Coverage for Faulty Workmanship Denied
June 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no coverage for the insureds' alleged negligent failure to construct a building. Evanston Ins. Co. v. DCM Contracting, 2020 U.S. Dist. LEXIS 63977 (N.D. Ga. Feb. 28, 2020).
Turning Point Church sued DCM Contracting for faulty workmanship on a construction project. Turning Point sent a demand letter to DCM on August 18, 2017 and filed suit in December. Evanston did not receive notice of Turning Point's claims and the lawsuit until May 15, 2018.
Evanston filed suit for a declaratory judgment and moved for summary judgment. The court first considered the late notice. The policy required notice "as soon as practicable" DCM was also required to provide copies of demands, notices, or legal papers to Evanston. Here, DCM did not give notice to Evanston until nine months after receipt of Turning Point's demand. A phone communication with DCM's agent between August 2017 and May 2018 was insufficient. DCM provided no documents, including the summons and complaint, to the agent. DCM waited five months to forward the underlying lawsuit. This was a breach of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mitsubishi Estate to Rebuild Apartments After Defects Found
March 19, 2014 —
Kathleen Chu and Takahiko Hyuga – BloombergMitsubishi Estate Co. (8802), Japan’s biggest developer by market value, will rebuild a Tokyo residential complex where it stopped selling apartments that went for as much as 350 million yen ($3.4 million) after finding defects.
The reconstruction will take about three to four years to complete, and builder Kajima Corp. will be in charge of the project and cover the cost, said Masayuki Watanabe, a spokesman at Tokyo-based Mitsubishi Estate. The building was constructed by Kajima along with Kandenko (1942) Co., according to the developer.
Mitsubishi Estate stopped selling apartments in the building in central Tokyo’s upscale Aoyama neighborhood after finding it needed repairs, including to some of the pipes, the developer said in an e-mail on Feb. 3. Eighty-three out of 86 units were under contract and were expected to be handed over to the owners on March 20, the company said last month.
Ms. Chu may be contacted at kchu2@bloomberg.net; Mr. Hyuga may be contacted at thyuga@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen Chu and Takahiko Hyuga, Bloomberg
Halliburton to Pay $1.1 Billion to Settle Spill Lawsuits
September 03, 2014 —
David Wethe, Margaret Cronin Fisk and Laurel Calkins – BloombergHalliburton Co. agreed to pay $1.1 billion to settle a majority of lawsuits brought over its role in the largest offshore oil spill in U.S. history.
The agreement is subject to court approval and includes legal fees, the Houston-based company said in a statement today. Halliburton was accused by spill victims and BP Plc of doing defective cementing work on the Macondo well before the April 2010 Gulf of Mexico oil spill. Halliburton blamed the incident on decisions by BP, which owned the well.
The settlement comes as the judge overseeing oil-spill cases weighs fault for the disaster. An agreement now averts the company’s risk of a more costly judgment for some spill victims and removes much of the uncertainty that has plagued Halliburton for the past four years as investors waited to see the payout tally. With its biggest piece of liability resolved, Halliburton can refocus its attention on developing new oilfield technology that will help it boost profits worldwide.
Reprinted courtesy of Bloomberg journalists
David Wethe,
Margaret Cronin Fisk and
Laurel Calkins
Mr. Wethe may be contacted at dwethe@bloomberg.net; Ms. Fisk may be contacted at mcfisk@bloomberg.net; and Ms. Calkins may be contacted at lcalkins@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Homeowner Has No Grounds to Avoid Mechanics Lien
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has rejected a motion by a homeowner in a dispute with the contractor who built an extension to his home. In McCracken v. Pirvulete, Mr. McCracken filed a mechanics lien after Mr. Pirvulete failed to complete payment. The matter went to trial with a series of exhibits that showed “the contractual relationship was strained and the parties disagreed over performance and payment.” As a result of the trial, the court awarded Mr. McCracken, the contractor, $1,922.22.
Mr. Pirvulete appealed, contending that the court had not allowed his daughter to act as a translator, that the court had failed to give him sufficient time to present his case, that the mechanics lien should have been dismissed, and several other claims, all before a formal judgment was issued. After the court formalized its judgment and rejected the appeal, Mr. Pirvulete appealed again.
The appeals court found that Mr. Pirvulete did not provide an adequate record for review. The court dismissed Mr. Pirvulete’s claims. The court notes that Mr. Pirvulete claimed that a request for a discovery period was denied, however, he has provided neither the request nor the denial. The trial court has no record of either.
