Georgia Court Reaffirms Construction Defect Decision
August 27, 2013 —
CDJ STAFFIn 2011, the Georgia Supreme Court ruled that construction defects could count as “occurrences” under a general liability policy. John Watkins, writing in Law360, notes that the ruling “has potentially broad implications for Georgia insureds.” He goes on to look at a later Georgia Supreme Court case, in which the court reaffirmed its decision in the 2011 Hathaway case.
In the 2013 case, Taylor Morrison Services Inc. v. HDI-Gerlins Ins., the court held that the property damage had to happen to something other than the work performed by the insured, and that a breaches of warranty without fraud claims may be covered. But Watkins notes that this points to “the continuing efforts of insurers to deny coverage for construction defects under CGL policies.”
This overruled some of the past decisions of the United States District Court for the Northern District of Georgia. Watkins noted that the Eleventh Circuit seemed to wonder about the scope of Hathaway, but with Taylor Morrison, “the Georgia Supreme Court provided a clearly stated response.”
Looking at the implications, he gives an example in which if a window installer work causes a window to leak and the water intrusion damages a floor, the floor, but not the window would be covered. But he cautions, “the result may turn on the policy language and the particular facts.” In any case, he assures us that “coverage disputes regarding construction defects are sure to continue.”
Read the court decisionRead the full story...Reprinted courtesy of
Courts Will Not Second-Guess Public Entities When it Comes to Design Immunity
May 13, 2024 —
Garret Murai - California Construction Law BlogIt was a bizarre confluence of events. Jorgen Stufkosky was driving on SR-154 in Santa Ynez, California. Martha Aguayo was driving on the same highway ahead of Stufkosky when she struck a deer causing it to fly across the centerline into traffic from the opposite direction. The deer struck a SUV causing its driver to lose control. The driver of the SUV crossed the same centerline where he collided head on with Stufkosky, killing him.
Stufkosky’s children later sued the California Department of Transportation in the case Stufkosky v. California Department of Transportation, 97 Cal.App.5th 492 (2023), alleging that their father’s death was due to Caltrans’ negligent design of SR-153, inadequate number of deer crossing signs, and its high posted speed limit.
While in the trial court, Caltrans filed a motion for summary judgment on the ground that Caltrans was immune from liability under Government Code section 830.6, the so called “design immunity” statute.
The trial court agreed and the Stufloskys appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Smart Construction and the Future of the Construction Industry
October 11, 2021 —
Caroline A. Harcourt, James W. McPhillips & Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law Blog“Smart Construction” is a loose term but generally refers to the development and use of processes and applications that improve construction planning and the management of projects (thereby potentially streamlining costs of construction).
The increased deployment of collaboration tools (e.g., Zoom, Microsoft Teams, WebEx) and other cloud-based technology solutions during the COVID-19 pandemic will invariably result in more efficient project management in construction going forward. These type of efficiencies are sorely needed, especially as the industry is trying to recover from supply chain issues, lockdown challenges and social distancing requirements resulting from the pandemic.
However, smart construction goes well beyond those basic business efficiency and collaboration tools. For example, drones are regularly used on construction projects to monitor site conditions, detect problems, and assess conditions safely. Meanwhile, newer technologies such as “programmable” cement, “self-healing” concrete, and autonomous and robotic machinery are increasingly being deployed in construction projects. And yet, these current technology solutions are just the tip of the iceberg as researchers continue to look for new ways machines and technology can be used to solve complex engineering challenges.
Reprinted courtesy of
Caroline A. Harcourt, Pillsbury,
James W. McPhillips, Pillsbury and
Adam J. Weaver, Pillsbury
Ms. Harcourt may be contacted at caroline.harcourt@pillsburylaw.com
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Point Taken: The UK Supreme Court Finally Confirms the General Law of Liquidated Damages (LDs)
April 04, 2022 —
Vincent C. Zabielski & Julia Kalinina Belcher - Gravel2Gavel Construction & Real Estate Law BlogIn a long-awaited decision which overturned the Court of Appeal’s ruling in the Triple Point Technology vs PTT Public Company case, the UK Supreme Court confirmed the general law of LDs, which is that—absent clear words to the contrary—they accrue up to the date of termination of a contract regardless of whether the contractor completes the work; after that, general damages are recoverable. This approach was held to reflect “commercial reality and the accepted function of liquidated damages.” Although the contract in question was not a construction contract, the decision is equally relevant in the construction sphere.
