Insurance Alert: Insurer Delay Extends Time to Repair or Replace Damaged Property
November 26, 2014 —
Valerie A. Moore & Christopher Kendrick – Haight Brown & Bonesteel LLPIn Stephens & Stephens XII v. Fireman's Fund Ins. (No. A135938, filed November 24, 2014), the plaintiffs obtained property insurance on a warehouse. Within a month, it was discovered to be stripped of all wiring and metal. Fireman's Fund paid for emergency repairs but nothing more, concerned that the damage had occurred outside the policy period.
The policy provided for valuation of either "replacement cost," meaning the expenditure required to replace the damaged property with "new property of comparable material and quality," or "actual cash value," defined as the actual, depreciated value of the damaged property. For replacement cost, Fireman’s Fund was not required to pay "until the lost or damaged property is actually repaired ... as soon as reasonably possible after the loss or damage," and only "[t]he amount [the insured] actually spend[s]...."
In the subsequent bad faith lawsuit, the jury awarded the full cost of repair, despite there being no repairs. The appeals court reversed, holding that there was no right to an immediate award for the costs of repairing the damage; however, the court nonetheless held that the insured was entitled to a "conditional judgment," awarding those costs if repairs were actually made.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Exception to Watercraft Exclusion Does Not Apply
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that an additional insured was not entitled to coverage despite an exception to the watercraft exclusion. Holden v. U.S. United Ocean Serv., LLC, 2014 U.S. App. LEXIS 15954 (5th Cir. Aug. 19, 2014).
United entered a contract with Buck Kreihs Company, Inc. under which Buck Kreihs would perform ship-repair work for United. Under the contract, Buck Kreihs would indemnify United for all liabilities arising out of the work or services performed by Buck Kreihs for United. The contract further provided that Buck Kreihs was to procure general liability coverage and name United as an additional insured. Buck Kreihs did so under a policy issued by St. Paul.
Holden, an employee of Buck Kreihs, was injured while preparing to remove a gangway that led from a dock at Buck Kreihs's facility to a barge owned by United. Holden sued United, which tendered to St. Paul as an additional insured. St. Paul denied coverage under the policy's watercraft exclusion. Holden and United settled. United pursued its third party suit against St. Paul. The district court granted summary judgment to St. Paul.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Supreme Court McMillin Ruling
January 24, 2018 —
Don MacGregor - CDJ STAFFReaction to the recent California Supreme Court ruling in McMillin Albany LLC v. The Superior Court of Kern County has been both swift and diverse, with many notable California law firms weighing in on the potential impact this landmark ruling may have on the Construction Industry and construction defect litigation. In our ongoing desire to serve as a meaningful and comprehensive provider of news and information for Construction and Claims Professionals, we have included a selected number of the submissions we have received regarding this very important judicial ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Get Your Contracts Lean- Its Better than Dieting
January 13, 2020 —
Brian Perlberg, Esq. - ConsensusDocsI recently took the AGC Lean Construction Educations Program Units 1-7. After studying diligently, I’m happy to say that I passed the exam and earned my CM-Lean credential. Surprisingly, this makes me the first attorney to earn this distinction out of over 1,200 CM-Lean holders. So why is a construction attorney learning about lean? After all, this was my first exam in 20 years since I took the bar.
Well, according to McKinsey Global Institute, construction actually became less productive from 1995 through 2009. When it comes to efficiency, construction still lags significantly behind the manufacturing sector and the overall economy. Construction contracts – what we sign and the way in which we negotiate them, or lack thereof – is a principal reason why construction productivity is stagnant.
