Be Wary of Construction Defects when Joining a Community Association
February 07, 2013 —
CDJ STAFFThere are some benefits to living in small developments with correspondingly small community association. Marilyn Briscoe told the Chicago Tribune that in her 34-unit town home association, "people kind of look out for each other here."
But the article also cautions to not only meet the other owners, but that you should "know the developer" and "be leery if you discover litigation for construction defects." Ryan Shpritz, an association attorney said that "you don't want to start out your new association by spending money on lawyer fees or repairing defects." Whether the development is large or small, "having construction defect litigation going on will have an impact on salability."
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Wins in Arbitration Only to Lose Before the Superior Court on Section 7031 Claim
June 19, 2023 —
Garret Murai - California Construction Law BlogIf you’re a regularly reader of the California Construction Law Blog you’re aware of Business and Professions Code section 7031 which courts have variously described as “harsh[ ],” “draconian” and “unjust,” but, importantly, nevertheless valid. We haven’t seen many cases applying Section 7031 in an arbitration setting, however, until now.
In Vascos Excavation Group LLC v. Gold, 87 Cal.App.5th 842 (2022), a contractor who prevailed on a payment claim in arbitration, had its victory snatched from its fingertips by the Superior Court which found that the arbitrator had exceeded her authority because the contractor was subject to Section 7031.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Toolbox Talk Series Recap – Arbitration Motion Practice
August 07, 2023 —
Michael Zehner - The Dispute ResolverIn the June 22, 2023 edition of the Toolbox Talk Series,
Adrian Bastianelli, Peckar & Abramson, P.C., and
Brian Cashmere, Williams Mullen, moderated by Jennifer Millender of the American Arbitration Association (“AAA”), discussed motion practice in arbitration. Specifically, they offered advice on how to choose the right issue for a motion, how to get approval for a motion, how to write the motion, and how to get the arbitrator to grant it. They also discussed the pros and cons of motion writing in arbitration settings.
1. How to choose the “right issue” for a motion in arbitration
The panel discussed what type of issues can, or should, be brought up in a motion in arbitration. Cashmere stated that a clear and concise issue is best for this type of review. For example, statute of limitations, notice, or contract interpretation issues may make great summary judgment or partial summary judgment motions. Essentially, an issue that the arbitrator may resolve via primarily a question of law is more likely to succeed. Bastianelli warned against submitting just any “available” motion, as the practice may turn the arbitrator against you. Both panelists mentioned the need to consider strategy before filing a motion—ask, “how will filing this motion help or hurt reachingArbi final resolution.” Cashmere noted that sometimes the threat of bringing the issue to a hearing can put pressure on the adverse party in a way that is favorable to your client’s goals; possibly even more so than actually submitting the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Zehner, BBG Construction LawMr. Zehner may be contacted at
mzehner@bbglaw.com
Massive Wildfire Near Boulder, Colo., Destroys Nearly 1,000 Homes and Businesses
January 03, 2022 —
Mark Shaw - Engineering News-RecordA wildfire, driven by wind gusts up to 105 mph, swept through 6,000 acres in suburban neighborhoods east of Boulder, Colo., destroying 991 homes and damaging 127 others in the towns of Superior and Louisville, according to estimates from the Boulder County sheriff’s office.
Reprinted courtesy of
Mark Shaw, Engineering News-Record
Mr. Shaw may be contacted at shawm@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
How to Determine the Deadline for Recording a California Mechanics Lien
September 17, 2015 —
William L. Porter, Esq. – Porter Law Group BulletinThe California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. As noted below, in order to pursue this remedy, certain deadlines must be met.
Know Your Mechanics Lien Filing Deadlines Generally
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a ”direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The primary differences are that the direct contractor is only required to serve the “Preliminary Notice” on the Construction Lender (Civil Code section 8200-8216), whereas the subcontractor and material supplier must serve not only the Construction Lender, but also the Owner and Direct Contractor (see Civil Code section 8200(e)). Another difference is that a direct contractor has a longer period of time in which to record a mechanics lien after a valid “notice of completion” or a “notice of cessation” has been recorded (Civil Code sections 8180-8190), (60 days for original contractors as compared to 30 days for subcontractors and suppliers – See Civil Code sections 8412 and 8414).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, The Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Georgia Coal-to-Solar Pivot Shows the Way on Climate Regs
July 02, 2014 —
Mark Drajem and Margaret Newkirk – BloombergGeorgia small-business owner Julian Smith keeps hearing that the Obama administration’s latest climate regulations will drive up local electric bills. He doesn’t believe the prediction, but he isn’t arguing: The fears are doing wonders for his solar-panel installation company.
“My phone is blowing up with new customers,” Smith, owner of SolarSmith LLC of Savannah, said in an interview. “It turns out that if you tell everybody the amount they will spend on electricity will skyrocket, they will believe you.”
In Smith’s home state, as in the rest of the nation, businesses and consumers are struggling to size up competing claims about the Environmental Protection Agency’s plan to cut carbon pollution from power plants, released June 2. The proposed regulations are among the most sweeping and complex in the EPA’s history, promising to revamp the way electricity has been generated and distributed for a century.
Mr. Drajem may be contacted at mdrajem@bloomberg.net; Ms. Newkirk may be contacted at mnewkirk@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Mark Drajem and Margaret Newkirk, Bloomberg
“Incidental” Versus “Direct” Third Party Beneficiaries Under Insurance Policies in Which a Party is Not an Additional Insured
April 18, 2023 —
Garret Murai - California Construction Law BlogAs they say, when it rains, it pours. Indemnity and insurance are the “Big Two” when it comes to risk avoidance on construction projects. The next case,
LaBarbera v. Security National Security Company, 86 Cal.App.5th 1329 (2022), involves both. It’s an interesting case, which I think could have gone either way, involving claims by a higher-tiered party that they were a third party beneficiary under an insurance policy in which they were not named as an additional insured.
The LaBarbera Case
The Indemnity Provision and Insurance Policy
In June 1016, Chris LaBarbera hired Richard Knight doing business as Knight Construction to remodel his house in Carmichael, California. The construction contract included an indemnity provision which provided that Knight would defend and indemnify LaBarbera from all claims arising out the remodeling work except for claims arising from LaBarbera’s sole negligence and willful misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
First-Party Statutory Bad Faith – 60 Days to Cure Means 60 Days to Cure
October 19, 2020 —
David Adelstein - Florida Construction Legal UpdatesIn a first party bad-faith lawsuit, such as a bad faith claim against an insured’s property insurer, there are three requirements that must be met before the bad faith lawsuit is filed: “‘(1) determination of the insurer’s liability for coverage; (2) determination of the extent of the insured’s damages; and (3) the required notice must be filed under section 624.155(3)(a).’” Fortune v. First Protective Ins. Co., 45 Fla. L. Weekly D2092a (Fla. 2d DCA 2020) (citation omitted).
The third requirement is for the insured to file a Civil Remedy Notice (known as a “CRN”) as a condition precedent to filing a statutory bad faith lawsuit giving the insurer 60 days’ notice of the bad faith violation and to cure the violation, i.e., pay the claim if the violation is payment.
A very common bad faith payment violation is the assertion that the insurer did NOT attempt “in good faith to settle claims when, under the circumstances, it could and should have done so, had it acted fairly and honestly towards its insured and with due regard for his or her interests.” Fla. Stat. s. 624.155(1)(b)(1).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com