Mind Over Matter: Court Finds Expert Opinion Based on NFPA 921 Reliable Despite Absence of Physical Testing
September 12, 2022 —
Gus Sara - The Subrogation StrategistIn Smith v. Spectrum Brands, Inc., 2022 U.S. Dist. LEXIS 142262, the United States District Court for the Eastern District of Pennsylvania (District Court) considered whether the plaintiffs’ liability expert met the requirements of Rule 702 of the Federal Rules of Evidence and could testify that a filter pump for an aquarium tank was defectively designed and caused a fire at the plaintiffs’ home. The defendant filed a motion to exclude the plaintiffs’ liability expert on grounds that the expert’s opinion did not satisfy the reliability element of Rule 702 because the expert never conducted physical testing on the filter pump. The court found that the cognitive testing employed by the expert through various methods, including visual inspections of the evidence, a review of photographs of the scene and literature from the manufacturer, and research on similar products, was sufficiently reliable to admit his opinion.
The Smith case involved a civil action brought by Jeanette Scicchitano Smith and Alexander Smith that arose from a 2019 fire at their residence in Lincoln University, Pennsylvania. The fire purportedly started in a filter pump, which was operating at the time of the fire, that the plaintiffs purchased in 2002 as part of an aquarium tank kit.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Seven Proactive Steps to Avoid Construction Delay Disputes
September 29, 2021 —
Michael Pink - Construction ExecutiveDelays, cost overruns and disputes have long been part of the commercial construction industry, making the work of reactive forensic analysis by consultants and attorneys a necessary component. Yet many internal practices and issues within construction companies strongly correlate with projects that result in legal disputes and financial losses. There are seven proactive steps that can help companies minimize losses and claims.
Prepare a Cost- and Resource-Loaded Critical Path Method Schedule
This is the first step any contractor can take to establish and document a manpower plan, a timeline and an intended flow for its work. Doing so is beneficial for two reasons: it will become the basis for measuring impacts and variances to both cost and schedule in a delay, dispute or claim setting; and it will serve as a great project management resource or tool. Without thinking through manpower, durations and workflow in great detail at the beginning of the project, contractors put themselves at risk of becoming delayed and blowing the budget.
Reprinted courtesy of
Michael Pink, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Supreme Court Rules in Builder’s Implied Warranty of Habitability Case
September 03, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to an article in JD Supra Business Advisor (written by Mark S. DePillis, Carl G. Roberts, Benjamin M. Schmidt, and Matthew White of Ballard Spahr LLP), “The Pennsylvania Supreme Court ruled that a builder’s implied warranty of habitability extends only to the initial buyer of a home, and not to subsequent purchasers.” This reversed an earlier ruling in Conway v. The Cutler Group, Inc. “that created more expansive liability for home builders.”
DePillis, Roberts, Schmidt, and White suggested that “builders should monitor possible future legislation addressing the public policy issues that the Supreme Court identified as falling squarely within the legislature’s domain.”
Read the court decisionRead the full story...Reprinted courtesy of
The Anatomy of a Construction Dispute Stage 2- Increase the Heat
January 21, 2015 —
Christopher G. Hill – Construction Law MusingsLast week we discussed the groundwork and circumstances of a construction claim. This week’s post will discuss the next steps, hopefully short of full blown arbitration or litigation that you, as a construction company, can pursue presuming your claim has been properly preserved.
If your contract requires certain steps such as informal resolution attempts or other items, these are the first things that must be done while still preserving your rights to pursue all remedies available. Instituting such contractually required resolution steps can and should be the first “notch” on the dial of increased pressure on the Owner, General Contractor or possibly Subcontractor against whom you have a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Federal Court Holds that Demolition Exclusion Does Not Apply and Carrier Has Duty to Defend Additional Insureds
September 02, 2024 —
Craig Rokuson - Traub LiebermanIn the recent case of
Travelers Indem. Co. v. Trisura Specialty Ins. Co., 2024 U.S. Dist. LEXIS 101953 (S.D.N.Y. June 7, 2024), the court had occasion to consider the classic additional insured fact pattern of a construction accident. Travelers insured the general contractor and provided a defense to the general contractor as well as its wholly owned subsidiary. Trisura insured the subcontractor, who employed the injured worker. Travelers brought suit, alleging that Trisura is obligated to defend and indemnify the general contractor, its subsidiary, the owner of the building (The City of New York), and the tenant.
Trisura denied any obligation to provide coverage due to the application of the “Demolition Exclusion” to the Trisura policy, which provides, in part, that there is no coverage for injury or damage arising out of the demolition of any building or structure which has original ground height in excess of three stories. The accident occurred during the interior demolition of the fifth floor of the building. The court held that the Demolition Exclusion applies only when there is a complete tearing down, razing, or destruction of an entire building. As the accident occurred during interior demolition, the exclusion did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Sustainability Is an Ever-Increasing Issue in Development
November 21, 2022 —
Scott L. Baker - Los Angeles Litigation BlogBusinesses must be open to change. It is essential to survive in the business world, regardless of the industry. This goes hand-in-hand with the necessity to change along with consumer needs and values as well.
With the increasing emphasis on sustainability across industries, many businesses have had to make their processes and products more environmentally friendly. However, in terms of real estate construction, there are some challenges.
SUSTAINABILITY IN NEW CONSTRUCTION IS NOW A MATTER OF LAW – NOT JUST A PREFERENCE
The push to become greener comes from many fronts. Property owners, potential buyers and even lawmakers all expect the real estate industry to go greener. For example, homeowners and businesses often want their properties to meet their personal values of sustainability.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Governor Signs AB5 Into Law — Reshaping California's Independent Contractor Classification Landscape
December 02, 2019 —
Eric C. Sohlgren & Matthew C. Lewis - Payne & Fears Legal AlertToday, Governor Gavin Newsom signed California Assembly Bill 5 (“AB5”), controversial legislation which will have a substantial impact on California employers when it goes into effect on January 1, 2020.
AB5 enacts into a statute last year’s California Supreme Court decision in Dynamex Operations West, Inc. v. Superior Court, 4 Cal. 5th 903 (2018), and the Court’s three-part standard (the “ABC test”) for determining whether a worker may be classified as an employee or an independent contractor.
Under the ABC test established in Dynamex and now under AB5, a worker may be properly considered an independent contractor only if the hiring entity establishes all three of the following: (A) that the worker is free from the control and direction of the hirer in connection with the performance of the work, both under the contract for the performance of such work and in fact; (B) that the worker performs work that is outside the usual course of the hiring entity’s business; and (C) that the worker is customarily engaged in an independently established trade, occupation, or business of the same nature as the work performed for the hiring entity.
Reprinted courtesy of
Eric C. Sohlgren, Payne & Fears and
Matthew C. Lewis, Payne & Fears
Mr. Sohlgren may be contacted at ecs@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com