Contracting under an integrated lean project delivery method (ILPD) and incorporating Lean construction tools is the most powerful means to increase efficiency and add-value to owners. Owners are the client’s end-users of construction projects. ConsensusDocs has taken a leadership role in publishing the first standard ILPD contract which is an integrated form of agreement (IFOA). The ConsensusDocs 300 Integrated Project Delivery (IPD™) provides an off-the-shelf solution to contract utilizing lean tools. Not every owner can or is comfortable using an IPD approach. Consequently, ConsensusDocs produced the ConsensusDocs 305 Construction Lean Construction Addendum last year to provide an option for contracting for lean on Construction Management at-Risk and design-build projects. Some people call this approach IPD-lite or IPD’ish. Some disfavor such terms, because those terms have been used loosely on projects that aren’t very Lean.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Perlberg, Esq., Executive Director and Senior Counsel of ConsensusDocsConsensusDocs may be contacted at
support@consensusdocs.org
School Board Sues Multiple Firms over Site Excavation Problem
February 12, 2013 —
CDJ STAFFA West Virginia school board has filed a lawsuit against four companies over the construction of the Lewisburg Elementary School. The main allegation is that Carpenter Reclamation Inc. excavated the site deeper than was called for, which then incurred greater expenses for the subsequent contractors, and further that the liner installed by Carpenter Reclamation was defective. The suit also names Western Surety, which issued a performance bond for Carpenter Reclamation.
The school board claims that Carpenter’s failure to fix the problem, required $5,800 in evaluation, review, and testing. Further, the plumbing and lead contractors had additional expenses of $10,587 and $212,645 because of the deeper foundation. The school board has also named these firms, Dougherty Company, Inc. and Swope Construction, in the lawsuit. Ron Mallory, the president of Swope Construction said that the school board’s dispute was “with the site contractor, not with us,” noting that they did corrective work under a change order.
Read the court decisionRead the full story...Reprinted courtesy of
Gary Bague Elected Chairman of ALFA International’s Board of Directors
November 17, 2016 —
Gary A. Bague – Haight Brown & Bonesteel LLPDuring ALFA International’s (ALFA) Annual Business Meeting on October 28, the membership elected Gary Bague to serve as the Chairman of the Board of Directors. Gary’s term as Chairman will run through October 2018. After he completes his term as Chairman, Gary will continue to serve on the Board of Directors as Chair Emeritus for two years.
The Board of Directors is responsible for establishing all policies relative to accomplishing the purposes of ALFA, recommending the Corporation’s budget to the Membership, approving applications for membership, supervising the work of the Chief Executive Officer, and otherwise managing the business and affairs of ALFA. As Chairman of the Board, Gary will preside over all meetings of the Executive Committee, Board of Directors, and Membership. He will also serve as an ex officio member of all committees, and will have the duties of a president of the Corporation.
Read the court decisionRead the full story...Reprinted courtesy of
Gary A. Bague, Haight Brown & Bonesteel LLPMr. Bague may be contacted at
gbague@hbblaw.com
Real Estate & Construction News Round-Up (11/30/22) – Proptech Trends, Green Construction, and Sustainable Buildings
December 13, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores 4 key trends expected to impact proptech in 2023, global investment in green construction technologies, sustainable buildings and their perceived value for tenants in Europe, and more.
- Sitting at the crossroads between real estate and technology, proptech has experienced significant growth, which is expected to accelerate via 4 key trends in 2023. (Zain Jaffer, Forbes)
- Global investment in green construction technologies reached $2.2 billion in 2022, with legislation and technological innovation serving as the key driving forces behind this growth. (Jennifer Kite-Powell, Forbes)
- In Europe, sustainable buildings have increased the asset values for commercial real estate managers, with tenants willing to pay more for efficient buildings. (David Worford, Environment + Energy Leader)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
New Megablimp to Deliver to Remote Alaskan Construction Sites
January 13, 2017 —
Ryan W. Sternoff - Ahlers & Cressman PLLC BlogFor nearly 20 years, Lockheed Martin has been working on developing a “Hybrid Airship” that may transform the ability to construct facilities in remote project locations.[i]
On September 13, 2016, the Daily Journal of Commerce reported that the first of these “Hybrid Airships,” which can land in snow, ice, gravel, and water, are set to deliver from a facility operated by PRL Logistics in Kenai, Alaska, beginning in 2019.[ii] PRL will be operating the blimps in partnership with UK-based Straightline Aviation who placed the first order for the airships this year. According to PRL, the hope is that the airships will provide low cost solutions for moving freight in Alaska, where runways and roads are not always available. The helium-lifted behemoth blimps have space for 47,000 pounds of cargo and 18 passengers and cost about $40 million dollars.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan W. Sternoff, Ahlers & Cressman PLLCMr. Sternoff may be contacted at
rsternoff@ac-lawyers.com