Duke Energy Appeals N.C. Order to Excavate Nine Coal Ash Pits
April 17, 2019 —
Mary B. Powers - Engineering News-RecordDuke Energy Progress said April 11 it will appeal the North Carolina Dept. of Environmental Quality’s order issued earlier this month to excavate nine remaining large coal ash pits at six power plants in the state and move ash to lined landfills; the firm claims the new mandate at sites previously deemed low-risk will cost up to $5 billion to implement.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com
Prejudice to Insurer After Late Notice of Hurricane Damage Raises Issue of Fact
January 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment on admittedly late notice because prejudice to the insured remained an issue of fact. Guzman v. Scottsdale Ins. Co., 2021 U.S. Dist. LEXIS 219625 (S.D. Fla. Nov. 15, 2021).
The insured first noticed water leaking into his kitchen from the roof during Hurricane Irma on September 10, 2017. Various attempts were made by the insured to fix the leak, but none were successful. After the hurricane, the roof continued to leak whenever it rained. Notice was finally given to Scottsdale, the insurer, on April 19, 2020.
Scottsdale retained structural engineer Nazario Ramirez, who inspected the property twice. He also had photographs of the rapids. Ramirez denied being prejudiced during his inspections. Based on the pictures aerial photography and weather research, he determined that the damage was caused by underlayment failing, which could have resulted from age and deterioration or poor construction. When Scottsdale's corporate representative was deposed, he testified that Ramirez was able to determine the cause of the damage to the roof.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
SIGAR Report Finds +$15 Billion in “Waste, Fraud and Abuse” in Afghanistan
August 20, 2018 —
Pillsbury's Construction & Real Estate Law Team - Gravel2GavelToday, our colleagues Alex Ginsberg, Glenn Sweatt and Kevin Massoudi published their Client Alert on a recently issued Special Inspector General for Afghanistan Reconstruction (SIGAR) Report that finds over $15 billion in waste, fraud and abuse. In New SIGAR Report Identifies “Waste, Fraud and Abuse” in Afghanistan, our colleagues identify key takeaways from the Report include:
- The Report reviewed public spending for Afghanistan reconstruction efforts and identified at least $15.5 billion in waste, fraud and abuse.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Missouri Construction Company Sues Carpenter Union for Threatening Behavior
February 10, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to KMOV News, Raineri Construction Company in Missouri filed suit against the Local Carpenters’ District Council claiming employees had been “stalked and threatened” by the union. However, the Carpenters Union “denies the allegations” and said “it has the right to protest against a company that doesn’t always meet the union standards for pay and benefits.”
Tony Raineri, one of the construction company’s executives, said to KMOV News: “For me it wasn’t such a big deal until they started making threats of bodily harm, started following me and my wife to our home, started following my employees to their homes.”
KMOV News reported that a “union representative told News 4’s Craig Cheatham that no one acting on behalf of the Carpenters Union ever threatened, harassed or stalked Raineri, his employees or their clients.”
Read the court decisionRead the full story...Reprinted courtesy of
Life After McMillin: Do Negligence and Strict Liability Causes of Action for Construction Defects Still Exist?
January 24, 2018 —
Thomas Balestreri and Amanda Crawley - Balestreri, Potocki, & HolmesThe ruling is in but the battle will likely continue over the practical application of SB 800. On January 18, 2018 the California Supreme Court issued its decision in
McMillin Albany, LLC v. Superior Court (Van Tassel) (January 18, 2018, S229762) __ Cal.4th __, holding that the statutory prelitigation scheme in The Right to Repair Act (“the Act”) that provides for notice and an opportunity for the Builder to repair defects applies to all claims for construction defects in residential construction sold on or after January 1, 2003, regardless whether the claim is founded on a violation of the Act’s performance standards or a common law claim for negligence or strict liability. (
McMillin Albany, LLC v. Superior Court (Van Tassel) (January 18, 2018, S229762) __ Cal.4th __.) With this holding, has the Court ruled that common law causes of action for construction defect still survive? If so, what will they look like and what standards will be applied?
The short answer is that it appears that common law causes of action still survive, at least for now, but it is not clear from this decision what they will look like and what standards will apply.
