Engineer and CNA Dispute Claim Over Dual 2014 Bridge Failures
December 15, 2016 —
Scott Van Voorhis – Engineering News-RecordAn engineering company whose error led to two pedestrian bridge collapses in North Carolina in 2014 that left one worker dead and caused costly damage contends it is being unfairly denied $2 million in potential insurance coverage by its carrier due to what it claims is an “ambiguous” wording of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Care, Custody or Control Exclusion Requires Complete and Exclusive Control by Insured Claiming Coverage
July 30, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Homes Construction v. Natl. Fire & Marine Ins. Co. (No. D074219, filed 6/5/19) a California appeals court held that a “care, custody or control” exclusion did not bar coverage for defense of a general contractor as an additional insured under a subcontractor’s policy, because the exclusion requires exclusive control, but the facts and allegations posed a possibility of shared control with the subcontractor.
McMillin was the general contractor on a housing project and was added as an additional insured to the roofing subcontractor’s policy pursuant to the construction subcontract. The homeowners sued, including allegations of water intrusion from roof defects. McMillin tendered to the roofing subcontractor’s insurer, which denied a defense based on the CGL exclusion for damage to property within McMillin’s care, custody or control.
In the ensuing bad faith lawsuit, McMillin argued that the exclusion required complete or exclusive care, custody or control by the insured claiming coverage, which was not the case for McMillin. The insurer argued that the exclusion said nothing about complete or exclusive care, custody or control. Further, the intent to exclude coverage for damage to any and all property in McMillin’s care, custody or control, to whatever degree, was demonstrated by the fact that the additional insured endorsement in question was not an ISO CG2010 form, but a CG2009 form, which expressly adds a care, custody or control exclusion to the additional insured coverage not found in the CG2010 form. The argument was that the CG2009 form evidences an intent to conclusively eliminate coverage for property in the additional insured’s care, custody or control. In addition, the insurer argued that this result was also reinforced by its inclusion of an ISO CG2139 endorsement in the roofer’s policy, which eliminated that part of the “insured contract” language of the CGL form, defining an “insured contract” as “[t]hat part of any other contract or agreement pertaining to your business . . . under which you assume the tort liability of another party to pay for ‘bodily injury’ or ‘property damage’ to a third person or organization.” The insurer’s argument was that by having eliminated coverage for contractual indemnity or hold harmless agreements, it had “closed the loop” of eliminating additional insured coverage for construction defect claims.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
China Home Glut May Worsen as Developers Avoid Price Drop
August 06, 2014 —
Zhang Dingmin - Bloomberg NewsThe biggest immediate risk facing China’s economy is about to get worse.
A reluctance among some developers to sell units at prices lower than they could fetch just months ago threatens to cause a swelling in unsold properties. The worsening glut would extend a slide in construction that’s already put a drag on the world’s second-largest economy, and counter policy makers’ efforts to stimulate the real-estate industry with loosened rules.
In Nanjing, eastern China, nine housing projects originally planned for sale in the first half of 2014 were held for later this year, consulting firm Everyday Network Co. says. The number of homes added to the market in July in 21 major cities dropped 25 percent from June, according to Centaline Group, parent of China’s biggest real-estate brokerage.
Read the court decisionRead the full story...Reprinted courtesy of
Zhang Dingmin, Bloomberg NewsZhang Dingmin may be contacted at
dzhang14@bloomberg.net
Top 10 Take-Aways from the 2024 Annual Forum Meeting in New Orleans
May 20, 2024 —
Marissa L. Downs & Brendan Witry - Laurie & Brennan, LLPOver 600 construction lawyers, experts, and consultants met in New Orleans last week for the Forum’s 2024 Annual Meeting where Program Coordinators Brenda Radmacher and Joseph Imperiale together with John Cook and Buck Beltzer put together an insightful program focused on all things construction litigation. Here are our 10 top take-aways from this unique program.
10. Don't underestimate the soft skills that are necessary to effectively represent your clients. There are different ways to measure success when it comes to construction litigation, according to Stephen Dale (WSP USA), Melissa Beutler Withy (Big-D), and Matthew Whipple (Wohlsen Construction). What these (and likely other inside counsel) will look for when retaining outside counsel is the ability to accurately forecast litigation expense and timely communicate case developments. Being able to master these "soft" skills is as important (if not more so) as an attorney's aptitude for trial advocacy. The in-house counsel who hire litigation counsel will be held accountable to deliver results on the investment they are making in legal fees. Outside counsel who cannot manage budgets or avoid surprises in the course of a case will not be successful as litigators.
Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLP and
Brendan Witry, Laurie & Brennan, LLP
Ms. Downs may be contacted at mdowns@lauriebrennan.com
Mr. Witry may be contacted at bwitry@lauriebrennan.com
Read the court decisionRead the full story...Reprinted courtesy of
Reminder About the Upcoming Mechanic’s Lien Form Change
August 26, 2019 —
Christopher G. Hill - Construction Law MusingsAs July 1, 2019 approaches with its inevitable changes to the Virginia Code, I wanted to remind you once again that the statutory form for a Virginia mechanic’s lien will change as of that date.
HB2409 passed both houses of the General Assembly and has been signed by the Governor. This bill reconciled the language found in Virginia Code Sec. 43-4 with the various forms for general contractor, subcontractor and sub-subcontractor/supplier forms found in later sections of the code. As you will see if you download the .pdf of the bill as signed, this involved some tweaks to 43-4 and some updates to the mechanic’s lien forms that are in the code. The recent Desai case from the Virginia Supreme Court made it clear that such action was necessary.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What You Need to Know About Enforcement Actions by the Contractors State License Board
April 15, 2015 —
Garret Murai – California Construction Law BlogI questioned whether to even write this post.
Because, of course, YOU would never find yourself hightailing it out of town with the California Contractor’s State License Board (“CSLB”) sniffing down your tail pipes.
Then again, mistaken identities occur all the time. So, here’s what you need to know if the CSLB mistakes you for one of “those” contractors.
What violations are subject to CSLB enforcement actions?
The CSLB can take enforcement actions based on any one of numerous violations set forth under the California Business and Professions Code (“B&P Code”), including:
1.
B&P Code §7107: Abandonment of a construction project or operation without legal excuse.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Natural Disasters’ Impact on Construction in the United States
December 14, 2020 —
Robert S. Peckar & Crystal T. Dang - Construction ExecutiveIn these times of easy and instant access to news from around the globe, the effects of major earthquakes in Indonesia and Mexico, cyclones in Southeast Asia, Tsunamis around the world, volcanoes in Europe in unexpected places and, of course, raging forest fires and hurricanes in the United States are frequently in the news. Accompanying each of these disasters are immediate threats to construction projects, both physical and those affecting the safety and health of personnel.
However, after the dust settles or the waters recede, myriad issues will become obstacles to the road to recovery for a contractor to navigate. In 2020 alone, the volume of strong storms and forest fires have focused so much attention on the impact of disasters. The purpose of this article is to provide guidelines in anticipation of disasters, for reviewing the impact of a disaster as it is happening, and developing a mitigation plan to limit losses.
Anticipating Disasters
The best time to prepare for a disaster on a project is before the project starts. Reviewing contract rights, insurance policies and company disaster response protocols while a category 3 hurricane is a day away is not a best practice. To avoid falling into that situation, a contractor should follow the following guidelines. Doing so facilitates proper action during the actual disaster itself and in the aftermath.
Reprinted courtesy of
Robert S. Peckar & Crystal T. Dang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Peckar may be contacted at rpeckar@pecklaw.com
Ms. Dang may be contacted at cdang@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Comply with your Insurance Policy's Conditions Precedent (Post-Loss Obligations)
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesI am of the opinion that if your property insurer requests a sworn proof of loss, furnish one with the assistance of counsel (preferably). Ignoring the insurer’s request or refusing to comply with insurer’s request is NOT value-added; it is simply placing you at a disadvantage based on the insurer’s argument that you, as the insured, materially breached the policy. I generally find no value having to confront this expected argument. Instead, I find value making an effort to comply with post-loss obligations including the insurer’s request to submit a sworn proof of loss. Working with counsel can help you comply with post-loss obligations (conditions precedent) while not weakening the value or merits of your claim.
By way of example, in Edwards v. Safepoint Ins. Co., 46 Fla. L. Weekly D1086a (Fla. 4th DCA 2021), the insured did not provide its property insurer with the requested sworn proof of loss. The insurer moved for summary judgment that the insured’s failure to submit the sworn proof of loss was a material breach of the policy that rendered the policy ineffective. The trial court agreed and granted summary judgment. The Fourth District Court of Appeal affirmed explaining “[a] total failure to comply with policy provisions made a prerequisite to suit under the policy may constitute a breach precluding recovery from the insurer as a matter of law. If, however, the insured cooperates to some degree or provides an explanation for its noncompliance, a fact question is presented for resolution by a jury.” Edwards, supra, quoting Haiman v. Federal Ins. Co., 798 So.2d 811, 812 (Fla. 4th DCA 2001).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com