Yes, Indeedy. Competitive Bidding Not Required for School District Lease-Leasebacks
October 01, 2014 —
Garret Murai – California Construction Law BlogRemember when you discovered that the tooth fairy wasn’t real?
It was kind of a bummer on one hand learning that it wasn’t a fairy that magically appeared to swap your tooth for cold hard cash, but rather your mom or, visual horrors, dad.
At the same time, it was, to your nearly-halfway-to-a-decade-on-this-planet-wizened-six-year-old mind, confirmation of what you had a sneaking suspicion was the case in any event.
And, so it is with the next case.
Lease-Leasebacks
In California, most public school construction projects are built using the traditional design-bid-build project delivery method in which a design professional designs the project, the project is put out for competitive bid and the selected contractor builds the project.
But not all school construction projects are built this way.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Challenging and Defending a California Public Works Stop Payment Notice: Affidavit vs. Counter-Affidavit Process
October 21, 2019 —
William L. Porter - Porter Law GroupOne of the most effective collection procedures available to subcontractors and suppliers to California Construction projects is the “stop payment notice” procedure found under California Civil Code sections 9350 – 9364. Under this procedure, the unpaid subcontractor or supplier may serve the stop payment notice on the public entity and the direct or “prime” contractor and cause the public entity to withhold from the direct contractor 125% of the funds identified in the stop payment notice. Thereafter, funds will not generally be released unless the parties reach a settlement agreement or the issue is decided through litigation, arbitration or mediation. There is however an alternative procedure available to direct contractors to expedite the determination of whether a stop payment notice is valid and to possibly obtain an early release of the funds withheld by the public entity. This “summary proceeding” process could result in release of funds to the direct contractor in less than 30 days. The summary proceeding can also be challenged by the unpaid subcontractor or supplier. All public works contractors, subcontractors and suppliers should be aware of the process. The process for direct contractors to release a stop payment notice and for subcontractors and suppliers to challenge the process works as follows:
After a California stop payment notice has been served and the public entity has withheld funds accordingly, the direct contractor may challenge the stop payment notice by serving an “affidavit” (basically a sworn statement showing why the stop notice is not valid) on the public entity, demanding that the public entity release all funds withheld. Upon receipt of such an affidavit, the public entity will serve the subcontractor or supplier who served the stop payment notice with a copy of the affidavit, along with a “demand for release of funds”. If the stop payment notice claimant does not respond with a “counter-affidavit” by the date stated on the notice sent by the public entity (“not less than 10 days nor more than 20 days after service on the claimant of a copy of the affidavit”), then the public entity will be within its rights to release the withheld funds to the direct contractor, and the stop payment notice claimant will relinquish its stop payment notice rights.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
London’s Best Districts Draw Buyers on Italian Triple Dip
August 27, 2014 —
Neil Callanan – BloombergItalians were the biggest group of foreigners to buy homes in London’s best districts in the seven months through July as weak domestic growth prompted investment abroad.
Italy, which fell into a triple-dip recession in the second quarter, accounted for 6.7 percent of all homes sold in the 13 neighborhoods that Knight Frank LLP defines as prime central London, the broker said in an e-mail today. France was second as euro-area investors accounted for 14.5 percent of purchases, the most in the period since 2011. Russia led the group a year ago, followed by the United Arab Emirates.
The European Central Bank’s monetary-policy easing “is driving more euro-zone residents to search for yield abroad,” Goldman Sachs analysts including New York-based chief currency strategist Robin Brooks wrote in a note last week. Yields for homes in prime central London rose in July for the first time since April 2011 as more people opted to rent on concerns that home taxes may rise if the Conservative Party-led government loses next year’s elections, Knight Frank said on Aug. 11.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, BloombergMr. Callanan may be contacted at
ncallanan@bloomberg.net
Texas and Georgia Are Paying the Price for Sprawl
March 15, 2021 —
Conor Sen - BloombergCities in the Sun Belt South have been needing a more modern development model for a while. That's created tensions, both economically and politically, that have only accelerated during the past year's pandemic. My colleague Noah Smith wrote a column about this specific to Texas, but it's broader than any one state and it's useful to think about how we got to this point and why these issues are relevant in 2021 in a way they weren't a generation ago.
There's an institutional reluctance to pivot away from the Sun Belt model defined by low taxes and cheap land because of how successful it was for key constituencies for decades. Coming out of World War II, there was a scramble nationwide to build more housing in response to soldiers coming home from war and pent-up demand for family formation.