Portions of the decision seem to suggest that the Act is the sole and exclusive remedy for construction defect claims: “…even in some areas where the common law had supplied a remedy for construction defects resulting in property damage but not personal injury, the text and legislative history [of the statute] reflect a
clear and unequivocal intent to supplant common law negligence and strict product liability actions under the Act.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 6].) (Italics added for emphasis) However, at the end of the decision, the Court seems to be saying that there may still be a place for common law claims for negligence and strict liability alongside the Act but that these causes of action may be subject to the performance standards in the Act.
The
McMillin case went up to the Supreme Court on a procedural issue: whether a common law action alleging construction defects resulting in both economic loss and property damage is subject to the Act’s prelitigation notice and cure procedures. The Van Tassels had dismissed their claims under the Act opting to proceed solely on their common law claims including negligence and strict liability. McMillin sought a stay to force the Van Tassels to comply with the Act’s prelitigation procedures. The Supreme Court held that the Van Tassels must comply with the statutory procedures and affirmed the stay issued by the trial court. But the question remained: now that the Van Tassels were left only with common law claims, how would they proceed under the Act?
To understand how the Court dealt with this question, one must first understand how the Court dealt with the narrow procedural question presented by the case. The Court provides a very detailed, clear explanation of the reasons why it felt the Legislature intended for all construction defect claims involving residential construction must comply with the prelitigation requirements of the Act. In summing up its conclusions the Court makes three definitive holdings.
First, for claims involving economic loss only—the kind of claims involved in
Aas—the Court holds that the Legislature intended to supersede
Aas and provide a statutory basis for recovery. (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 10].) In other words, the Court clearly agrees that the Act was meant to allow recovery of damages based solely on economic damages. No surprise there. Second, the Court held for personal injuries, the Legislature made no changes to existing law that provides common law remedies for the injured party. (Id.) Nobody has ever contested that. Finally, the Court held that for construction defect claims involving property damage and not just economic loss “the Legislature replaced the common law
methods of recovery with the new statutory scheme.” (
Id.,) (Italics added for emphasis.)
In other words, the Court is not saying that negligence and strict liability are not permitted causes of action. The Court is merely stating that these causes of action must comply with the Act’s statutory scheme just as the same as a claim for economic loss. Here the Court is focusing on the procedure that must be followed. “The Act, in effect, provides that construction defect claims not involving personal injury will be treated the same procedurally going forward whether or not the underlying claims gave rise to any property damage.” (
Id.)
Having laid out its fundamental premise, the Court then deals with Plaintiff’s arguments regarding the intent of the Legislature and makes light work of them all. In the process, the Court disapproves
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal. App. 4th 98, and
Burch v. Superior Court (2014) 223 Cal. App. 4th 1411, to the extent they are inconsistent with the views expressed in the
McMillin opinion.
This is where the decision gets interesting. The Court reminds us that the Van Tassels had dismissed their statutory causes of action for violation of the performance standards under Section 896. One would think at that point that Plaintiffs had to be wondering if they had any claims left given that the Court had ruled that the Act was the sole means of recovery for construction defects. Not so fast. The Court points out that the complaint still rests on allegations of defective construction and that the suit remains an “ ‘action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction’ of the plaintiffs’ homes (§896)
and McMillin’s liability under the Van Tassels’ negligence and strict liability claims depends on the extent to which it [McMillin] violated the standards of sections 896 and 897.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 19].) (Emphasis added.) WHAT DID THE COURT JUST SAY? Did the Court just say that a plaintiff could bring a common law cause of action for negligence or strict liability based on a violation of the performance standards under Section 896? What exactly would that claim look like? What would be the elements of such a cause of action?
To answer these questions, the Court states in the very next paragraph, which also happens to be the last paragraph in the decision: “In holding that claims seeking recovery for construction defect damages are subject to the Act’s prelitigation procedures regardless of how they are pleaded,
we have no occasion to address the extent to which a party might rely upon common law principles in pursuing liability under the Act.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 19].) (Italics added for emphasis) Is the Court answering “No” to the questions posed above? Probably not. It is simply following the age old rule that an appellate court will
not rule on an issue that is not specifically presented by an appeal, leaving that question for another day.