By way of reminder, Triple Point failed to complete the works under Phase 1 of a contract for the design, installation, maintenance and licencing of software. Despite agreeing a revised project plan, PTT gave notice to terminate.
Reprinted courtesy of
Vincent C. Zabielski, Pillsbury and
Julia Kalinina Belcher, Pillsbury
Mr. Zabielski may be contacted at vincent.zabielski@pillsburylaw.com
Ms. Belcher may be contacted at julia.belcher@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Enforceability Of Subcontract “Pay-When-Paid” Provisions – An Important Update
June 15, 2020 —
Patrick McNamara - Porter Law GroupA California Court of Appeals opinion published earlier this month brings a change to payment bond claims brought by unpaid subcontractors and suppliers. The decision (Crosno Construction, Inc. v. Travelers Casualty and Surety Company of America) places limitations on a payment bond surety’s ability to rely on subcontract “pay-when-paid” language, stating that a payment provision typically found in subcontracts is contrary to the “reasonable time” statutory requirement and will not be enforced. This represents a major shift in California construction payment bond claim rights.
Plaintiff Crosno Construction, Inc. (“Crosno) was a subcontractor to general contractor Clark Brothers (“Clark”), who was principal on a public works payment bond issued by Travelers. The owner was a public agency district (“District.”) Crosno had completed most of its subcontract work when a dispute between District and Clark arose, causing the project to stop. Crosno then sought payment through a payment bond claim against Travelers. Travelers denied the claim, relying on the subcontract’s payment provisions and asserting the defense that it had no obligation to pay on the bond claim because the litigation between Clark and the District had not yet reached its conclusion.
Subcontract. The subcontract between Clark and Crosno contained a “pay-when-paid” provision stating that Clark would pay Crosno within a reasonable time after receiving payment from the District. In defining “a reasonable time,” the subcontract language provided that the time for payment “in no event shall be less than the time [Clark] and [Crosno] require to pursue to conclusion their legal remedies against [District] or other responsible party to obtain payment.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Used French Fry Oil Fuels London Offices as Buildings Go Green
December 10, 2015 —
Siobhan Wagner – BloombergPricewaterhouseCoopers LLP’s office above Charing Cross railway station in London is cooled, heated and fueled by an unlikely source: used cooking oil.
The system, which helped the property become the greenest building in the U.K. capital, uses oil refined less than two miles away at London Bridge. It also helps prevent an invisible problem: “fatbergs” formed when oils dumped in drains and pipes congeal with baby wipes and diapers and block the city’s sewers.
“We’re using London’s waste to fuel a London office building,” said Jon Barnes, head of building at PwC. The system contributed toward a one-third reduction in electricity costs after a two-year refurbishment of the One Embankment Place office building that finished last year.
Read the court decisionRead the full story...Reprinted courtesy of
Siobhan Wagner, Bloomberg
Randy Okland Honored as 2019 Intermountain Legacy Award Winner
January 06, 2020 —
Jennifer Seward - Engineering News-RecordA passion for construction is in Randy Okland’s blood. His family’s business, Salt Lake City’s Okland Construction, was founded in 1918 by his grandfather, John Okland, a Norwegian immigrant and shipbuilder. Randy swept the floors and cleaned and fueled company vehicles while working as a laborer and later as a carpenter and concrete former. After graduating from the University of Utah, Randy worked full time at Okland, eventually taking over leadership of the company from his father in 1980.
Jennifer Seward, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Team Temporarily Stabilizes Delaware River Bridge Crack
February 02, 2017 —
Justin Rice - Engineering News-RecordThe team temporarily stabilizing the Delaware River Bridge and planning its permanent repair also are trying to find a precedent for the bridge’s uncommon fracture. Connecting the Pennsylvania and New Jersey turnpikes, the 61-year-old symmetrical truss bridge was shut down indefinitely on Jan. 20, when a complete fracture in a steel truss was discovered below the bridge deck.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com