Construction Litigation Roundup: “A Less Than Valiant Effort”
June 21, 2024 —
Daniel Lund III - LexologyA Miller Act claimant in federal court in New Jersey in relation to a VA medical center project found itself on the wrong end of the law and was sent packing by the court.
The claimant had supplied products for the project to general contractor Valiant Group, LLC, pursuant to a purchase order from the GC. The general contractor allegedly refused to pay the supplier, leading to the claim against the GC and its payment bond surety in the amount of $126,900. The supplier also sought recovery under the federal Prompt Payment Act, 31 U.S.C. §§ 3901-07. State law claims were asserted as well.
Chipping away at the federal law claims – the claims forming the asserted basis for federal court jurisdiction for the case – the court first dispensed with the Prompt Payment Act claim. According to the court, allegations that the general contractor had “wrongfully and improperly withheld remuneration… despite [having] ‘received payment from the U.S. Department of Veterans Affairs’" – whether or not accurate – did not trigger the Act. The court wrote:
“The Prompt Payment Act was enacted ‘to provide the federal government with an incentive to pay government contractors on time by requiring agencies to pay penalties . . . on certain overdue bills . . . [and] was later amended to include provisions applicable to subcontractors.’… Absent from the Act, however, are ‘any explicit provisions for subcontractor enforcement if the prime contractor fails to make timely payment.’… This is because the Act ‘merely requires that the prime contractor's contract with the subcontractor include the specified payment clause. [It] does not require the prime contractor to actually make payments to the subcontractor[.]’… The Act, therefore, does not ‘give subcontractors an additional cause of action for an alleged breach by a general contractor of a subcontract.’”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Addenda to Construction Contracts Can Be an Issue
March 30, 2016 —
Christopher G. Hill – Construction Law MusingsWe’ve all been there. Your client either has a well drafted standard subcontract (with any luck in consultation with an experienced construction attorney) that it presents to its subcontractors and suppliers or your client is presented with a construction contract that has some provisions that it would prefer were either different or gone altogether.
In the first of these scenarios, your client often gets push back from a subcontractor to change certain provisions. Such a response is not necessarily a bad thing depending on the provisions that the potential subcontractor may have. The construction contract documents will govern the way that the project moves forward and will be strictly enforced in Virginia and elsewhere so some early give and take is not unusual or unwanted.
In the second scenario, your client is likely to be reading a fairly one sided document. The General Contractor has drafted the contract and is “north” of your client in the payment chain. Like it or not, they will in most instances leave it to you and your attorney to root out the particularly egregious on sided terms and seek to negotiate them to some sort of equality.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
A Court-Side Seat: A FACA Fight, a Carbon Pledge and Some Venue on the SCOTUS Menu
November 02, 2020 —
Anthony B. Cavender - Gravel2GavelIn this summary of recent developments in environmental and regulatory law, venues are challenged, standing is upheld, statutory exemption is disputed and more.
THE U.S. SUPREME COURT
Change Must Come from Within … Maryland?
As the new term begins, the Court has agreed to review BP PLC v. Mayor and City Council of Maryland, a decision of the U.S. Court of Appeals for the Fourth Circuit which held that a climate change damages case filed against many energy companies must be heard in the state courts of Maryland and not the federal courts. The petitioners argue that the federal office removal statute authorizes such removal, and the Fourth Circuit’s contrary decision conflicts with rulings from other circuit courts.
THE FEDERAL COURTS
Where Is the Fund in That?
On September 25,2020, in U.S. House of Representatives v. Mnuchin, et al., the U.S. Court of Appeals for the District of Columbia held that the lower court should not have dismissed a lawsuit filed by the U.S. House of Representatives challenging the Executive Branch’s transferal of appropriated funds to the Department of Defense to build a physical barrier along the southern border of the United State. The case is More than $8 billion is at stake, a sum that had been transferred from various federal accounts not involved with building the wall. The appeals court held that the lower court should not have dismissed this lawsuit because the House of Representatives had standing to bring this lawsuit even if the U.S. Senate was not involved with this litigation. Accordingly, the case was returned to the lower court for additional findings, with the appeals court noting that the Constitution’s Appropriation’s Clause serves as an important check on the Executive Branch.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
NY Supreme Court Rules City Not Liable for Defective Sidewalk
February 12, 2014 —
Beverley BevenFlorez-CDJ STAFFEileen N. Fanning sued the city of Watertown, New York after incurring injuries from a fall on a sidewalk on Court Street, according to the Watertown Daily Times. A state Supreme Court judge dismissed the lawsuit.
