Real Estate & Construction News Roundup (7/10/24) – Strong Construction Investment in Data Centers, Increase Use of Proptech in Hospitality and Effects of Remote-Work on Housing Market
August 05, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, renters stay in their units longer, GenAI change how commercial real estate operates, and banks continue high exposure due to commercial real estate.
- Strong investor interest, particularly in opportunistic and value-add segments, signals a strong market for construction firms specializing in high-yield projects. (Sebastian Obando, Construction Dive)
- A growing number of renters are staying in their units for longer periods of time than they did a decade ago with over one-third of U.S. renters have lived in the same apartment for more than five years. (Mary Salmonsen, Multifamily Dive)
- Several U.S. regional and mid-sized banks continue to face the squeeze from high exposure to the commercial real estate sector that has been shaken by higher-for-longer interest rates and empty office buildings. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
More Hensel Phelps Ripples in the Statute of Limitations Pond?
February 03, 2020 —
Christopher G. Hill - Construction Law MusingsAs is always the case when I attend the Virginia State Bar’s annual construction law seminar, I come away from it with a few posts on recent cases and their implications. The first of these is not a construction case, but has implications relating to the state project related statute of limitations and indemnification issues for construction contracts brought out in stark relief in the now infamous Hensel Phelps case.
In Radiance Capital Receivables Fourteen, LLC v. Foster the Court considered a waiver of the statute of limitations found in a loan contract. The operative facts are that the waiver was found in a Continuing Guaranty contract and that the default happened more than 5 years prior to the date that Radiance filed suit to enforce its rights. When the defendants filed a plea in bar stating that the statute of limitations had run and therefore the claim was barred, Radiance of course argued that the defendants had waived their right to bring such a defense. The defendants responded that the waiver was invalid in that it violated the terms of Va. Code 8.01-232 that states among other things:
an unwritten promise not to plead the statute shall be void, and a written promise not to plead such statute shall be valid when (i) it is made to avoid or defer litigation pending settlement of any case, (ii) it is not made contemporaneously with any other contract, and (iii) it is made for an additional term not longer than the applicable limitations period.
The Circuit Court and ultimately the Supreme Court agreed with the defendants. In doing so, the Virginia Supreme Court rejected arguments of estoppel and an argument that a “waiver” is not a “promise not to plead.”
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Seattle’s Audacious Aquarium Throws Builders Swerves, Curves, Twists and Turns
January 08, 2024 —
Nadine M. Post - Engineering News-RecordPatrick Nation describes the reinforcing steel for the main tank of the 50,000-sq-ft Seattle Aquarium Ocean Pavilion as a “monster” job for CMC Rebar. In his mind, it was like bending 496 tons of bars “on a golf ball.” In reality, the operation was more like weaving a giant steel basket. Ironworkers had to painstakingly hand-thread the reinforcing steel for the doubly curved and slanted concrete walls of the 350,000-gallon saltwater exhibit—one bar at a time—to create the dense latticework for the 41-ft-tall basket.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Bradley T. Guldalian Wins Summary Judgment
November 19, 2021 —
Bradley T. Guldalian - Traub LiebermanOn September 14, 2021, Traub Lieberman Partner Bradley T. Guldalian secured summary judgment on behalf of a City which operated a park containing a natural bathing spring in Sarasota County, Florida. The underlying loss occurred when the Plaintiff went to the park, entered the spring without incident, swam for more than an hour, then exited the spring and was returning to the area where she had stored her belongings when she slipped and fell on mud and grass, sustaining an open angulated fracture of her right tibia and fibula. The Plaintiff was rushed to the hospital where she underwent open reduction, internal fixation surgery on her right leg which consisted of implantation of a metal rod into the medullary cavity of her tibia that was secured by two proximal and two distal interlocking screws. She was in the hospital for four days. Upon discharge, the Plaintiff was placed in a walking boot and confined to a wheelchair for several months. The Plaintiff incurred nearly $100,000 in medical expenses. The Plaintiff filed a premises liability action against the City claiming it failed to maintain its premises in a reasonably safe condition. The Plaintiff also alleged that the City failed to warn her that the area where she had stored her belongings had become saturated and slippery proximately causing her fall and resulting injuries.
