When Construction Defects Appear, Don’t Choose Between Rebuilding and Building Your Case
October 11, 2021 —
Curtis Martin - ConsensusDocsWhen construction defects occur during construction, they intensify pressure from a schedule that may already be tight. Defects must be analyzed, confirmed, removed, and replaced and this can be time consuming. Or course, a construction schedule rarely anticipates defects, demolition, and rework and the owner will still expect the project to be completed on time; however, pressing forward with immediate remediation may have unintended consequences.
Before starting demolition, consider the evidentiary doctrine of spoliation. Spoilation occurs when a party destroys or unreasonably deprives another party of evidence and courts have imposed sanctions on a party that deprives an opponent of evidence. The doctrine has historically concerned documents, but its application has extended to electronic data, and courts also apply it to building conditions in construction defects cases. So, before tearing out or fixing defective work, consider the need to allow the opposing party to inspect, test and document it.
Imagine this scenario. The concrete in a slab placed by your subcontractor shows low compressive strength results in the 28-day cylinder tests. Tearing out the slab and replacing it will put you at least a month behind schedule and you don’t want to waste any time before removing and replacing it. Nevertheless, while you’re rebuilding the defective slab, be mindful that you are also building a case. If you plan to recover the costs you incur because of the defective concrete from the responsible parties, you should allow the subcontractor (and possibly the concrete supplier and other implicated parties) to examine, preserve, and/or test the work in question. Failure to do so may subject you to spoliation sanctions and jeopardize your right to recover damages.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis Martin, Peckar & AbramsonMr. Martin may be contacted at
cmartin@pecklaw.com
The Prompt Payment Act Obligation is Not Triggered When the Owner Holds Less Retention from the General Contractor
October 27, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCMost states have laws known as “prompt payment” statutes which govern the timing of payments on public works projects[i] from project owners to general contractors, and from general contractors to subcontractors.[ii] The purpose of these statutes is to ensure that contractors and subcontractors who may have less leverage than the project owners and prime contractors, respectively, are paid for their work on a timely basis.
Prompt Payment Act cases are rare, and, since many of the prompt payment statutes are founded on the same principles, when we come across a Prompt Payment Act case, it is “blog worthy.” This dispute arose from the construction of the Exposition Light Rail Line Project connecting downtown Los Angeles with Culver City on which FCI/Fluor/Parsons (“FFP”) was the prime contractor, and Bloise Construction, Inc. (“Bloise”) was the excavation subcontractor to FFP. Under the prime contract, Expo,[iii] the owner, was permitted to withhold ten percent of the payments owed to FFP, and FFP, pursuant to its subcontract with Bloise, was entitled to also withhold ten percent of the payments to Bloise as retention.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Mediation in the Zero Sum World of Construction
September 26, 2022 —
Christopher G. Hill - Construction Law MusingsConstruction is a zero sum game. What do I mean by that? I mean that even where you, a construction professional with a great construction lawyer, have reviewed and edited a subcontract presented to you or provided a well-drafted contract to the other party that contains an attorney fees provision, every dollar that you spend on litigation is a dollar less of profit.
Couple the fact that no construction company can or should bid or negotiate work with an eye toward litigation (aside from having a well written contract that will be enforced to the letter here in Virginia). Particularly on “low bid” type projects, contractors and subcontractors cannot “pad” their bids to take into account the possibility of attorney fees, arbitration, or litigation. Furthermore, the loss of productivity when your “back office” personnel are tied up dealing with discovery, phone calls, and other incidents of litigation that do nothing but rehash a bad project and increase the expense sap money from the bottom line. While the possibility of a judgment including attorney fees may soften this blow, you are still out the cash.
All of this said, if you are in commercial construction for any significant period of time disputes will arise and I have discussed the process in some detail at other places here at Construction Law Musings. As a construction litigator, I am fully aware of this fact of life. Efficient management of these disputes is key, particularly when they escalate to the point where some form of outside “help” (read arbitrator or judge) is necessary.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Allegations Confirm Duty to Defend Construction Defect Claims
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiRelying upon the same case cited by the Hawaii Supreme Court in its seminal decision on duty to defend, the federal district court determined the allegations sufficiently established a duty to defend construction defect claims. Voeller Constr. v. Southern-Owners Ins. Co., 2014 U.S. Dist. LEXIS 61862 (M. D. Fla. May 5, 2014).
The Bay Harbor Clearwater Condominium Association, Inc. sued Voeller Construction for statutory breach of warranty and building code violations which allegedly caused damage to the condominium structure. The complaint alleged that the damage was unknown to the unit owners at the time they purchased their units. The project was completed in 2007. Expert reports attached to the complaint listed July 7, 2010, as the earliest date of discovery of the damage to the property. The CGL policies were effective from January 24, 2007 to May 9, 2009. Therefore, the insurer argued there was no coverage because the alleged "property damage" was discovered for more than one year after the policies expired.
