Can a Home Builder Disclaim Implied Warranties of Workmanship and Habitability?
August 30, 2021 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn a recent Arizona Court of Appeals case, Zambrano v. M & RC II LLC, 2021 WL 3204491 (7/29/2021), the Court of Appeals addressed the question whether a home builder’s attempt to disclaim implied warranties of workmanship and habitability was effective. In that case, the buyer initialed the builder’s prominent disclaimer of all implied warranties, including implied warranties of habitability and workmanship. After the purchase, the buyer sued the builder, claiming construction defects. The builder moved for summary judgment, seeking enforcement of the disclaimer of warranties. The trial court granted the builder’s motion for summary judgment, thereby enforcing the disclaimers. The buyer appealed.
The Court of Appeals addressed the question whether – as a matter of public policy – the implied warranties of workmanship and habitability were waivable. The Court of Appeals started the analysis by noting that the Arizona Supreme Court had, in a 1979 case, judicially eliminated the caveat emptor rule for newly built homes. The court further noted the long history of cases detailing the public policy favoring the implied warranties. But the court also noted the competing public policy of allowing parties to freely contract; explaining that the usual and most important function of the courts is to maintain and enforce contracts rather than allowing parties to escape their contractual obligations on the pretext of public policy.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
California Complex Civil Litigation Superior Court Panels
December 31, 2014 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinThe Complex Civil Litigation Program is relatively new as it has only existed in California
since 2000. Complex divisions dedicate courtrooms solely for litigation of complex civil
cases that require exceptional judicial management including construction defects, antitrust,
securities, toxic torts, mass torts, and class actions. Complex civil courtrooms help the trial
court operate in a more efficient, expeditious, and effective manner. A complex court
reduces costs for litigants by streamlining motion practice and expeditiously resolving
discovery disputes.
Not all counties have dedicated complex civil divisions. For those that do, each county has
its own local rules, and some complex divisions have their own particular set of rules. The
Judicial management of complex cases begins early, and is applied continuously and actively
with the idea that final resolution be expedited as much as possible. In focusing on
cooperation amongst the parties to achieve these goals, often requiring joint statements to
the court and a prohibition on discovery motions until after the parties have formally metand-
conferred on the issues. Moreover, complex cases are centralized and are assigned to
one highly skilled Judge for all purposes.
The first six California counties to create a Complex Civil division include Alameda, Contra
Costa, Los Angeles, Orange, San Francisco, and Santa Clara. Riverside County Superior
Court is the most recent California County to add a Complex division, effective January 2015.
Riverside county Superior Court’s Complex department consists of ten civil judges, seven of
which are in the main courthouse with Riverside. Riverside county expects to consolidate all
complex civil litigation into one courtroom by January 2015. Riverside county Judge Sharon
Waters state that "[i]t's been something that I personally have felt has been long overdue"
and that "[t]he idea is that put it with one judge and let him or her develop the expertise."
Judge Waters believes "[t]he potential value of establishing a complex litigation courtroom
[is that] it allows the judge to focus on the cases full time."1
As of October 2014, Riverside county had about 450 to 500 pending cases designated as
complex, over fifty percent (50%) of which involved construction defect matters. The sole
Judge who will preside over the complex cases has not yet been named.
1 Jolly, Vik. "Riverside to Shift Complex Civil Cases to 1 Courtroom." Los Angeles Daily Journal (October 13,
2014)
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com;
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com;
and Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
You Are on Notice: Failure to Comply With Contractual Notice Provisions Can Be Fatal to Your Claim
September 26, 2022 —
Jenifer B. Minsky - ConsensusDocsImagine your firm is the construction manager on a multi-million-dollar project. At the end of the project you are five million dollars out-of-pocket. You have a stack of claims for additional and extended work which led to the overrun, payment for which will easily cover the shortfall. However, the owner refuses to compensate you until you can satisfactorily answer their inquiry: “Where are the notices that are expressly required under the terms of the contract?” You had a good relationship with the owner’s field representative who was aware you were performing the work and understood that your company was compiling claims. The once cooperative owner, now suffering financial restraints of their own, is resolute in their refusal leaving you no choice but to expend substantial sums of money to litigate the claims, the success of which is far from assured.
What Contract Language Can Be A Trap For An Unwary Contractor?
While courts are generally hesitant to order a forfeiture and some courts disfavor condition precedents, a judge’s hands may be tied by particular contract language requiring the strict enforcement of notice requirements. Such provisions may include: (1) an explicit clause that there be precise compliance with notice requirements; (2) express consequences for noncompliance (e.g., if the required notice is not provided the claim will be waived, forfeited or abandoned); (3) a statement that the notice requirements are a condition precedent to recovery; (4) language such as “if,” “provided that,” “or else” or “on condition that” (e.g., the owner shall review the claim, “provided such claim” was received within the applicable notice period) or (5) prohibition of any waiver of the notice requirement. To the extent the notice provision includes such language, a contractor can be without recourse even when the owner has actual knowledge of the claims or cannot show prejudice by the lack of notice.
Read the court decisionRead the full story...Reprinted courtesy of
Jenifer B. Minsky, Peckar & Abramson, P.C.Ms. Minsky may be contacted at
jminsky@pecklaw.com
Six Reasons to Use Regular UAV Surveys on Every Construction Project
October 14, 2019 —
Dustin Price - Construction ExecutiveUAVs are the future of the construction industry. From accurate 3D modeling simulations to regular safety and maintenance checks, UAVs can improve construction projects in many ways—and the value and applications for UAVs is consistently growing. Drones are agile, cost-effective and safe.
Here are some reasons why UAV surveys should be part of any construction project.
