Fort Lauderdale Partner Secures Defense Verdict for Engineering Firm in High-Stakes Negligence Case
June 10, 2024 —
Lewis Brisbois NewsroomFort Lauderdale, Fla. (June 3, 2024) - Fort Lauderdale Managing Partner Cheryl Wilke recently secured a defense verdict for civil engineering firm Gulfstream Design Group and its owner, Matthew Lahti, in a high-stakes professional negligence case in which the plaintiff sought more than $20 million. The verdict by a six-person jury in St. Augustine followed a nine-day trial.
The case involved a 100-acre tract of land in St. Johns County, Florida, owned by the plaintiff, Cynthia Taylor. The land was zoned for rural farming, and she wished to sell the property for development. She entered into a contract with Southeast Georgia Acquisitions (“SGA”) to sell the property with the goal of creating a 200-home subdivision. SGA hired Doug Burnett as land use counsel and our client, Gulfstream Design Group, as the civil engineer to design the project.
In St. Johns County, only a property owner can submit a Planned Unit Development Plan (“PUD”) for the purpose of rezoning. In this case, Burnett and Gulfstream created text and a proposed map for the PUD and submitted it for approval. The PUD was approved first at the staff level, then by planning and zoning and then by the County Commission. All the services were provided prior to closing with PUD approval, a condition of sale.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Force Majeure Under the Coronavirus (COVID-19) Pandemic
March 29, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCAs COVID-19 disrupts work and life as we know it, the question many contractors have is what protections are available against the inevitable project impacts and delays? Generally, construction contracts require a contractor to timely perform work until project completion or potentially face damages (liquidated or actual) and possible termination. When events occur, however, that are beyond our control (such as a national pandemic), it is important to review and understand what contract provisions or avenues are available for potential relief.
- Review Your Contract For A Force Majeure Provision.
A “force majeure” contract provision is commonly included in construction contracts, service agreements, purchase orders, etc. It typically covers events or conditions that can be neither anticipated nor controlled. These provisions, however, will vary greatly from contract to contract and may not include the language “force majeure” but rather may be included in general delay or impact clauses. For example, some common provisions include:
- Washington State Department of Transportation Clause (2018 Standard Specifications for Road, Bridge and Municipal Construction): The Contractor shall rebuild, repair, restore, and make good all damages to any portion of the permanent or temporary Work occurring before the Physical Completion Date and shall bear all the expense to do so, except damage to the permanent Work caused by: (a) acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or (b) acts of the public enemy or of governmental authorities; or (c) slides in cases where Section 2-03.3(11) is applicable; Provided, however, that these exceptions shall not apply should damages result from the Contractor’s failure to take reasonable precautions or to exercise sound engineering and construction practices in conducting the Work.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Triable Issue of Fact Exists as to Insurer’s Obligation to Provide Coverage Under Occurrence Policy
March 08, 2021 —
Valerie A. Moore & Kathleen E.M. Moriarty – Haight Brown & Bonesteel LLPIn Guastello v. AIG Specialty Ins. Co. (No. G057714. filed 2/19/21 ord. pub. 2/23/21), a California appeals court held that triable issues of material fact exist which precluded summary judgment for an insurer seeking to disclaim coverage on the basis that the “occurrence” pre-dated the policy period where a dispute exists as to the timing of the subject “occurrence.”
In Guastello, a subcontractor built retaining walls from 2003 to 2004 for a housing development in Dana Point, California. In 2010, one of these retaining walls collapsed causing damage to a residential lot owned by Thomas Guastello.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Kathleen E.M. Moriarty, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Ms. Moriarty may be contacted at kemoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Superior Court Of Pennsylvania Holds Curb Construction Falls Within The Scope Of CASPA
September 17, 2014 —
Jerrold Anders & Michael Jervis – White and Williams LLPIn Prieto Corp. v. Gambone Construction Co., the Superior Court of Pennsylvania recently considered three issues arising out of a construction dispute, including whether construction of a curb falls within the scope of the Contractor and Subcontractor Payment Act (CASPA), 73 P.S. §§ 501-516. CASPA is a Pennsylvania statute which is intended to protect contractors and subcontractors from abuses in the building industry and which establishes certain rules and deadlines for payments between owners, contractors, and subcontractors. Failure to abide by the act’s payment requirements subjects an owner or contractor to liability for interest, penalties and attorneys fees. In this case, Prieto was a subcontractor hired by Gambone to construct concrete or Belgian block curbs at Gambone’s property developments. Prieto sued Gambone under CASPA for failure to pay its invoices for four projects. After the trial court entered judgment for Prieto, Gambone appealed, arguing that CASPA did not encompass the work at issue, i.e. the construction of curbs, because curbs did not constitute an improvement to real property.