The court determined there was a duty to defend. Citing Trizec Props., Inc. v. Biltmore Constr. Co., 767 F.2d 810 (11th Cir. 1985), the court noted that if the complaint alleged facts which created potential coverage under the policy, the duty to defend was triggered. The Hawaii Supreme Court relied on Trizec and made the same ruling in Dairy Road Partners v. Island Ins Co., Ltd., 92 Haw. 398, 412, 992 P.2d 93, 107 (2000).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Breaking with Tradition, The Current NLRB is on a Rulemaking Tear: Election Procedures, Recognition Bar, and 9(a) Collective Bargaining Relationships
September 09, 2019 —
Keahn Morris, John Bolesta & James Hays - Construction and Infrastructure Law BlogIn its 84-year history, the National Labor Relations Board (NLRB, Board or Agency) has promulgated a very small number of rules pursuant to the Administrative Procedures Act, relying, instead, on individualized adjudications to establish the Board’s legislative policies. However, breaking with that long tradition, the current Board now appears to be on the verge of a formal rulemaking jag for on May 22, the Board released its “Unified Agenda” of anticipated regulatory actions which, in addition to proceeding with rulemaking regarding joint employer standards, announced the Board’s intention to consider formal rulemaking in a number of critical areas. Consistent with that wide-ranging Agenda, on August 12, the Board published a Notice of Proposed Rulemaking (NPRM) over the objection of Democratic appointee, Lauren McFerran, that would amend the Agency’s rules and regulations governing the filing and processing of election petitions in three very important ways. This NPRM, therefore, deserves attention.
The first possible amendment will modify the Board’s administrative election blocking charge practice by establishing a regulation-based vote and impound procedure to be used when a party, typically a union facing possible decertification, files an unfair labor practice (ULP) charge and, based thereon, seeks to block the holding of an election.
The second possible amendment will modify the Board’s current recognition bar case law by codifying prior Board case doctrine and creating a regulation-based requirement of notice of voluntary recognition to affected employees and a 45-day open period within which affected employees may call for an election before that voluntary recognition will be allowed to operate as a bar to employees raising later questions concerning the union’s representative status (QCR).
Reprinted courtesy of Sheppard Mullin attorneys
Keahn Morris,
John Bolesta and
James Hays
Mr. Morris may be contacted at kmorris@sheppardmullin.com
Mr. Bolesta may be contacted at jbolesta@sheppardmullin.com
Mr. Hays may be contacted at jhays@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
When Must a New York Insurer Turn Over a Copy of the Policy?
December 23, 2023 —
Nicholas P. Hurzeler - Lewis BrisboisNew York, N.Y. (December 7, 2023) - It has long been the rule in New York that a defendant should disclose all insurance policies that might provide coverage to the plaintiff for an underlying claim. McKiernan v Vaccaro, 168 AD3d 827 [2d Dept 2019]; Keenan v Harbor View Health & Beauty Spa, 205 AD2d 589 [2d Dept 1994]. This rule applies to all tort cases, including motor vehicle; however, it does not apply to lawsuits seeking to recover No Fault expenses (see, CPLR 3101(f)(5)).
Frequently, a plaintiff will demand a copy of the policy even when the claim is still pre-suit. This raises the question of when the insurer must comply with this specific type of discovery demand in New York.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas P. Hurzeler, Lewis BrisboisMr. Hurzeler may be contacted at
Nicholas.Hurzeler@lewisbrisbois.com
Issuing Judgment After Confirmation of Appraisal Award Overturned
May 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed and remanded the trial court's judgment in favor of the insured because after confirming the appraisal award, judgment was issued before the insurer could offer policy defenses. State Farm Florida Ins. Co. v. Hochreiter, 2023 Fla. App. LEXIS 743 (Fla. Ct. App. Feb. 3, 2023.
After a dispute arose over the scope and amount of damage suffered by the insureds' roof, they sued State Farm. State Farm responded to the complaint by demanding an appraisal, a stay of litigation, and an extension of time to respond to the complaint.
The trial court granted the demand and retained jurisdiction regarding post-appraisal matters once the appraisal was complete. The court further ordered State Farm to respond to the complaint within twenty days of the conclusion of the appraisal "if any issues remain." The order did not specify whether the issues that remained had to relate to the initial appraisal stage of the litigation or the subsequent stage during which the trial court had jurisdiction to adjudicate disputed issues related to coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Subcontractor Strikes Out in its Claims Against Federal Government
July 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesIs it a good idea for a subcontractor to sue the federal government? A recent case would suggest NO–way too many huge hurdles for the subcontractor to overcome. No matter how creative the arguments may be, it’s a high mountain to climb.
In Fox Logistics & Construction Co. v. U.S., 2024 WL 2807677 (Fed.Cl. 2024), a subcontractor sued the federal government when it was not paid by the prime contractor. The subcontractor claimed it was a third-party beneficiary under the government’s modifications to the prime contractor’s payment procedure, or alternatively it had an implied-in-fact contract with the government. The Court of Federal Claims granted summary judgment in favor of the government. The subcontractor, while creative, struck out in its claims based on the hurdles in a subcontractor suing the federal government.
This case involved upgrading an air force base. The subcontractor performed most of the work. The prime contractor had cash flow problems and did not pay the subcontractor. The government got involved to enforce provisions of its contract to force the prime contractor to pay subcontractors and even modified the payment procedure by having future payments to the prime contractor deposited into a new bank account that government could monitor. This ultimately did not work, and the prime contractor filed for bankruptcy. The subcontractor claimed it was owed millions–apparently, it was not able to recover the money through the prime contractor’s bankruptcy—and pursued claims against the federal government in an effort to recover money it was owed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com