South Carolina “Your Work” Exclusion, “Get To” Costs
July 30, 2014 —
Scott Patterson - CD CoverageIn Precision Walls, Inc. v. Liberty Mutual Fire Insurance Co., No. 2013-000787 (S.C. Ct. App. July 23, 2014), SYS was the general contractor for a project. SYS contracted with Precision for the supply and installation of exterior insulation board, to include the taping of all joints. After Precision completed its work, another subcontractor began construction of the brick veneer wall over the insulation board. During construction of the brick wall, some of the joint sealing tape installed by Precision began to come loose. To correct the problem, the existing portion of the brick veneer wall had to be torn down, all of the joint sealing tape removed and replaced, and the brick veneer wall rebuilt. SYS deducted the cost of tearing down and rebuilding the brick veneer wall from Precision’s contract. Precision sought reimbursement for this amount from its CGL policy issued by Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage
Global Insurer Agrees to Pay COVID-19 Business Interruption Claims
July 06, 2020 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogAXA, one of the biggest insurance companies in the world, has agreed to pay COVID-related business interruption claims by a group of restaurants in Paris after a court ruled that the restaurants’ revenue losses resulting from COVID-19 and related government orders were covered under AXA’s policies.
AXA initially took the position that its insurance policies did not cover business interruption caused by COVID-19. The restaurant then sued AXA in a French court, seeking coverage for operating losses resulting from a government order issued in March mandating the closure of restaurants and bars in response to the COVID-19 pandemic. The court concluded that the government orders, which prohibited restaurants from receiving the public and offering traditional sit-down dining services, triggered the policy’s coverage for business interruption coverage. The court rejected AXA’s argument that the pandemic was uninsurable, and made clear that if AXA intended to exclude such a risk it should have done so expressly in its policy. The court also rejected AXA’s argument that there must be a prerequisite of an insured event for the application of the “administrative closure” provision, noting that no prerequisite was required by the policy. AXA’s argument that the government orders did not require the restaurant to be closed because the restaurant was authorized to maintain take-away services was also rejected. As a result, the court ruled in favor of the policyholders, holding that the business interruption loss resulting from the government orders qualified for insurance coverage.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
SFAA Commends U.S. House for Passage of Historic Bipartisan Infrastructure Bill
November 15, 2021 —
The Surety & Fidelity Association of AmericaNovember 8, 2021 (WASHINGTON, DC) – The Surety & Fidelity Association of America (SFAA), a nonprofit, nonpartisan trade association representing all segments of the surety and fidelity industry, commends the U.S. House for passing the historic, bipartisan Infrastructure Investment and Jobs Act (IIJA). The $1.2 trillion deal will lay the foundation for extensive improvements in the nation’s roadways, bridges, railways, waterways and broadband.
“Both sides of the aisle understand the importance of investing in our country’s aging infrastructure. The passage of this historic bill provides the most significant resources in more than 50 years to address the current and future needs of our country’s infrastructure, while creating millions of jobs and growing our national and local economies,” said SFAA president and CEO, Lee Covington.
SFAA also commends President Joe Biden, House Speaker Nancy Pelosi (D-Calif.), House Majority Leader Steny Hoyer (D-Md.), Senate Majority Leader Chuck Schumer (D-N.Y.), Senate Minority Leader Mitch McConnell (R-Ky.), Sen. Tom Carper (D-Del.), Sen. Shelley Moore Capito (R-W.Va.), Sen. Kyrsten Sinema (D-Ariz.), Sen. Rob Portman (R-Ohio), and Rep. Peter DeFazio (D-Ore.) for their leadership on this bill, and members of the House who voted in favor.
The Surety & Fidelity Association of America (SFAA) is a nonprofit, nonpartisan trade association representing all segments of the surety and fidelity industry. Based in Washington, D.C., SFAA works to promote the value of surety and fidelity bonding by proactively advocating on behalf of its members and stakeholders. The association’s more than 450 member companies write 98 percent of surety and fidelity bonds in the U.S. For more information visit www.surety.org.
Read the court decisionRead the full story...Reprinted courtesy of
Triple Points to the English Court of Appeal for Clarifying the Law on LDs
July 01, 2019 —
Vincent C. Zabielski & Julia Kalinina Belcher - Gravel2GavelCan an employer recover liquidated damages (LDs) from a contractor if the contract terminates before the contractor completes the work?
Surprisingly, heretofore, English law provided no clear answer to this seemingly straightforward question, and inconsistent case law over the past century has left a trail of confusion. Given the widespread use of English law in international construction contracts, this uncertainty had gone on far too long.
