NY State Appellate Court Holds That Pollution Exclusions Bar Duty to Defend Under Liability Policies for Claims Alleging Exposure to PFAS
February 01, 2022 —
Robert F. Walsh & Paul A. Briganti - White and Williams LLPOn January 6, 2022, the New York Supreme Court, Appellate Division, Third Department, held that the “sudden and accidental” pollution exclusion (SAPE) and “absolute” pollution exclusion (APE) in liability policies relieved two insurers of a duty to defend the insured-manufacturer in connection with claims alleging damages as a result of exposure to perfluorooctanoic acid (PFOA) and perfluorooctane sulfonate (PFOS), which are man-made chemicals within the group of per- and polyfluoroalkyl substances (PFAS). See Tonoga, Incorporated v. New Hampshire Insurance Company, No. 532546, 2022 N.Y. App. Div. LEXIS 105 (App. Div. 3rd Dep’t Jan. 6, 2022).
In Tonoga, starting in 1961, the insured and its predecessors owned and operated a manufacturing facility in Petersburg, New York that produced materials coated with polytetrafluoroethylene (PTFE). Until 2013, the manufacturing process involved the use of PFOA and/or PFOS. In early 2016, excessive PFOA and/or PFOS concentrations were detected in Petersburg’s municipal water supply. Later that year, the New York Department of Environmental Conversation designated the insured’s facility a Superfund site, and the insured entered into a consent agreement that required it to assist in remedial measures. 2022 N.Y. App. Div. LEXIS 105, at *1-2.
Reprinted courtesy of
Robert F. Walsh, White and Williams LLP and
Paul A. Briganti, White and Williams LLP
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
City Development with Interactive 3D Models
October 23, 2018 —
Aarni Heiskanen - AEC BusinessThe Finnish city of Hyvinkää has developed a unique internet service for collaborative 3D city planning. It gives real estate owners, investors, developers, designers, authorities, and citizens easy-to-use tools to publish their 3D plans and ideas for the built city environment.
Participants can comment on the 3D plans directly in the city model. The 3D app is integrated with Facebook, which enables further conversation.
Building the 3D City Model
Päivi Tiihonen is the manager of the information services unit of the city’s technical and environmental sector. The city started building a browser-based 3D city model when Tiihonen assumed her position in 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Account for the Imposition of Material Tariffs in your Construction Contract
March 28, 2018 —
David Adelstein – Florida Construction Legal UpdatesAfter Hurricane Irma, I wrote an article that contractors should revisit the
force majeure provisions in their construction contracts. Not later. But Now.
The force majeure provision is an important provision in a construction contract to account for certain uncertainties that you have NO control over.
Recently, another reason has given rise to contractors needing to revisit their force majeure provisions, as well as any provisions dealing with material escalations. Not later. But now. The
imposition of raw steel and aluminum tariffs (tax on imported goods) and the back-and-forth regarding a potential trade war leads to the kind of uncertainty that should be assessed as a risk.
A risk in both time and cost from material escalations.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Homebuilder Confidence Takes a Beating
October 21, 2013 —
CDJ STAFFHomebuilder confidence dropped to fifty-five percent in October, the lowest percentage seen in the last four months. The score had been rising on the strength of renewed home sales. The current slump is attributed to increases in interest rates, which have made home purchases more expensive for prospective buyers, and the uncertainty of the budget struggle in Washington.
John Stumpf, the chairman and CEO of Wells Fargo said that “home price appreciation remains strong and affordability remains excellent.” Mr. Strum has “guarded optimism” over the effects of the budget struggle.
Read the court decisionRead the full story...Reprinted courtesy of
Experts: Best Bet in $300M Osage Nation Wind Farm Dispute Is Negotiation
March 11, 2024 —
Daniel Tyson - Engineering News-RecordNearly two months after a federal judge ruled that renewables developer Enel Green Power North America must deconstruct 84 land-based wind turbines because it did not secure mineral rights on Osage Nation land in northern Oklahoma, two energy sector attorneys say the unit of an Italy-based company must negotiate with the tribe.
Reprinted courtesy of
Daniel Tyson, Engineering News-Record
Mr. Tyson may be contacted at tysond@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
What Is the Best Way to Avoid Rezoning Disputes?