After the close of discovery, Mr. Guldalian filed a Motion for Summary Judgment on behalf of the City arguing the wet grass and mud upon which the Plaintiff fell and injured herself was a byproduct of patrons going in and out of the water and walking to and from the area where they stored their belongings, was open and obvious, and did not constitute a dangerous condition as a matter of law. Citing to case law from the Florida Supreme Court which held that it is common knowledge that walks adjacent to, leading to, or surrounding a bathing area generally have water constantly thrown upon them and are in a slippery condition, as well as deposition testimony from the Plaintiff confirming she had been swimming at the spring for the past eighteen plus years and was “very familiar” with the park, the spring, and the area where she normally stored her belongings, Mr. Guldalian argued that some injury-causing conditions, like wet grass and mud surrounding a swimming area, are simply so open and so obvious that they cannot be held, as a matter of law, to give rise to liability as dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Supply Chain Delay Recommendations
August 07, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by supply chain delays.
Contract Protection Tips:
The construction industry is being impacted substantially by inability to obtain necessary construction products due to supply chain issues. Most construction contracts do not accommodate time extensions due to supply chain impacts. To address this gap in contract terms, we recommend including language such as: “lack of or failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers” as part of the defined force majeure event under the contract.
This provision can be included in the Change Order section of the contract as well by including a provision such as: “If the Work is delayed by the failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers, contractor shall be entitled to a change order for its costs and time associated with the delay.”
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
No Coverage for Faulty Workmanship Where Underlying Claim is Strictly Breach of Contract
June 30, 2016 —
Tred R. Eyerly – Insurance Law HawaiiConsidering certified questions from the federal district court, the Arkansas Supreme Court followed a prior decision in deciding there was no coverage for property loss caused by faulty workmanship based solely on breach of contract. Columbia Ins. Group, Inc. v. Cenark Project Mgt. Services, Inc., 2016 Ark. LEXIS 185 (Ark. April 28, 2016).
The homeowners entered a contract in 2005 with Arkansas Infrastructure, Inc. (AII) to construct pads for the construction of six homes. The contract provided that AII would perform the work in accordance with the plans, specifications, and drawings developed by CENARK Project Management Services, Inc.
In 2012, the homeowners sued AII for breach of contract, alleging that AII had failed to construct the pads in accordance with the plans and specifications designed by CENARK.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
California Court of Appeal Provides Clarity On What Triggers Supplemental Analysis Under California Environmental Quality Act
July 20, 2020 —
Kelly Alhadeff-Black & Alexander N. Knaub - Lewis BrisboisIn a recent ruling, California’s Sixth District Court of Appeal clarified the need for supplemental environmental analysis under the California Environmental Quality Act (CEQA). Willow Glen Trestle Conservancy v. City of San Jose (6th Dist., May 18, 2020). Specifically, the court held that seeking additional discretionary approvals, such as regulatory permits, does not constitute a “new discretionary approval for the project” under the California Public Resources Code Section 21166 and the California Code of Regulations, title 14, section 15162 (the CEQA Guidelines).
In 2014, the City of San Jose approved a project that included the demolition and replacement of a wooden railroad bridge known as the Willow Glen Trestle (the Project). CEQA review for the Project was conducted via mitigated negative declaration (MND). The Project was quickly challenged by a local group called Friends of the Willow Glen Trestle, alleging that the City should have prepared an Environmental Impact Report based on the allegation that the Willow Glen Trestle constituted an historic resource for CEQA purposes. Ultimately, the City prevailed in that litigation (See Friends of the Willow Glen Trestle v. City of San Jose, et al. (6th Dist., 2016), which remanded the case to the trial court for further review consistent with the Court of Appeal’s verdict) with the court eventually finding that the City correctly analyzed and answered the question of historic resource classification and significance in reference to the Willow Glen Trestle.
Reprinted courtesy of
Kelly Alhadeff-Black, Lewis Brisbois and
Alexander N. Knaub, Lewis Brisbois
Ms. Alhadeff-Black may be contacted at Kelly.Black@lewisbrisbois.com
Mr. Knaub may be contacted at Alexander.Knaub@lewisbrisbois.com