Nor was there a record of a request that Mr. Pirvulete’s daughter provide translation. The court notes, “so far as we can glean from the record provided, the Register of Actions states, ‘Trial to proceed without Romanian Interpreter for Defendant; Daughter present to interpret if needed.’” Additionally, the court found that “there has been no showing that his facility with the English language is or was impaired in any way or that there was any portion of any proceeding, which he did not understand.”
Further, the appeals court found there were no grounds for a new trial, despite Mr. Pirvulete’s filings. The court concluded, “The owner has failed to provide a record adequate for review of most, if not all, of the claims of error. Some issues are not cognizable because they relate to entirely separate proceedings, and not the trial below. To the limited extent that the claims are examinable, the owner has made no showing of error.” The court affirmed the judgment of the lower court against Mr. Pirvulete.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (11/16/22) – Backlog Shifts, Green Battery Storage, and Russia-Ukraine Updates
December 05, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores backlog shifts in the nonresidential construction sector, updates from the ongoing war between Russia and Ukraine, lithium-ion battery storage issues in New York City, and more.
- According to Associated Builders and Contractors, construction backlog fell back below the reading observed in February 2020, largely due to a decline in the commercial and institutional sector. (Sebastian Obando, Construction Dive)
- Amid celebration after retaking Kherson from retreating Russian troops, the Kremlin targeted critical infrastructure before withdrawing. (Michael Kern, Oil Price)
- Real estate value in the metaverse is rising, given that virtual land can be built upon to create unique branding experiences that lend to advertising, marketing, socializing, and entertainment. (Evan Bourke & Sarah Hedley Hymers, Euronews)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Collapse of Breezeway Attached to Building Covered
February 24, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that a breezeway that collapsed during a party was covered by the commercial property policy. DENC, LLC v. Philadelphia Indem. Ins. Co., 2019 U.S. Dist. LEXIS 179083 (M.D. N.C. Oct. 15, 2019).
DENC owned an apartment complex that was insured by Philadelphia under an all-risk policy. During an early morning party, a large number of students gathered on the second-floor breezeway for a party. The students started jumping in the breezeway when a certain song started playing. The floor abruptly collapsed underneath the students.
Philadelphia sent an adjuster to inspect the breezeway a couple days later. He wrote to Philadelphia that "the sole and proximate cause of the loss is water damage occurring over an extended period of time causing the second floor breezeway to sage and the light weight concrete to crack." Shortly thereafter, the building was condemned. A structural engineer found multiple ways in which water had seeped into the breezeway's wood framing and photographed the resulting biological growth and wood decay. He concluded that the building had sustained significant long-term water intrusion which resulted in the wood framing inability to support the loads. The water intrusion was caused by the failure to properly install a water management system on the walls, a properly integrated waterproof system for the walkway slab and framing configuration, and improper venting of dryers.
DENC retained an engineer who testified that the breezeway was sagging because the concrete had broken.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (6/18/24) – Cannabis’ Effect on Real Estate, AI’s Capabilities for Fund Managers and CRE’s Exposure on Large Banks
July 15, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, hotel-to-apartment conversions take big leap, state governments pass squatting legislation, US regional banks risk having debt ratings downgraded, and more!
- Reclassifying cannabis as a lower-risk substance could bring significant changes to the real estate sector associated with cannabis. (Margaret Jackson, Yahoo)
- More than 60 of the largest banks in the country are at increased risk of failure due to their commercial real estate (CRE) exposures. (Florida Atlantic University).
- As extreme weather grows in frequency and intensity, the nation’s patchwork of building codes have not kept up with modern conditions and if something goes wrong, contractors are not off the hook if they simply build to code. (Julie Strupp, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Engineers Propose 'River' Alternative to Border Wall
May 10, 2017 —
Frank K. Johnson - Engineering News-RecordOf all the ideas that have been suggested for the border wall, there is one that may help to bring together Mexico and the U.S., instead of pitting the countries against each another over illegal immigration. I’m part of a group of civil engineers in Massachusetts that has conceived of a program that is based on a recently acquired patent for an advanced concrete construction technology for building large-scale, monolithic concrete structures capable of physically partitioning two countries while serving to promote economic development. This fast and thrifty construction method and our proposed program prove that, as far as creativity is concerned, civil engineering isn’t dead yet.
Read the court decisionRead the full story...Reprinted courtesy of
Frank K. Johnson, ENRENR may be contacted at