Reprinted courtesy of
Jerrold Anders, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Anders may be contacted at andersj@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Let the 90-Day Countdown Begin
February 11, 2019 —
Amy L. Pierce & Robert A. James - Gravel2Gavel Construction & Real Estate Law BlogMost contractors are diligent about making sure that they pay their licensing fees, renew worker’s compensation insurance, and maintain the required bonds. What may be less obvious is how critically important it is to have current company personnel listed on the company’s licensing records with the Contractor’s State Licensing Board. Only personnel listed on the CSLB’s records are authorized to act on behalf of the licensee with respect to CSLB-related matters.
Although this may sound simple enough, all such personnel will be required to comply with fingerprinting (and background check) requirements before their applications to be added to the company’s licensing records can be approved. No new personnel will be associated with the licensee until their application is determined to be acceptable and all other requirements are met. Unforeseeable processing delays could result in this new personnel being unable to timely act on behalf of the licensee.
Reprinted courtesy of
Amy L. Pierce, Pillsbury and
Robert A. James, Pillsbury
Ms. Pierce may be contacted at amy.pierce@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Vacation during a Project? Time for your Construction Documents to Shine!
October 09, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHappy Lazy Day Everyone! What’s that? You didn’t know that August 10th is considered National Lazy Day? Well, it is. And it ties nicely in with today’s theme: how to take a vacation during the thick of the construction project.
Everyone needs a break. You are no different. It can seem, however, that it is impossible to disconnect from the ongoing onslaught of questions, requests for information, change orders, pay applications, and the like. But you can. The key to taking–and enjoying–your vacation is to plan ahead. This is the time for your construction documents to shine. Make sure that your designs are on schedule; make sure that the change orders and RFIs have been processed so there is no backlog. And make sure that your second in command is familiar enough with the day to day details to step into your shoes for the duration.
Then– be sure to give everyone notice. Is it any of their business that you are taking some time off? No. However, everyone procrastinates. So, if you give the entire team advance notice that you will be “off grid” starting on X date, they will be more inclined to get pending issues to you sooner rather than later. They won’t want to be stalled on progress, and with a heads up on when you are out of pocket, they will make it a priority to get requests to you ahead of your departure date.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Congratulations to San Diego Partner Johnpaul Salem and Senior Associate Scott Hoy for Obtaining a Complete Defense Verdict!
November 13, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Johnpaul Salem and Senior Associate Scott Hoy just concluded a 4-week trial defending a local renowned hotel in San Diego. Plaintiff alleged premises liability against BWB&O’s client arguing plaintiff was injured while riding in an elevator due to alleged negligent maintenance and inspection. Plaintiff brought in a “hired gun” elevator expert from Missouri and sought $25 million in damages for two fractured ankles, a compound tibia fracture, and lifelong CRPS/PTDS/anxiety. BWB&O argued any injuries sustained were a direct result of Plaintiff’s actions. After a passionate and powerful closing argument by Mr. Salem, attacking the foundation of Plaintiff’s expert’s opinions and presenting vigilance of the hotel in the safety of its guests, the jury unanimously ruled in BWB&O’s client’s favor.
Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Candis Jones Named to Atlanta Magazine’s 2021 “Atlanta 500” List
March 01, 2021 —
Candis Jones - Lewis Brisbois NewsroomAtlanta Partner Candis Jones has been named to Atlanta Magazine’s 2021 “Atlanta 500” list of the most powerful business leaders in Atlanta. To compile this list, the publication reviewed nominations from the public and consulted experts across various sectors. The magazine’s editors and writers considered not only the status of the nominees within their respective organizations, but also whether the nominees were visionary by, for example, leading programs for their communities or creating opportunities for employees.
Ms. Jones is a member of Lewis Brisbois’ General Liability Practice. Representing a wide array of clients, including Fortune 500 companies, insurance carriers, and a major metropolitan transit authority, she focuses her practice on insurance defense, premises liability, personal injury, and medical malpractice. She was recently installed as the President of the Gate City Bar Association, the oldest African-American bar association in the state of Georgia, and also serves as a member of the Georgia Defense Lawyers Association and the Georgia Association of Black Women Attorneys.
Read the court decisionRead the full story...Reprinted courtesy of
Candis Jones, Lewis BrisboisMs. Jones may be contacted at