All we know for sure from
McMillin is that every claim for construction defects falling within the scope of the Act must follow the prelitigation procedure. There are no hall passes for negligence and strict liability. The larger question posed by the last two paragraphs in the decision, is whether the law recognizes a cause of action for negligence and strict liability for construction defects based on the standards in Section 896. The answer will have to be worked out by judges and trial attorneys in courtrooms across the State! The parameters of this hybrid cause of action that the Court seems to have posited will need more careful consideration than can be offered on first reading of
McMillin v. Superior Court.
Read the court decisionRead the full story...Reprinted courtesy of
Balestreri, Potocki, & Holmes
Who Will Pay for San Francisco's $750 Million Tilting Tower?
February 02, 2017 —
James Tarmy & Kartikay Mehrotra – BloombergNina Agabian, a retired director of research in global health science at the University of California, bought a 29th-floor apartment in San Francisco’s Millennium Tower in 2010. “It was supposed to be a wonderful building,” she said in January, sitting in a leather chair in the building’s vast, low-lit, owner's-club level. “For many of us, who left our business lives to start our older years, this had become a nice, comfortable place.”
The building, which opened in 2008 and was touted as the most luxurious tower in San Francisco, became a beacon of the city’s burgeoning wealth, attracting tech millionaires, venture capitalists, and even the San Francisco 49ers retired quarterback Joe Montana.
The 58-story tower's shine faded on May 10, 2016, when Agabian attended a homeowners association meeting and was informed that the building had sunk 16 inches into the earth and tilted over 15 inches at its tip and 2 inches at the base, according to suits filed by residents and the city of San Francisco. “You can imagine how distressed we were to know that, for one, our lifetime investment and savings are at risk,” she said. “And we have no idea whether or not there’s a fix to it, and if there is a fix to it, what it will entail.”
Reprinted courtesy of
James Tarmy, Bloomberg and
Kartikay Mehrotra, Bloomberg
Mr. Tarmy may be followed on Twitter @jstarmy
Mr. Mehrotra may be followed on Twitter @kartikaym
Read the court decisionRead the full story...Reprinted courtesy of
Conflict of Interest Accusations may Spark Lawsuit Against City and City Manager
February 07, 2014 —
Beverley BevenFlorez-CDJ STAFFCasper, Wyoming Councilman Craig Hedquist—who is also owner of Hedquist Construction—has been “accused of violating state and local conflict-of-interest laws,” according to the Star-Tribune. In response, Hedquist “is threatening a lawsuit against City Manager John Patterson, the city of Casper and ‘possibly others,’ according to a letter obtained by the Star-Tribune.”
The letter, which was sent to City Attorney William Luben by Hedquist attorney John Robinson, “demands the city preserve, from Aug. 1, 2012, on, all records of communication and consultation with attorneys and investigators, along with minutes, notes, recordings, executive sessions and digital data regarding Hedquist and Hedquist Construction.”
City Manager John Patterson told the Star-Tribune that “he was unaware of the letter and didn't know what the lawsuit might be about.”
Hedquist maintains that there was never a conflict of interest: “The general and expected practice for the Casper City Council members is to not vote on matters in which a council member may have a personal interest and record this recusal in the public record,” Hedquist said, as reported by the Star-Tribune. “I have done this on all contract matters regarding Hedquist Construction.”
Read the court decisionRead the full story...Reprinted courtesy of
Walkability Increases Real Estate Values
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFCNBC reported that environmentally-conscious Millennials are looking for homes that are within walking or biking distance to stores and work. The “areas that offer so-called walkability should see more home buyers and renters than those that don't.”
"Cities that want to thrive in our new economic and demographic realities will need to find ways to create and support more of these dynamic, productive walkable districts that are in high demand," Geoff Anderson, CEO of Smart Growth America, told CNBC. Anderson, “in conjunction with George Washington University School of Business, released a new report ranking the walkability of the nation's 30 largest metropolitan areas.”
Read the court decisionRead the full story...Reprinted courtesy of