Settlement Conference May Not Be the End in Construction Defect Case
February 21, 2013 —
CDJ STAFFThe builder has been sentenced to jail for theft. The building has been condemned over construction defects. And the settlement conference probably won’t bring an end to the case. The building in question is a condominium complex, located at 770 Sandy Street in Norristown, Pennsylvania. Bruce Fazio took out a $2.5 million construction loan to build it. And when it was done, there were inspections over construction defects, the building was condemned, and then the court ordered repair work. The city of Norristown has sued Fazio to recover the more than $1.5 million it took to repair the building and allow at least some condominium owners to move back in.
The suit alleges that Norristown officials failed to properly inspect the construction work, and that inspectors were not properly certified. Further, it is alleged that secretaries and clerks signed off on inspection reports and certificates of occupancy.
Read the court decisionRead the full story...Reprinted courtesy of
Daily Construction Reports: Don’t Leave the Job Without Them
January 11, 2022 —
Patrick Barthet - Construction ExecutiveTrying to remember exactly what was done at a job site last week, last month or last quarter along with knowing who worked at the site is nearly impossible without a written, video or electronic record for reference. That’s why daily construction reports are so important.
Yet many contractors fail to create these reports. And those that do create them, may do it only at the beginning of a project or sporadically throughout the progress of a job, and generally only when they are reminded to do so. Daily reports only become truly effective when they are, in fact, done daily. Whether it is to help resolve a pending delay issue or clarify a job site access claim, or any number of other matters where what happened at the time is so critical, those daily construction reports should be completed daily.
Be Timely
The reason that daily reports are admissible in court (with corroborating testimony) is that they are interpreted as being recorded at or about the time the events in question occurred. Field managers should, therefore, write up these reports daily while the work is occurring or very soon thereafter to capture as accurate an account as possible. If these reports are not created until the end of the week or month, the information will not be as accurate and may not be as helpful in supporting a particular position.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Out of Eastern Europe, a Window Into the Post-Pandemic Office
September 28, 2020 —
Andra Timu & Irina Vilcu - BloombergSpecial quarantine rooms. Floor-to-ceiling walls in bathroom stalls. Touchless entrances that take your temperature. This is what telecommunications company Ericsson’s office building in Bucharest looks like after coronavirus. The space has become the pilot for a 100-prong coronavirus standard that a real estate investor in Eastern Europe is pitching as a new global “immune” building standard.
Liviu Tudor, president of the Brussels-based European Property Federation, hopes the standard will convince more employees to go back to work. He’s gathered a team of experts in construction, health care and engineering, such as such as Adrian Streinu-Cercel, the head of Bucharest's biggest infectious diseases hospital, to develop three tiers of “immune” building certifications that he says are intended to make indoor spaces “pandemic proof.”
Read the court decisionRead the full story...Reprinted courtesy of
Andra Timu & Irina Vilcu, Bloomberg
How Contractors Can Prevent Fraud in Their Workforce
August 13, 2019 —
Sarah Hofmann - Construction ExecutiveThe word fraud might conjure up images of Wall Street executives led out to police cars in cuffs, or sleazy conmen with slicked-back hair. While these ideas might be popular in movies and TV, and often in the news, many small and large businesses fall victim to fraud. Whether it’s a trusted site manager who needed a little extra cash to cover an unexpected bill or the accountant who’s been on board for years and has been slowly siphoning an extra paycheck through a ghost employee each month, fraud might be hitting businesses without them even knowing it.
The construction industry is hardly immune to such schemes. According to the ACFE’s 2018 Report to the Nations on Occupational Fraud and Abuse, organizations lose an estimated 5% of their revenue each year to fraud. The median amount lost per instance of fraud was $130,000 across all industries, but fraud cases in the construction industry cost almost twice that much at $227,000 per fraud. They also last longer on average: fraud schemes in the construction industry continue for 24 months before being detected versus the overall median average of 16 months. The more time a scheme continues, the more money is lost for organizations.
What types of fraud schemes are most common in the construction industry?
The construction industry is more susceptible to certain types of fraud than other industries due to the nature of the work. The companies may be smaller in size leading to fewer resources to combat fraud and more trust among employees. Also, construction companies inherently deal with many vendors, subcontractors, bidding organizations and other various third parties, which can all pose fraud risks.
Reprinted courtesy of
Sarah Hofmann, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Attempt to Shift Cost of Defense to Another Insurer Found Void as to Public Policy
June 09, 2016 —
Garret Murai – California Construction Law BlogWhile construction can sometimes be risky, construction litigation is almost always expensive. This volatile mix of risk and expense has made risk shifting, through indemnity and insurance, a primary goal and concern of project owners, contractors and suppliers alike. Construction insurers know this all too well and insurers, even between themselves, seek to shift risk.
As one primary insurer found, however, risk shifting provisions in their policies – specifically, one which sought to shift the cost of defense to another insurer – is not without its limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Don’t Fall in Trap of Buying the Cheapest Insurance Policy as it May be Bad for Your Business Risks and Needs
March 25, 2024 —
David Adelstein - Florida Construction Legal UpdatesDon’t fall in the trap of buying the cheapest insurance policy. It will come and bite you in the butt big time! Consult with an insurance broker that understands construction and, importantly, your specific industry, to provide you coverage within your industry. Otherwise, you’ll be paying for a policy that may (i) not be a good policy, and (ii) may provide you minimal to no value for your industry’s RISKS and NEEDS when factoring in exclusions. When procuring insurance, think of the old adage “penny wise and pound foolish,” and don’t make decisions that fit within this adage!