The combination of the automobile as the nation's now-dominant form of transportation and the passage of the Federal Highway Act of 1956 made building out the suburbs of less-populated southern states an irresistible growth model for politicians and economic development interests alike. If it required tax breaks and fewer regulations to lure jobs and people from northern states to accelerate the process, so be it.
Read the court decisionRead the full story...Reprinted courtesy of
Conor Sen, BloombergMr. Sen may be contacted at
csen9@bloomberg.net
Owners and Contractors Beware: Pennsylvania (Significantly) Strengthens Contractor Payment Act
June 13, 2018 —
Wally Zimolong – Supplemental Conditions Yesterday, Governor Tom Wolf signed into law House Bill 566 which make major changes to Pennsylvania’s Contractor and Subcontractor Payment Act. Owners and General Contractors that fail to take head of the changes could face significant financial consequences.
The Pennsylvania Contractor and Subcontractor Payment Act, known as CAPSA or simply the Payment Act, was passed into law in 1994. The intent was “to cure abuses within the building industry involving payments due from owners to contractors, contractors to subcontractors, and subcontractors to other subcontractors.” Zimmerman v. Harrisburg Fudd I, L.P., 984 A.2d 497, 500 (Pa. Super. Ct. 2009). In reality, abuses still occurred. While the Payment Act purportedly dictated a statutory right to payment within a certain amount of time and imposes stiff penalties for failure make payment, including 1% interest per month, 1% penalty per month, and reasonable attorneys fees, the language of the Payment Act left recalcitrant contractors with wiggle room. Particularly, the Payment Act allowed owners and higher tier subcontractors to withhold payment “deficiency items according to the terms of the construction contract” provided it notified the contractor “of the deficiency item within seven calendar days of the date that the invoice is received.” 73 P.S. Section 506. The problem was that the Payment Act did not expressly state where the notice must be in written, what it must say, and what happened if notice was not given.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Cybersecurity "Flash" Warning for Construction and Manufacturing Businesses
April 26, 2021 —
Jeffrey M. Dennis - Newmeyer DillionThe FBI recently released its 2020 Internet Crime Report (Report), which details and analyzes complaints received through the FBI’s Internet Crime Complaint Center (IC3). In 2020, IC3 received a record number of complaints – nearly 800,000, with reported losses in excess of $4.1 billion. Companies must acknowledge that cybercrime is a real, dangerous threat to their business, and understand how, and why, these threats continue to escalate. At a minimum, businesses should take several proactive steps to protect themselves.
What is IC3?
IC3 is an online platform hosted by the FBI, which exists to provide the public with a trusted place to report cybercrime to the FBI. Since its inception in 2000, the IC3 has received 5.6 million complaints, and has averaged approximately 440,000 complaints over each of the last five years. The complaint figure for 2020 is nearly double that average.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey M. Dennis, Newmeyer DillionMr. Dennis may be contacted at
jeff.dennis@ndlf.com
ISO’s Flood Exclusion Amendments and Hurricane Ian Claims
October 03, 2022 —
Randy J. Maniloff - White and Williams LLPI understand that it may seem early to be addressing possible coverage issues, under homeowner’s policies, for the devastation in Florida caused by Hurricane Ian. At the moment, those affected are dealing with a major catastrophe and possibly life-altering situation.
But I’m a realist. While we all have those impacted in our thoughts and prayers, that’s not going to rebuild the state or people’s lives. Money is. And when it comes to the source of money to do so, insurance will be far and away the first and principal place that people turn.
Indeed, even before it started to rain, Florida Governor DeSantis was discussing the availability of insurance for his citizens, as well as plenty of articles written forecasting how significant the insurance impact could be. If Covid-19 taught us anything about the pursuit of insurance, the discussion begins the second the need arises.
When it comes to insurance coverage for hurricanes, the starting place is always the same. Homeowner’s [and commercial property] policies generally cover wind damage and exclude flood damage. For flood coverage, a flood policy is needed, offered by the National Flood Insurance Program or the private market.
Read the court decisionRead the full story...Reprinted courtesy of
Randy J. Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
Mediation Fails In Federal Lawsuit Seeking Damages From Sureties for Alleged Contract Fraud
August 17, 2020 —
Richard Korman - Engineering News-RecordAfter mediation failed, a federal whistle blower lawsuit over alleged fraud against two contractors, which also targets sureties and a surety bond producer, is moving forward. The parties have asked a U.S. district court judge in Washington, D.C. to rule on outstanding motions in preparation for a possible trial.
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of