CA Supreme Court Finds “Consent-to-Assignment” Clauses Unenforceable After Loss Occurs During the Policy Period
August 26, 2015 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Fluor Corporation v. Superior Court (No. S205889; filed 8/20/15), the California Supreme Court overruled its earlier decision in Henkel Corp. v. Hartford Accident & Indemnity Co. (2003) 29 Cal.4th 934, holding that notwithstanding the presence of a consent-to-assignment clause in a liability policy, Insurance Code section 520 bars an insurer from refusing to honor the insured’s assignment of coverage after a loss has taken place during the policy period.
In Henkel, the Supreme Court limited the ability of corporate successors to obtain coverage under predecessors’ policies on a contract theory. The Henkel Court held that where a successor corporation contractually assumed liabilities of the predecessor corporation, the insurance benefits would not automatically follow. The Henkel Court ruled that if the predecessor company’s policy contains a consent-to-assignment clause, any assignment of insurance policy benefits to a successor corporation required the insurer’s consent. The Court said that policy benefits are not transferable choses in action unless at the time of corporate transfer they could be reduced to a monetary sum certain. The Court reasoned that historic product or environmental liabilities might not even be known to the predecessor at that time, much less reduced to a sum certain, so coverage for such risks could not be considered a transferable chose in action. Thus, where the liability was inchoate at the time of the corporate transaction, the Henkel Court said that coverage would not necessarily follow because the insurer’s duties had not yet attached.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
While You Were Getting Worked Up Over Oil Prices, This Just Happened to Solar
October 29, 2014 —
Tom Randall – BloombergEvery time fossil fuels get cheaper, people lose interest in solar deployment. That may be about to change.
After years of struggling against cheap natural gas prices and variable subsidies, solar electricity is on track to be as cheap or cheaper than average electricity-bill prices in 47 U.S. states -- in 2016, according to a Deutsche Bank report published this week. That’s assuming the U.S. maintains its 30 percent tax credit on system costs, which is set to expire that same year.
Even if the tax credit drops to 10 percent, solar will soon reach price parity with conventional electricity in well over half the nation: 36 states. Gone are the days when solar panels were an exotic plaything of Earth-loving rich people. Solar is becoming mainstream, and prices will continue to drop as the technology improves and financing becomes more affordable, according to the report.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Randall, BloombergMr. Randall may be contacted at
trandall6@bloomberg.net
What Construction Contractors Should Know About the California Government Claims Act
May 28, 2024 —
Garret Murai - California Construction Law BlogIf you work on state or local public works projects in California you should have at least a basic understanding of the Government Claims Act formerly known as the Tort Claims Act (Govt. Code §§ 900 et seq.). In the event of a dispute with a public entity, the Government Claims Act will usually apply, absent contractual provisions providing otherwise (Govt. Code §§930, 930.2) (e.g., in a construction contract), and requires that a “claim” first be presented to a “public entity” before a claimant files a lawsuit against the public entity. Failure to comply with the Government Claims Act can serve as a bar to maintaining a lawsuit against a public entity.
What types of claims does the Government Claims Act apply to?
The Government Claims Act broadly applies to most claims against state and local public entities. This is not limited to construction projects and includes all claims for “money or damage” arising from death, personal injury, breach of contract, and damage to real and personal property, wrongful death, or breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New York Supreme Court Building Opening Delayed Again
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFSI Live reported that the opening of the new state Supreme Court building in St. George, New York is delayed again due to problems with the air-conditioning and elevator systems. Delay, however, is not new to this project, which was originally expected to be completed over a decade ago.
Initial delay was introduced “with the finding of remains from a 19th-century burial ground at the site, a former municipal parking lot, and more recently, with construction set-backs and other tie-ups,” according to SI Live.
When completed, the new “building will boast 14 courtrooms, jury assembly, hearing and deliberation rooms, judges' chambers and court offices. There will also be holding cells for prisoners.”
Read the court decisionRead the full story...Reprinted courtesy of
Latosha Ellis Selected for 2019 Leadership Council on Legal Diversity Pathfinder Program
April 10, 2019 —
Michael S. Levine - Hunton Andrews KurthHunton Andrews Kurth has selected Latosha Ellis, an associate in the firm’s Insurance Coverage practice, for the 2019 Leadership Council on Legal Diversity (LCLD) Pathfinder Program. Pathfinder is a national yearlong program that trains diverse, high performing, early-career attorneys in critical career development strategies, including foundational leadership and building professional networks.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Judicial Economy Disfavors Enforcement of Mandatory Forum Selection Clause
December 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesMandatory forum (venue) selection provisions are generally construed in favor of enforceability. Parties agreed to the forum for disputes so why not enforce them, right? A recent federal district court case out of the Eastern District of Louisiana exemplifies an exception grounded in judicial economy which disfavors the enforceability of mandatory forum selection provisions. Keep in mind that this judicial economy exception is fairly limited but the fact pattern below demonstrates why enforcing the mandatory forum selection provision was disfavored due to judicial economy.
In U.S. f/u/b/o Exposed Roof Design, LLC v. Tandem Roofing, 2023 WL 7688584 (E.D.La. 2023), a sub-subcontractor filed a Miller Act payment bond lawsuit against the prime contractor and the prime contractor’s Miller Act payment bond sureties. The sub-subcontractor also sued the subcontractor that hired it. However, the sub-subcontractor’s subcontract with the subcontractor included a mandatory forum selection provision in a different form. The subcontractor moved to sever and transfer the sub-subcontractor’s claims against it to the forum agreed upon in the subcontract. The trial court denied the severance and the transfer. Below are the reasons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
South Carolina Supreme Court Finds that Consequential Damage Arise From "Occurrence"
October 10, 2013 —
Tred Eyerly — Insurance Law HawaiiThe South Carolina Supreme Court held that continuing damage that was part of a continuum of property damage constituted an "occurrence." Auto-Owners Ins. Co. v. Rhodes, 2013 S.C. LEXIS 248 (Sept. 25, 2013).
Rhodes hired Eadon to design, fabricate, and erect three outdoor advertising signs on Rhodes' property bordering an interstate highway. After the signs were erected, one fell across the highway, blocking both lanes of southbound traffic. The state Department of Transportation ordered Rhodes to remove the remaining two signs and revoked Rhodes' permit to maintain signs on the property.
Rhodes sued Eaton. Eaton's insurer, Auto-Owners, filed a declaratory judgment action to determine whether there was coverage under the CGL policy. The trial court found the sign falling on the interstate constituted an "occurrence" that resulted in damages beyond the defective work to property other than the defective work itself.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com