Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 —
CDJ STAFFActing on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Condominium Exclusion Bars Coverage for Construction Defect
August 17, 2011 —
Tred R. Eyerly - Insurance Law HawaiiCoverage was denied under the policy’s condominium exclusion in California Traditions, Inc. v. Claremont Liability Ins. Co.,2011 Cal. App.LEXIS912 (Cal. Ct. App., ordered published July 11, 2011).
California Traditions was the developer and general contractor for a housing development. California Traditions subcontracted with Ja-Con to perform the rough framing work for 30 residential units. The project had 146 separate residences that were freestanding with no shared walls, roof, halls, or plumbing or electrical lines. To allow a higher density development, the project was developed, marketed and sold as condominiums.
The purchaser of one of the units filed a complaint against California Traditions alleging property damage from the defective construction. California Traditions cross-complained against Ja-Con.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Favors Finding Construction Defects as an Occurrence
September 23, 2019 —
Ashley L. Cooper - SDV InsightsA recent Illinois Appellate Court’s decision in, Acuity Ins. Co. v. 950 West Huron Condominium Owners Association, 2019 IL App (1st) 180743 (2019), strengthens Illinois’ precedent favoring construction defects as an occurrence under a Commercial General Liability (“CGL”) insurance policy. Acuity also broadens an insurance carrier’s obligation to defend its insured against construction defect allegations.
In Acuity, the court determined whether claims for construction defect filed against a subcontractor, triggered a duty to defend under a CGL policy. To make its determination, the court focused on the subcontractor’s scope of work. The court notes that a subcontractor normally contracts for a discrete scope of work on a project. Unlike a general contractor, who has control over or contractual obligations for all aspects of the project, a subcontractor does not have those board responsibilities. The court explained that “[f]rom the eyes of the subcontractor, the ‘project’ is limited to the scope of its own work, and the precise nature of any damage that might occur to something outside of that scope is as unknown or unforeseeable as damage to something entirely outside of the construction project.”
Accordingly, the court in Acuity held that when a complaint alleges that a subcontractor’s negligence caused damage to a part of the construction project outside of the subcontractor’s scope of work, the allegations are enough to trigger the insurer’s duty to defend the subcontractor under a CGL policy. The court’s decision in Acuity relied on a similar Illinois Appellate Court decision, Milwaukee Mut. Ins. Co. v. J.P. Larsen, Inc., 956 N.E.2d 524 (Ill. App. 2011). In Larsen, the court reached a similar conclusion where a third-party complaint by a general contractor against a subcontractor alleged that the subcontractor’s improper window caulking caused water intrusion and property damage to other parts of the building. The court in Larsen held that because the complaint alleged not only construction defects, but also damage to other property outside the subcontractor’s scope of work, the insurer had a duty to defend the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley L. Cooper, Saxe Doernberger & Vita, P.C.Ms. Cooper may be contacted at
alc@sdvlaw.com
Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Senate Advances Bad Faith Legislation
July 18, 2018 —
TLSS Insurance Law BlogNew Jersey is the latest to join the list of states that have enacted or are considering enacting legislation that would authorize policyholders to file civil suits against first-party insurers for unfair business practices, such as unreasonably delaying or denying benefit payments, engaging in false advertising, or otherwise committing a wide range of unfair or deceptive practices.
On June 7, the New Jersey Senate passed a bill entitled the New Jersey Insurance Fair Conduct Act. The Act would create a new statutory cause of action pursuant to which a first-party insurer would be liable for bad faith based on a single statutory violation, thereby entitling an aggrieved policyholder to collect triple damages and attorneys’ fees. The proposed legislation is now before the state’s General Assembly for further consideration.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
Dispute Review Boards for Real-Time Dispute Avoidance and Resolution
August 20, 2019 —
Neal J. Sweeney, Esq. - ConsensusDocsThe use of dispute tribunals generally referred to as Dispute Review Boards or DRBs on major projects has matured. Use of a DRB cannot guarantee elimination of post-project litigation, but when used properly, a DRB can be an enormously effective tool to avoid and resolve disputes rapidly and during construction.
The modest out-of-pocket costs of a DRB can pay big dividends. DRBs offer the opportunity to shorten the life cycle of a dispute by requiring the principals to confront and address the merits of their dispute, rather than simply hunkering down and focusing on posturing and preparing for arbitration or litigation. Even when a DRB cannot immediately resolve a dispute, the process can still facilitate subsequent settlement and cost-effectively prepare both parties for formal adjudication. DRBs can also enhance communications and help the parties avoid and resolve problems before they spiral into disputes.
DRBs were first and are most widely used on big civil and infrastructure projects, but the benefits of a DRB extend equally to major building projects, particularly hospitals, and industrial projects and should be used in those sectors.
Read the court decisionRead the full story...Reprinted courtesy of
Neal J. Sweeney, Esq., Jones Walker LLPMr. Sweeney may be contacted at
nsweeney@joneswalker.com
How to Lose Your Contractor’s License in 90 Days (or Less): California and Louisiana
November 15, 2021 —
Rafael Boza - Gravel2Gavel Construction & Real Estate Law BlogHaving your Contractor’s License up and running to perform work when needed, where needed, is an indispensable compliance matter that contractors face every year. However, this indispensable process may also be cumbersome and time consuming. Knowing the regulations applicable to your business in each state and what to do, how to do it, and when to do it, is of critical importance to maintain compliance and your ability to work in different states.
In this post we will do a high-level review of reporting obligations in California and Louisiana.
California’s
Contractors’ State License Law, Bus. & Prof. Code §§ 7000 et seq., requires licensees to report various information to the Contractors State License Board (CSLB) “within 90 days” of the effective date or event. Louisiana State
Licensing Laws and Regulations, R.S. §§ 37:24 et seq. and La. Admin. Code tit. 46, XXIX, §§ 101 et seq. also require similar reporting to the Louisiana State Licensing Board for Contractors (LSLBC), sometimes “within 15 days” of the event.
Read the court decisionRead the full story...Reprinted courtesy of
Rafael Boza, PillsburyMr. Boza may be contacted at
rafael.boza@pillsburylaw.com