2 The Sixth DCA, in
Hughes v. Universal Property & Casualty Insurance Company,3 directly rejected the Fourth DCA’s interpretation and instead found a retroactive application of the pre-suit notice to be unconstitutional under Florida law. Prior to the Fourth DCA’s ruling, most trial courts had found no retroactive application for the pre-suit notice provision.4
In August 2021, shortly after Florida Statutes Section 627.70152 went into effect on July 1, 2021, Rebecca Hughes (“Hughes”) sued Universal Property & Casualty Insurance Company (“Universal Property”) for breach of contract after Universal Property denied her insurance claim. Hughes did not file a pre-suit notice under Section 627.70152. Universal Property moved to dismiss based on Hughes’ failure to file the pre-suit notice, arguing that the pre-suit notice requirement applies to all lawsuits filed after July 1, 2021, even if the claimant’s insurance policy was issued before the statute’s effective date. The trial court agreed with Universal Property and dismissed the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Holly A. Rice, Saxe Doernberger & Vita, P.C.Ms. Rice may be contacted at
HRice@sdvlaw.com
Insurer Must Defend and Indemnify Construction Defect Claims Under Iowa Law
February 23, 2017 —
Tred R. Eyerly – Insurance Law HawaiiApplying Iowa law, the federal district court found that the insurer had to defend and indemnify construction defect claims for damage to property caused by the insured's subcontractors. Van Der Weide v. Cincinnati Ins., 2017 U.S. Dist. LEXIS 4469 (N.D. Iowa Jan. 12, 2017).
Van Der Weide contracted with Bouma & Company, Inc. to construct a house in 1996. Before construction began, Bouma purchased a CGL policy and a separate umbrella policy from Cincinnati, which were in effect from January 30, 1996 to January 30, 1999.
Bouma used various subcontractors to build the home, including Elkato Masonry, which did the brick veneer and masonry work. The house was completed in February 1998 and Van Der Weide moved in during August 1998.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Does the Russia Ukraine War Lead to a Consideration in Your Construction Contracts?
April 04, 2022 —
David Adelstein - Florida Construction Legal UpdatesMaterial costs are still affecting the construction industry. Supply chain impacts too. The volatility started with COVID-19 (and, in certain cases, before with the imposition of tariffs) and has continued through present date.
But what about the war between Russia and Ukraine and the impact this has had or may have on the supply chain? I think the spillover from the war (with oil, gas, the energy sector, etc.), including the imposition of any sanctions, is not fully realized other than the concern exists in an economy that is already battling through material costs and supply chain disruptions.
How does this affect you?
It may not.
Or you may regularly enter into construction contracts in which you would be smart to address material costs and supply chain impacts. The reason being is that everything from a risk standpoint should begin with your construction contract. Not addressing an issue does not actually mitigate the risk. Confronting the issue does mitigate the risk because you are contractually addressing a concern and know where the other party stands relating to that concern so that business decisions can be made.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractors Pay Heed: The Federal Circuit Clarifies Two Important Issues For Bid Protestors
September 13, 2021 —
Andrew Balland - ConsensusDocsThe United States Court of Appeals for the Federal Circuit (Federal Circuit) recently decided two cases that are relevant to many disappointed offerors considering a bid protest. One decision rendered in March 2021 confirmed the authority of the United States Court of Federal Claims (COFC) to hear a protest based on an agency’s breach of an implied-in-fact contract. A second decision issued in February 2021 reversed a COFC decision from last year regarding the timeliness requirements to obtain a CICA stay and their interplay with Department of Defense (DoD) enhanced debriefing regulations.
Federal Circuit Confirms The Court Of Federal Claims’ Jurisdiction Over Procurement-Related Implied Contract Claims
When a contractor’s bid protest is denied by the Government Accountability Office (GAO), the unsuccessful protestor may challenge the GAO’s decision as arbitrary and capricious in an action before the COFC. While 28 U.S.C. § 1491(b)(1) authorizes the COFC to hear such procurement-related challenges, § 1491(a) also permits the court to adjudicate claims against the United States based on any express or implied contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew Balland, Watt, Tieder, Hoffar & Fitzgerald, LLP
Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Sacramento’s Commercial Construction Market Heats Up
September 10, 2014 —
Garret Murai – California Construction Law BlogOne reason I changed law firms from the Bay Area to Sacramento was I felt that Sacramento’s construction market, which was one of the areas hardest hit in California following the Real Estate Bubble Burst, was poised for a comeback.
And as with past real estate cycles, residential construction has led the growth, and is now being followed by commercial construction. Indeed, according to data compiled by Engineering News-Record, commercial and institutional projects are propelling Sacramento’s construction market[.]
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com