Tips for Drafting Construction Contracts
May 04, 2020 —
Stuart Rosen - Construction ExecutiveWhen negotiating a construction contract, a contractor and its advisers must first determine the areas of greatest concern.
For example, if the contractor believes that the drawings that were prepared by the architect and other design professionals are deficient, the contractor may want to reference those deficiencies in the contract. The contractor should emphasize that it is not responsible for the drawings and to the extent the project schedule is extended to allow the parties to address such issues with the drawings, the contractor would be entitled to additional compensation.
This article provides contractors with additional tips, with a broad focus on project delays, for their protection when negotiating and drafting construction contracts, and helps contractors understand the rationale for such tips to better prepare contractors in such negotiations.
Contractor’s liability to the owner for delay damages
It is imperative that the contract include a waiver of claims for consequential damages. AIA Document A201TM – 2017 includes such a waiver, which provides, in pertinent part, “The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract … This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14.”
Reprinted courtesy of
Stuart Rosen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rosen may be contacted at
srosen@proskauer.com
There's No Such Thing as a Free House
April 01, 2015 —
Megan McArdle – BloombergShould people be able to get a free house by refusing to pay their mortgage?
That's the question Florida has to answer. The housing crisis is over, and the housing market is healing itself, though slowly in some places. But a backlog of foreclosures still remains ... and it has been going on so long that some homes are now past the statute of limitations for collecting debt. Lawyers for the homeowners are arguing that this means they get to keep the house. Lawyers for the banks are, unsurprisingly, arguing that each month they fail to pay the mortgage payment starts the statutory clock anew.
Both arguments create problems if the courts endorse them. If failing to pay really restarted the clock every month, then there wouldn't be a statute of limitations on debt -- creditors could just keep sending you bills forever and dun you right up to the edge of your grave. There's a very good reason that we have statutes of limitations on most crimes and most debts: The law recognizes that our interests in justice and contract rights must be balanced against other considerations. People need to be able to plan their lives without decades-old problems coming back to bite them, and also, as cases age, they get harder and harder to prove as witnesses die, evidence gets lost and memories fade.
Read the court decisionRead the full story...Reprinted courtesy of
Megan McArdle, BloombergMs. McArdle may be contacted at
mmcardle3@bloomberg.net
Hydrogen—A Key Element in the EU’s Green Planning
December 07, 2020 —
Matthew Oresman & Henrietta Worthington - Gravel2Gavel Construction & Real Estate Law BlogGettyImages-1150744671-300x225Hydrogen is gaining global recognition for its potential as a key player in the energy transition. Investors and businesses are exploring opportunities across multiple sectors, including energy, manufacturing, transport and finance. According to a report by Bloomberg, the current pipeline for global hydrogen projects is worth an estimated $90 billion. The EU is not going to be left behind, with a focal point of its Green Deal being on hydrogen.
The EU’s executive branch (the European Commission or EC) has confirmed its commitment to increasing hydrogen projects across the bloc, with a priority on green hydrogen. Its Hydrogen Strategy, released in March, states that hydrogen is “essential to support the EU’s commitment to reach carbon neutrality by 2050 and for the global effort to implement the Paris Agreement while working towards zero pollution.”
The EU’s executive branch (the European Commission or EC) has confirmed its commitment to increasing hydrogen projects across the bloc, with a priority on green hydrogen. Its Hydrogen Strategy, released in March, states that hydrogen is “essential to support the EU’s commitment to reach carbon neutrality by 2050 and for the global effort to implement the Paris Agreement while working towards zero pollution.”
Reprinted courtesy of
Matthew Oresman, Pillsbury and
Henrietta Worthington, Pillsbury
Mr. Oresman may be contacted at matthew.oresman@pillsburylaw.com
Ms. Worthington may be contacted at henrietta.worthington@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
More In-Depth Details on the Davis-Bacon Act Overhaul
November 06, 2023 —
Seth C. Wiseman & Angela M. Richie - Construction ExecutiveThe U.S. Department of Labor’s finalization of a
rule updating the Davis-Bacon Act, the federal law that governs how prevailing wages for federal construction projects can be determined, will have a significant impact on contractors and workers alike in the construction industry. The new rule, in effect, adopts the 30% rule, meaning that the prevailing wages must be equal to the wage paid to at least 30% of workers of a particular classification in a particular area. The new rule also implements a new anti-retaliation provision, specifically protecting construction workers who raise concerns about payment practices from adverse employment actions. The timing of this new rule is particularly significant for contractors, as it will likely raise the cost of labor for contractors at a time when the Infrastructure Investment and Jobs Act and the CHIPS Act are providing additional funding for federal projects across the country. Thus, it is important for all parties in the construction industry to understand the updated rule in order to evaluate the short-term impacts on their respective projects and long-term impact on their respective businesses.