The good news is that drafters of construction contracts throughout the world can now have a well-deserved good night’s sleep courtesy of the English Court of Appeal’s March 2019 decision in Triple Point Technology, Inc. v PTT Public Company Ltd [2019] EWCA Civ 230.
The Triple Point case concerned the delayed supply by Triple Point (the “Contractor”) of a new software system to employer PTT. The contract provided for payments upon achievement of milestones, however order forms incorporated into the contract set out the calendar dates on which fixed amounts were payable by PTT, resulting in an apparently contradictory requirements on when payment was due. Triple Point achieved completion (149 days late) of a portion of the work milestones, and were paid for that work. Triple Point then sought payment for the work which was not yet completed, relying on the calendar dates in the order forms rather than achievement of milestone payments. Things got progressively worse as PTT refused payment, Triple Point suspended the work for PTT’s failure to pay, PTT terminated the contract and then appointed a new contractor to complete the work.
Reprinted courtesy of
Vincent C. Zabielski, Pillsbury and
Julia Kalinina Belcher, Pillsbury
Mr. Zabielski may be contacted at vincent.zabielski@pillsburylaw.com
Ms. Belcher may be contacted at julia.belcher@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Coverage for Construction Defects Barred By Exclusion j (5)
April 15, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Texas Court Appeal reversed a trial court judgment which found coverage in favor of the contractor based upon exclusion j(5). Dallas Nat'l Ins. Co. v. Calitex Corp., 2015 Tex. App. LEXIS 2002 (Tex. Ct. App. March 3, 2015).
Turnkey Residential Group, Inc., was the contractor to construct a twelve-unit townhome complex in Dallas. The owner of the project was Calitex Corporation. Construction began on November 2006. The project was to be completed by Turnkey by October 27, 2007.
Calitex filed suit against Turnkey and some of its subcontractors in February 2008. Calitex alleged problems with Turnkey's work included: (1) the stone exterior was not properly treated and leaked, and some areas were left uncovered with stone; and (2) windows leaked. It was further alleged that the quality of materials, labor and craftsmanship did not meet the standards of the contract and resulted in damages. Turnkey submitted a notice of claim to its insurer, Dallas National Insurance Company (DNIC). Coverage was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Policy's Limitation Period for Seeking Replacement Costs Not Enforced Where Unreasonable
March 12, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe New York Court of Appeals determined that a two year period for obtaining replacement costs for damage to property was unenforceable where the property could not be reasonably replaced in two years. Executive Plaza, LLC v. Peerless Ins. Co., 2014 WL 551251 (N.Y. Ct. App. Feb. 13, 2014).
Plaintiff's office building was severely damaged in a fire on February 23, 2007. It cost more than a million dollars to restore the building to its previous condition. Plaintiff had $1 million in coverage from Peerless. The policy provided that replacement costs for any loss would be paid after the damaged property was repaired. The insured was required to make the repairs as soon as possible. Further, the policy provided that any legal action against the insurer had to be brought within two years of the loss.
Peerless paid the "actual cash value" of the destroyed building pursuant to the policy in the amount of $757,812.50. Peerless informed the plaintiff that it would have to provide documentation of the completion of repairs to collect the full replacement value, another $242,187.50.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Seeking Better Peer Reviews After the FIU Bridge Collapse
September 16, 2019 —
Engineering News-RecordOn the surface, it seemed like an outrageous defensive move following a painful tragedy. Louis Berger Group has refused requests from the Dept. of Labor to hand over emails with FIGG Bridge Engineers about its peer review of the ill-fated Florida International University pedestrian bridge. The structure collapsed on March 15, 2018, killing six people and injuring several others.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
DC District Court Follows Ninth Circuit’s Lead Dismissing NABA’s Border Wall Case
April 10, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 14, the U.S. District Court for the District of Columbia dismissed the complaint of the National American Butterfly Association (NABA) alleging that the U.S. Government’s border wall preparation and law enforcement activities at NABA’s National Butterfly Center, located in South Texas along the Rio Grande River, violated federal environmental laws (National Environmental Policy Act (NEPA)) and the Endangered Species Act (ESA)) as well as NABA’s constitutional rights. The case is National American Butterfly Association v. Nielsen, et al.
On January 25, 2017, the President issued an Executive Order to the Secretary of the Department of Homeland Security (Secretary) to “take all appropriate steps to immediately plan, design, and construct a physical wall along the southern border” with Mexico. A few weeks later, the Secretary issued a memorandum to the U.S. Customs and Border Enforcement to implement the Executive Order. The land occupied by the NABA has been affected by these actions, as well as other actions taken by the Secretary pursuant to her authority under the Illegal Immigration Reform and Immigrant Responsibility Act (IIRIRA), located at 8 U.S.C. § 1103.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com