August 30, 2021 —
Collier Marsh - Construction ExecutiveConstruction companies and developers are accelerating projects in the southeast and throughout the country as the economy rebounds from the worst of the COVID-19 pandemic. Whether they are building commercial, industrial or residential projects, these developments often require rezoning to maximize an investment. But rezoning disputes can add significant delays and costs to a project and can even defeat the project altogether.
There are proactive steps construction companies can take to avoid disputes as they are working to secure rezoning approval, as well after the rezoning is complete. During the initial rezoning process, before a final municipal decision, one of the best practices is to anticipate opposition and address it head-on. As for post-approval disputes, those often come down to how carefully a company followed the local procedures and, where applicable, the local evidentiary requirements.
Reprinted courtesy of
Collier Marsh, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Marsh may be contacted at
colliermarsh@parkerpoe.com
Washington, DC’s COVID-19 Eviction Moratorium Expires
August 23, 2021 —
Zachary Kessler, Amanda G. Halter & Adam Weaver - Gravel2Gavel Construction & Real Estate Law BlogThroughout the COVID-19 pandemic, federal and local governments have adopted varying moratoria on evictions, enacted as emergency legislative protections for tenants facing eviction. The federal moratorium on eviction, promulgated by the Centers for Disease Control and Prevention (CDC), is set to expire on July 31. While the Supreme Court recently left the moratorium in place, the Court signaled that it would likely be held unconstitutional if extended and challenged again. With the sole federal moratorium expiring, state and local protections may remain in effect; however, many of these local orders are also beginning to expire. Washington, DC’s eviction moratorium, one of the most tenant-friendly pieces of emergency legislation in the country, is one such example, beginning a phaseout process that allows the pace of evictions to slowly begin throughout 2021 before a final legislative sunset in February 2022.
In response to the COVID-19 pandemic, the Council of the District of Columbia and Mayor Muriel Bowser enacted a series of public health emergency legislation. Under the Coronavirus Omnibus Emergency Amendment Act of 2020, the Council put a pause on evictions for nonpayment of rent or violations of lease provisions, prohibiting landlords from filing a complaint to evict a tenant who detained “possession of real property without right” or whose “right to possession has ceased.” Under the moratorium, the Council effectively banned residential evictions, unless a court found that a tenant had performed an “illegal act” within the rental unit, that the tenant was causing undue hardship on the health, welfare, and safety of other tenants or neighbors, or that the tenant had abandoned the premises. The moratorium and other tenant-protections were initially set to remain in place indefinitely, expiring 60 days after the end of Mayor Bowser’s declared COVID-19 emergency period.
Reprinted courtesy of
Zachary Kessler, Pillsbury,
Amanda G. Halter, Pillsbury and
Adam Weaver, Pillsbury
Mr. Kessler may be contacted at zachary.kessler@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Fourth Circuit Clarifies What Qualifies As “Labor” Under The Miller Act
May 08, 2023 —
Jeffrey Hummel - The Construction SeytUnder the Miller Act, 40 U.S.C. §§ 3131 et seq., contractors hired to work on federal construction projects are required to furnish payment bonds in order to ensure payment to certain persons that provide labor for the project. The United States Court of Appeals for the Fourth Circuit recently issued a published decision clarifying the type of work that qualifies as “labor” under the Miller Act. Elliot Dickson v. Fidelity and Deposit Company (issued April 26, 2023).
In that case, the U.S. Department of Defense hired Forney Enterprises (Forney) as the prime contractor on a renovation project at the Pentagon. Forney retained Fidelity and Deposit Company of Maryland (Fidelity) to provide the required Miller Act payment bond. Forney then entered into a subcontract with Elliott Dickson (Dickson), a professional engineer, to work as a project manager on the contract. Dickson primarily supervised labor on the site, but also performed other tasks, including logistical and clerical duties, taking various field measurements, cleaning the worksite, moving tools and materials, and sometimes even watering the concrete himself. Dickson’s work required him to be onsite on a daily basis.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey Hummel, SeyfarthMr. Hummel may be contacted at
jhummel@seyfarth.com