The recent decision in Nautilus Ins. Co. v. Pinnacle Engineering & Development, Inc., 2024 WL 940527 (S.D. Fla. 2024) serves as an example. Here, a subcontractor was hired by a general contractor to perform underground utility work for a townhome development which consisted of 57 townhome units included in 18 detached structures. The subcontractor’s underground work was defective which caused damage to the property’s water line, sewer system, plumbing lines, pavers, etc. The general contractor was liable to the owner for this defective work. Although the general contractor was an additional insured under the subcontractor’s commercial general liability (CGL) policy, the subcontractor’s CGL carrier denied the duty to defend and initiated an insurance coverage lawsuit. Motions for summary judgment were filed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Ambiguity in Pennsylvania’s Statute of Repose Finally Cleared up by Superior Court
October 17, 2023 —
Mark L. Parisi - White and Williams LLPIn an unpublished opinion from the Pennsylvania Superior Court handed down on August 31, 2023, a long-standing disagreement about the wording of Pennsylvania's Statute of Repose was finally resolved. In Pennsylvania, “a civil action or proceeding brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction or construction of any improvement to real property must be commenced within 12 years after completion of construction of such improvement” to recover most forms of damages that are sought in these kinds of cases.
A statute of repose is different than a statute of limitations. A statute of repose is a hard line that does not shift. There is no discovery rule with a statute of repose. Most, if not all, states have statutes of repose for construction. The Pennsylvania statute of repose is among the longest in the country. It can be even longer – up to 14 years – if the injury (including property damage) or wrongful death “shall occur more than 10 and within 12 years after completion of construction.”
Read the court decisionRead the full story...Reprinted courtesy of
Mark L. Parisi, White and Williams LLPMr. Parisi may be contacted at
parisim@whiteandwilliams.com
Exact Dates Not Needed for Construction Defect Insurance Claim
March 01, 2012 —
CDJ STAFFThe Texas Court of Appeals reversed the decision of the trial court in Vines-Herrin Custom Homes v Great American Lloyds Insurance Company on December 21, 2011. Vines-Herrin Custom Homes built a single-family home in Plano, Texas in 1999. They obtained a commercial general liability policy from Great American, later purchasing coverage from Mid-Continent, which the decision describes as “a sister company of Great American.”
While the home was under construction, Emil G. Cerullo sought to purchase it. At the time, it was under contract to another buyer. Two months later, Vines-Herrin told Cerullo that the deal had “fell through.” Cerullo bought the house with modifications from the original plan. Upon moving in, Cerullo began having water intrusion and other problems. “Cerullo noticed water gathering on window sills and damage to the sheetrock and baseboard.” Additional problems followed, including cracks, leaks, “and in early 2002, the ceiling and roof began to sag.”
Cerullo sued Vines-Herrin, claiming negligent construction. Vines-Herrin filed a claim seeking defense and indemnification under the insurance policies. Coverage was denied and Vines-Herrin filed suit to require coverage and also bringing claims for “breach of the duty of good faith and fair dealing, breach of contract, and DTPA and insurance code violations.”
In May, 2006 Vines-Herrin stated that it had no more defense funds and went into arbitration with Cerullo. The underlying construction defect action was settled for about $2.5 million. As part of the settlement, “Cerullo became the rightful owner of all remaining claims, rights, and causes of action against” Vines-Herrin’s insurers. He then joined the coverage lawsuit.
The non-jury trial was held under the controlling law of the time which “imposed a duty to defend only if the property damage manifested or became apparent during the policy period.” The court concluded in Cerullo’s favor. During the post-judgment motions, the Texas Supreme Court rejected the manifestation rule. Under this ruling, the trial court set aside its judgment and found in favor of the insurance companies. The trial court noted that although “the Residence was covered by an uninterrupted period of insurance (which began before the Residence was constructed) and that the damages to the Residence manifested during the uninterrupted period of insurance coverage,” “Mr. Cerullo failed to allege the date when actual physical damage to the property occurred.”
The first claim by Cerullo and Vines-Herrin was that the “Final Judgment” occurred in October 2004, and that all proceedings thereafter were void. The court rejected this as the “final judgment” is not “final for the purposes of an appeal unless it actually disposes of every pending claim and party or unless it clearly and unequivocally states that it finally disposes of all claims and all parties.” Despite the use of the word “final,” the trial court’s decision did not do this.
The second issue was the application of the Texas Supreme Court case Don’s Building Supply Inc. v. OneBeacon Insurance. In this case, framing rot due to defective stucco was not discovered until after the end of the policy period. The Supreme Court noted that “the key date is when injury happens, not when someone happens on it.”
The appeals court found that the trial court misapplied the Don’s Building Supply decision. Rather than an exact date, “so long as that damage occurred within the policy period, coverage was provided.” The appeals court noted that “Cerullo alleged the house was constructed in 1999 and he purchased it in May 2000.” “By April of 2001, Cerullo noticed that the windowsills in the study were showing signs of leakage and water damage.” As the court put it, “the petitions then alleged a litany of defects.”
The court noted that coverage by Great American was in effect from November 9, 1999 to November 9, 2000. In May of 2000, the house suffered “substantial flooding from a rainstorm that caused damage.” This was during the policy period. “As a matter of law, actual damages must occur no later than when they manifest.”
The court concluded that as damage manifested during the period of coverage, so must have the damage. The court ruled that “contrary to the trial court’s determination otherwise, the evidence showed Great American’s duty to indemnify was triggered, and expert testimony establishing the exact date of injury was not required to trigger the duty.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of