According to Fanning as reported by the Watertown Daily Times, the plaintiff “fell on an uneven section of sidewalk” and “suffered multiple broken bones in her hand, as well as neurological damage to her arm, among other injuries.” She claimed that the damage is permanent. The lawsuit involved Purcell Construction (the landscape pavers), Neighbors of Watertown (a renovation project), and the city of Watertown.
The judge ruled that “Neighbors of Watertown was not liable for her injuries because the agency neither owned nor controlled the property where the injuries occurred and therefore ‘did not owe a duty of care’ to users of the walk as it was not responsible for the sidewalk’s maintenance.” The city was not held liable “because it had received no prior written notice about the alleged defective condition of the property.” Furthermore, the judge “agreed with Purcell Construction’s claim that the area claimed to be defective is ‘one little section’ of sidewalk ‘over which the public walked’ for nearly 20 years.”
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
NY Construction Safety Firm Falsely Certified Workers, Says Manhattan DA
March 25, 2024 —
Johanna Knapschaefer - Engineering News-RecordA New York-based construction safety firm and 25 individuals were indicted Feb. 28 for allegedly operating a bogus safety training school, Manhattan District Attorney Alvin Bragg's office says. The firm, Valor Security & Investigations is also linked to “endangering the life” of Ivan Frias, who fell to his death from the 15th floor of a New York City construction site in 2022.
Reprinted courtesy of
Johanna Knapschaefer, Engineering News-Record
Ms. Knapschaefer may be contacted at knapj@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New York Team Secures Appellate Win on Behalf of National Home Improvement Chain
September 26, 2022 —
Lewis BrisboisNew York, N.Y. (August 12, 2022) - New York Appellate Partner Nicholas P. Hurzeler, with New York Partners John J. Doody and David M. Pollack, obtained a significant appellate victory on behalf of a national home improvement chain when a New York Appellate Division panel for the Second Department reduced a jury verdict by more than half.
In this matter, which was
covered by Law360, the plaintiff was a customer at one of the chain's stores when he was involved in a confrontation with a man and his wife as they exited the store. The chain's loss prevention official told police that the plaintiff had assaulted the female customer. As a result of the incident, the plaintiff was arrested, spent the night in jail, and was arraigned at the same courthouse where he worked as a staff attorney while wearing only an undershirt and jogging shorts. He also had to disclose his arrest on his judgeship nomination application. The charges against him were ultimately dropped after the chain's loss prevention official told prosecutors that surveillance video showed that the female customer’s assault claims were false.
The plaintiff subsequently sued the home improvement chain and its loss prevention official for allegedly causing his false arrest and interfering with his career goal of securing a New York state court judgeship. At the close of the trial in this case, the jury determined that the defendant was liable for battery and false imprisonment, and awarded the plaintiff $1.8 million for pain and suffering.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Beyond the Disneyland Resort: World Class Shopping Experiences
May 03, 2018 —
Beverley BevenFlorez-CDJ STAFFIf you don’t want to venture far from the Disneyland Resort, consider heading to
the Outlets at Orange. Formerly known as the Block of Orange, this open air shopping center features outlet stores such as Neiman Marcus Last Call, Nordstrom Rack, and Sax Fifth Avenue’s Off Fifth, as well as an AMC movie theater, restaurants, Lucky Strike Bowling Alley, and Dave and Buster’s.
For another local option, head to
the Brea Mall, where you can find department stores such as Macy’s and Nordstrom’s and a host of other stores like Apple, Guess, and Tommy Bahama.
For a more exclusive shopping experience, travel to south Orange County's
Fashion Island of Newport Beach. Their department stores include Bloomingdale’s, Macy’s, Neiman Marcus’s, and Nordstroms, and the shopping center also contains many boutique shops and eateries.
Read the court decisionRead the full story...Reprinted courtesy of