Claim Against Broker for Failure to Procure Adequate Coverage Survives Summary Judgment
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe broker's motion for summary judgment, seeking to dismiss negligence claims for failure to obtain adequate coverage, was denied by the court in Voss v. The Netherlands Ins. Co., 2014 N.Y. LEXIS 384 (N.Y. Ct. App. Feb. 25, 2014).
The insured met with a representative of CH Insurance Brokerage Services Co., Inc. (CHI) to discuss coverage for the premises and her two companies. At CHI's request, the insured shared information on sales figures for calculating business interruption coverage. The broker represented that CHI would reassess and revisit the coverage needs as her business grew.
CHI recommended $75,000 per incident in coverage for business interruption losses. The insured questioned whether the $75,000 limit was adequate, but the broker assured her that it was sufficient. The insured then accepted the recommendation. Subsequently, the insured's business grew, but CHI renewed the policy with the same $75,000 business interruption limit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Improper Means Exception and Tortious Interference Claims
August 14, 2023 —
David Adelstein - Florida Construction Legal UpdatesLast week, I discussed a case (
here) that involved a federal district court (trial court) denying a motion to dismiss on a negligent supervision claim.
In this same case, the plaintiff, a subcontractor/fabricator, also sued the defendants–parent company of a prime contractor and two entities the prime contractor hired to inspect the subcontractor’s fabricated units–for tortious interference of the subcontractor’s contract with the prime contractor. The defendants moved to dismiss this tortious interference claim which gave rise to another interesting discussion by the trial court relating to the burden to plead and prove tortious interference claims. This discussion is worthy to remember the next time you not only want to plead a tortious interference claim, but want to be in a position to put on evidence to prove the claim at trial.
“Under Florida law, the elements of a tortious-interference-with-contract claim are: ‘(1) the existence of a contract, (2) the defendant’s knowledge of the contract, (3) the defendant’s intentional procurement of the contract’s breach, (4) absence of any justification or privilege, and (5) damages resulting from the breach.’” Bautech USA, Inc. v. Resolve Equipment, 2023 WL 4186395 (S.D.Fla. 2023) (citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Previously Owned U.S. Home Sales Rise to Eight-Month High
July 23, 2014 —
Victoria Stilwell – BloombergSales (ETSLTOTL) of previously owned U.S. homes climbed in June to an eight-month high as more listings helped prices cool, luring buyers into the market.
Sales increased 2.6 percent to a 5.04 million annual rate last month, led by gains in all four U.S. regions, figures from the National Association of Realtors showed today in Washington. The median forecast of 78 economists surveyed by Bloomberg projected sales would rise to a 4.99 million rate. Prices advanced at the slowest pace since March 2012 and inventories rose to an almost two-year high.
Historically low interest rates and smaller price increases are helping bring homeownership within reach for more Americans. A pickup in employment opportunities that lead to faster wage growth would provide an added spark for a residential real-estate market that began to soften in the middle of 2013.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Coping with Labor & Install Issues in Green Building
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported on the problem that builders have with using green techniques—finding skilled laborers and subs. “If a green product is not installed correctly it most likely won’t do its job,” building scientist Carl Seville said to Builder.
Austin Trautman of Vali Homes told Builder that the biggest problem he had with his first net-zero prototype house was the HVAC work. “It’s actually a simpler system with straightforward installation, but they just couldn’t figure it out.”
Cliff Majersik, executive director of the Institute for Market Transformation, said that teaching subs the new techniques is worthwhile: “Once you know how to do it, an energy-efficient house can even be less expensive to build.”
Read the court decisionRead the full story...Reprinted courtesy of
Roni Most, Esq., Reappointed as a City of Houston Associate Judge
November 06, 2023 —
Linda Carter - Kahana FeldYesterday, Roni M. Most, Esq., was reappointed as an Associate Judge for the City of Houston. Mr. Most is the Managing Partner of Kahana Feld’s Houston office, chairs the firm’s Corporate Compliance & Transaction group, and heads the Texas division of Kahana Feld’s National Appellate Strategy & Advocacy group. Mr. Most was first appointed as an Associate Municipal Court Judge of the City of Houston in 2012 and he continues to serve in this position. The Most name has been a fixture in Harris County courts, with Judge Most being a third-generation attorney, his family has advocated for their client’s causes for over five decades.
Mr. Most received his Bachelor of Liberal Arts degree from the University of Texas at Austin and went on to graduate with his J.D. from the South Texas College of Law in 2000. Upon graduating, Mr. Most started The Most Law firm, and then went on to become one of the founding partners of Gerber & Most, PLLC. Mr. Most joined Kahana Feld as a Partner in January 2021. He brings over 20 years of experience in general civil litigation (property & casualty) and appeals, state and federal corporate litigation, collections, construction law, and real estate, as well as providing general business counsel.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
“License and Registration, Please.” The Big Risk of Getting Busted for Working without a Proper Contractor’s License
July 25, 2021 —
Christopher A. Henry & Mia Hughes - ConsensusDocsThe need for contractors to maintain the proper contracting license may seem like a mundane, clerical detail, and generally is just that. If, however, the contractor ignores or mishandles paperwork and the proper license is not in hand, licensing may go from a mundane, clerical detail to a financial catastrophe. An unlicensed contractor may be barred from asserting claims or collecting payments for work already performed; the contractor may even be required to return payments for unlicensed work performed.
A recent case in Georgia, a state that had no state-wide general contractor’s license requirement in effect until 2008 illustrates the risk of unlicensed work.[1] In Saks Management and Associates, LLC v. Sung General Contracting, Inc.,[2] the court ruled that without a license the general contractor did not have the right to enforce a contract. The contractor’s claims for payment failed, and the mundane, clerical error led a major financial loss. This disastrous result for the Georgia contractor is far from an outlier, and is a real risk in many states.
Reprinted courtesy of
Christopher A. Henry, Jones Walker LLP and
Mia Hughes, Jones Walker LLP
Mr. Henry may be contacted at chenry@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
The Business of Engineering: An Interview with Matthew Loos
July 15, 2019 —
Aarni Heiskanen - AEC BusinessMatthew Loos is an experienced project manager in the civil engineering industry. He works as a project engineer at Jones|Carter in Fort Worth, Texas. In this interview, we discuss Matt’s new book, The Business of Engineering.
It is not very common that an engineer writes a non-technical book. What inspired you to do so?
Have you ever gotten an idea stuck in your head that you just couldn’t let go of? A time when you couldn’t go to sleep because the idea was consistently begging for your attention?
That’s what happened to me. The idea for this book hits me right before bed, as most good ideas do. I couldn’t go to sleep after the idea struck me. I spent half of the night writing the chapters of this book in my mind. I had been thinking about the idea of engineering and how it relates to other career fields, even the non-technical ones. I was disenchanted with the trifling number of classes I took that prepared me for the business world. These were the initial thoughts that eventually led me down the road into thinking about engineering as a profession going forward.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at