Las Vegas Sphere Lawsuits Roll On in Nevada Courtrooms
October 02, 2023 —
Richard Korman - Engineering News-RecordBig concerts have yet to start at Las Vegas’ distinctive new ball-shaped entertainment venue, but the legal noise over its construction has been heard in Clark County courtrooms for more than two years.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
TRI Pointe Merges with Weyerhaeuser’s Real Estate Company
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Big Builder, “TRI Pointe settled--expectedly--on its mammoth $2.8 billion deal to acquire Weyerhaeuser's five home building operations in the Northwest, California/Nevada, Arizona, Texas, and the Mid-Atlantic regions, a talent-rich operator group, 27,000 building lots, and power brand names via a complex Reverse Morris Trust financial transaction.”
This now makes TRI Pointe “one of the top 10 largest public homebuilders in the United States by equity market capitalization based on the closing price of TRI Pointe common stock on July 8, 2014,” according to their press statement, as quoted in Big Builder.
Read the court decisionRead the full story...Reprinted courtesy of
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
Colorado Temporarily Requires Employers to Provide Sick Leave While Awaiting COVID-19 Testing
April 06, 2020 —
Shawna Ruetz - The Grindstone Lewis Brisbois Labor & Employment BlogOn March 11, 2020, the Colorado Department of Labor and Employment (CDLE) issued emergency rules, referred to as Colorado Health Emergency Leave with Pay (Colorado HELP) Rules, requiring employers in certain industries to provide four days of paid sick leave to employees with flu-like symptoms while awaiting test results for COVID-19, or to anyone who is under instructions from a healthcare provider to quarantine or isolate due to a risk of having COVID-19. These rules take effect immediately for 30 days, or longer if the state of emergency declared by Colorado Governor Polis continues.
Which industries are covered by the Colorado HELP Rules?
- Leisure and hospitality;
- Food services;
- Child care;
- Education (including transportation, food service, and related work at educational establishments);
- Home health (if working with elderly, disabled, ill, or otherwise high-risk individuals)
- Nursing homes; and
- Community living facilities; and
- Retail establishments that sell groceries (added March 26).
How much paid sick leave must be provided?
Employers are required to provide up to four days of paid sick leave to employees with flu-like symptoms who are being tested for COVID-19. If the employee tests negative, the leave ends.
Read the court decisionRead the full story...Reprinted courtesy of
Shawna Ruetz, Lewis BrisboisMs. Ruetz may be contacted at
Shawna.Ruetz@lewisbrisbois.com
Faulty Workmanship may be an Occurrence in Indiana CGL Policies
April 07, 2011 —
Beverley BevenFlorez CDJ STAFFThe question of whether construction defects can be an occurrence in Commercial General Liabilities (CGL) policies continues to find mixed answers. The United States District Court in Indiana denied the Plaintiff’s Motion for Summary Judgment in the case of General Casualty Insurance v. Compton Construction Co., Inc. and Mary Ann Zubak stating that faulty workmanship can be an occurrence in CGL policies.
Judge Theresa L. Springmann cited Sheehan Construction Co., et al. v. Continental Casualty Co., et al. for her decision, ”The Indiana Supreme Court reversed summary judgment, which had been granted in favor of the insurer in Sheehan, holding that faulty workmanship can constitute an ‘accident’ under a CGL policy, which means any damage would have been caused by an ‘occurrence’ triggering the insurance policy’s coverage provisions. The Indiana Supreme Court also held that, under identically-worded policy exclusion terms that are at issue in this case, defective subcontractor work could provide the basis for a claim under a CGL policy.”
As we reported on April 1st, South Carolina’s legislature is currently working on bill S-431 that would change the wording of CGL policies in their state to include construction defects. Ray Farmer, Southwest region vice president of the American Insurance Association spoke out against the bill. “CGL policies were never meant to cover faulty workmanship by the contractor,” he said. “The bill’s supplementary and erroneous liability provisions will only serve to unnecessarily impact construction costs in South Carolina.”
Read the Opinion and order...
Read the court’s ruling...
Read the American Insurance Association statement...
Read the court decisionRead the full story...Reprinted courtesy of
Weyerhaeuser Leaving Home Building Business
November 13, 2013 —
CDJ STAFFThe Washington-based timber giant, Weyerhaeuser, has announced that has sold off its homebuilding business. The division went by the name of WRECO (Weyerhaeuser Real Estate Company) and comprised five home builders, Maracay Homes, Pardee Homes, Quadrant Homes, Trendmaker Homes, and Winchester Homes. The division was bought by TRI Pointe Homes for about $2.7 billion of which $700 million was paid in cash.
Weyerhaeuser intends to focus on their core business of timber products.
Read the court decisionRead the full story...Reprinted courtesy of
Extreme Flooding Overwhelms New York Roadways, Killing 1 Person
July 24, 2023 —
Associated Press - BloombergNEW YORK (AP) — Heavy rain spawned extreme flooding in New York’s Hudson Valley that killed at least one person, swamped roadways and forced road closures on Sunday night, as much of the rest of the Northeast U.S. braced Monday for potentially punishing rains.
As the storm moved east, the National Weather Service extended flash flood warnings into Connecticut, including the cities of Stamford and Greenwich, before creeping into Massachusetts. Forecasters said some areas could get as much as 5 inches (12 centimeters) of rain.
In New York's Hudson Valley, rescue teams found the body of a woman in her 30s who drowned after being swept away while trying to evacuate her home, Orange County Executive Steven Neuhaus told WABC-TV. Officials were waiting for the medical examiner's office to arrive, he said.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at