Reprinted courtesy of
Seth C. Wiseman & Angela M. Richie, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Wiseman may be contacted at swiseman@grsm.com
Ms. Richie may be contacted at arichie@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Succeeds At the Supreme Court Against Public Owner – Obtaining Fee Award and Determination The City Acted In Bad Faith
September 20, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCA contractor won a rare but much-deserved victory at the Supreme Court on July 8, 2021 in Conway Construction Co. v. City of Puyallup, 197 Wn.2d 825, 490 P.2d 221 (2021). The case, which involved an aggressive stance by a public owner:
- confirmed that the public owner bears the burden of demonstrating a termination for default is justified,
- reaffirmed the requirement to provide an opportunity to cure, and
- rejected the public owner’s attempts to escape its own contract language that the contractor relied upon.
John Ahlers and Lindsay Watkins of Ahlers Cressman and Sleight and Jamie Becker of Osborne Construction submitted the Amicus Brief for the Associated General Contractors (AGC) of Washington in support of Conway to the Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
White and Williams Elects Four Lawyers to Partnership, Promotes Six Associates to Counsel
January 13, 2017 —
White and Williams LLPWhite and Williams is pleased to announce the election of Edward Beitz, Justin Fortescue, Jennifer Santangelo and Amy Vulpio to the partnership and the promotion of Paul Briganti, Joshua Galante, Dana Spring Monzo, George Morrison, Craig O’Neill and Steven Urgo from associate to counsel.
The newly elected partners and promoted counsel represent the wide array of practices that White and Williams offers its clients, including bankruptcy, corporate, finance, healthcare, insurance coverage, labor and employment, real estate and reinsurance. These lawyers have earned their elevations based on their contributions to the firm and their practices.
“We are thrilled to elect these four lawyers to the partnership and promote six associates to counsel. These promotions are representative of the breadth of services and deep bench that we have to offer at White and Williams,” said Patti Santelle, Managing Partner. “The election of our new partners and promotion of our counsel is a reflection of their success and dedication as well as the continued health of the firm.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Avoiding 'E-trouble' in Construction Litigation
September 10, 2018 —
Judah Lifschitz - Construction ExecutiveDuring the 2016 presidential election, the FBI subpoenaed Hillary Clinton's emails after she used a private email server during her time as Secretary of State. Separately, the more recent investigation into Donald Trump’s campaign policy adviser, George Papadopoulos, resulted in scrutiny over both his email and social media.
As shown the above examples, there are damaging effects of electronically stored information in politics, but how does it impact the construction industry?
If not used carefully and properly, emails will serve as “truth serum” in court. Attorneys can simply read an email to know employees’ thoughts or actions, meaning an impulsive email or social media post will most likely come back to haunt the company. Requests for ESI are inevitable in litigation today and the production of inappropriate emails and other ESI open the door for an opposing attorney to argue that a company fosters a culture of uncouth, unprofessional and unfocused project management.
Reprinted courtesy of
Judah Lifschitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lifschitz may be contacted at
lifschitz@slslaw.com
Vacant Property and the Right of Redemption in Pennsylvania
April 06, 2016 —
Suzanne Prybella – White and Williams LLPIn Pennsylvania, pursuant to the Municipal Claims and Tax Liens Act (53 P.S. §7293(a)) (the Act), the owner of a property sold under a tax or municipal claim may redeem the sold property at any time within nine months after the date of acknowledgment of the sheriff's deed by, in general, paying the amount of the debt. However, there is a caveat contained in the Act with respect to vacant property, which states that “there shall be no redemption of vacant property by any person after the date of the acknowledgment of the sheriff's deed.” (53 P.S. §7293(c)). In Brentwood Borough School District v. HSBC Bank USA, N.A., 111 A.3d 807 (Pa. Commw. Ct. 2015), a case of first impression before the Commonwealth Court of Pennsylvania, the court addressed the definition of “vacant property” under the Act and the timing of a petitioner to invoke the right of redemption with respect to vacant property.
Read the court decisionRead the full story...Reprinted courtesy of
Suzanne Prybella, White and Williams LLPMs. Prybella may be contacted at
prybellas@whiteandwilliams.com