1. UAV scans are much faster than human inspections
Drones can cover large territory much faster than human inspectors can. They can also be used over more difficult terrain, and they can survey areas that are otherwise inaccessible. A drone survey can be completed in a day; not only does this mean that the territory is well-surveyed each time, but it also means surveys can be done more frequently.
Construction projects need to be inspected regularly and on time if the project is to meet its deadlines. Delayed construction projects can cost a company millions of dollars, as construction projects need to be completed stage by stage, usually on a strict timeline. Drones will improve the consistency of the project and, in turn, this will improve the reputation of the company itself.
Reprinted courtesy of
Dustin Price, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Finalizes PPE Fitting Requirement for Construction Workers
December 31, 2024 —
Jonathan H. Schaefer - Construction Law ZoneOn December 11, 2024, the Occupational Safety and Health Administration (OSHA) announced it finalized a revision to the personal protective equipment (PPE) standard for the construction industry. The
final rule adds specific language to the existing standard requiring employers to provide properly fitting PPE for construction industry workers. This change aligns the construction industry with the standards in place for the general industry.
According to OSHA, many types of PPE must properly fit workers. Improperly sized PPE can ineffectively protect workers, creating new hazards for them, such as oversized gloves or protective clothing being caught in machinery and discouraging use because of discomfort or poor fit. OSHA stated that the longstanding issue with improperly fitting PPE particularly impacted women, as well as physically smaller or larger workers.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan H. Schaefer, Robinson+ColeMr. Schaefer may be contacted at
jschaefer@rc.com
EPA and the Corps of Engineers Repeal the 2015 “Waters of the United States” Rule
January 13, 2020 —
Anthony B. Cavender - Gravel2GavelThe pre-publication version of the final rule to be promulgated by EPA and the U.S. Army Corps of Engineers (ACOE) to repeal the 2015 redefinition of the Clean Water Act’s term “Waters of the United States” which is the linchpin of these agencies’ regulatory power under the CWA, was made available on September 12, 2019. The rule should be published in the Federal Register in the next few weeks, and it will be effective 60 days thereafter. Many challenges are expected to be filed in the federal courts.
The 2015 rule was very controversial, and petitions challenging the rule were filed in many federal district courts, several courts of appeal, and finally in the Supreme Court (see NAM v. Department of Defense), which held that all initial challenges must be filed in the federal district courts. The upshot of these challenges is that, at this time, the 2015 rule has been enjoined in more than half the states while the other states are bound by the 2015 rule, a situation which is frustrating for everyone.
In addition to repealing the 2015 rule, the agencies also restored the pre-2015 definition had had been in place since 1986. As a result, the pre-2015 definition of waters of the U.S. will again govern the application of the following rules: (a) the ACOE’s definition of “waters of the U.S.” at 33 CFR Section 328.3; (b) EPA’s general Oil Discharge rule at 40 CFR Section 110; (c) the SPCC rules at 40 CFR Part 112; (d) EPA’s designation of hazardous substances at 40 CFR Part 116; (e) EPA’s hazardous substance reportable quantity rule at 40 CFR Part 117; (f) the NPDES permitting rules at 40 CFR Part 122; (g) the guidelines for dredged or fill disposal sites at 40 CFR Part 230; (g) Exempt activities not requiring a CWA 404 permit (guidelines for 404 disposal sites at 40 CFR Part 232); (h) the National Contingency Plan rules at 40 CFR Part 300; (i) the designation of reportable quantities of hazardous substances at 40 CFR Part 302; and (j) EPA’s Effluent Guidelines standards at 40 CFR Part 401.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Arezoo Jamshidi Selected to the 2023 San Diego Super Lawyers List
April 03, 2023 —
Arezoo Jamshidi - Haight Brown & Bonesteel LLPCongratulations to Arezoo Jamshidi who has been selected to the 2023 San Diego Super Lawyers list. Each year, no more than five percent of the lawyers in the state are selected by the research team at Super Lawyers to receive this honor. Super Lawyers, part of Thomson Reuters, is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The annual selections are made using a patented multiphase process that includes a statewide survey of lawyers, an independent research evaluation of candidates and peer reviews by practice area. The result is a credible, comprehensive and diverse listing of exceptional attorneys. The Super Lawyers lists are published nationwide in Super Lawyers magazines and in leading city and regional magazines and newspapers across the country. Super Lawyers magazines also feature editorial profiles of attorneys who embody excellence in the practice of law.
Read the court decisionRead the full story...Reprinted courtesy of
Arezoo Jamshidi, Haight Brown & Bonesteel LLPMs. Jamshidi may be contacted at
ajamshidi@hbblaw.com
When is an Indemnification Provision Unenforceable?
September 06, 2021 —
Christopher G. Hill - Construction Law MusingsVirginia Code Sec. 11-4.1 makes indemnification provisions in construction contracts that are so broad as to indemnify the indemnitee from its own negligence unenforceable. Of course, this begs the question as to what language of indemnification provisions make them unenforceable.
A case from the City of Chesapeake Virginia Circuit Court examined this question. In Wasa Props., LLC v. Chesapeake Bay Contrs., Inc., 103 Va. Cir 423 [unfortunately I can’t find a copy to which to link], Wasa Properties (“Wasa”) hired Chesapeake Bay Contractors (“CBC”) to perform utility work at Lake Thrasher in the Tidewater area of Virginia. Wasa then alleged that CBC breached the contract and caused over $400,000 in damages due to incorrectly installed water lines. Wasa used the following indemnification language as the basis for its suit:
To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner and his agents and employees from and against all claims, damages, losses, and expenses, including but not limited to attorney’s fees arising out of or resulting from the performance of the Work.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com