General Release of Contractor Upheld Despite Knowledge of Construction Defects
February 27, 2019 —
Garret Murai - California Construction Law BlogAh, the elusive Lepus Cornutus, commonly known as the Jackalope. Rarely seen, we may have one in SI 59 LLC v. Variel Warner Ventures, LLC, Court of Appeals for the Second District, Case No. B285086 (November 15, 2018), an interesting case involving a developer, a contractor, a general release, and Civil Code section 1688.
SI 59 LLC v. Variel Warner Ventures, LLC
In 2005, Variel Warner Ventures, LLC (Variel Warner) entered into a construction contract with Verdugo Management & Investment, Inc. (Verdugo) to construct improvements at an 85 unit apartment complex. Under the terms of the contract, Verdugo agreed to construction the improvements in a good and workmanlike manner in strict compliance with all drawings and specifications and to comply with all laws. It didn’t. The work was defectively flashed, counterflashed, and waterproofed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
New Addition to the ASCE/SEI 7-22 Standard Protects Buildings from a 500-year Flood Event
June 05, 2023 —
The American Society of Civil EngineersReston, VA — The
American Society of Civil Engineers (ASCE) released a new update to their most widely used standard today,
ASCE/SEI 7-22 Minimum Design Loads and Associated Criteria for Building and Other Structures. As the increasing frequency of severe storms puts strain on communities across the globe, the design standard's
new flood load provisions will protect against 500-year flood events, which is a significant improvement to the 100-year flood hazard referenced in the previous version. The update — which is available in a supplement as a free download — is a significant revision of the design provisions in Chapter 5 to strengthen building resilience against the flood hazard. The ASCE 7 national loading standard is an integral part of building codes in the United States and around the globe.
"For more than 30 years, the ASCE 7 standard has been the authoritative source for the specification of minimum design loads and related criteria in the civil engineering community," said Tom Smith, ASCE Executive Director. "To ensure structures continue to be safe for the public, it is imperative that the standards we rely on are updated to account for emerging risks to the built environment. This Supplement is the most significant change to the standard's flood load provisions since the inception of ASCE 7 and will improve the safety and reliability of structures across the globe."
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Arbitration and Mediation: What’s the Difference? What to Expect.
September 09, 2019 —
Brittany Rupley Haefele - Porter Law GroupMediation
Mediation is a process in which a neutral person or persons facilitate communication between the disputants to assist them in reaching a mutually acceptable settlement agreement. During this process, a neutral third party, with no decision-making power, intervenes in the dispute to help the litigants voluntarily reach their own agreement. Through a series of discussions, statements and private caucuses between the parties and the mediator, the process lets both parties negotiate and agree to a resolution with which everyone can abide. It is an excellent method of bringing a dispute to a conclusion without the further uncertainty and expense of litigation.
Arbitration
Arbitration, in addition to mediation, is one of the most common methods of alternative dispute resolution (“ADR”), whereby the parties bring a dispute before a disinterested third party who is typically selected by both parties. An arbitrator hears evidence presented by the parties, makes legal rulings, determines facts and makes an arbitration award. Arbitration awards may be entered as judgments in accordance with the agreement of the parties or, where there is no agreement, in accordance with California statutes. Arbitrations can be binding or non-binding, as agreed by the parties in writing. In most cases, the arbitrator’s decision is binding and final.
When is it Appropriate to Engage in Mediation and/or Arbitration?
Mediation can be held at any time, before or during a lawsuit. It is a voluntary process, where both sides simply agree to go to mediation in an effort to get the case settled. Sometimes, it is a contractually required process for the parties to complete prior to going to litigation or arbitration. Typically, in this situation, if a party ignores this requirement and fails to participate in a contractually mandated mediation, they will lose their rights to recover attorneys’ fees and costs – even if they ultimately prevail. Other times, mediation is strongly encouraged by the judge if a lawsuit has already been filed, and some would even say, ordered by the court (though it is typically not called “mediation” but something very similar like a “Dispute Resolution Conference” or “Mandatory Settlement Conference”).
Read the court decisionRead the full story...Reprinted courtesy of
Brittany Rupley Haefele, Porter Law GroupMs. Haefele may be contacted at
bhaefele@porterlaw.com
Who is Responsible for Construction Defect Repairs?
August 24, 2017 —
Laura Parsons-CDJ STAFFAn appellate court has ruled that the sponsor and not the condo board is responsible for repairing construction defects at 50 Madison Avenue, a multi-story apartment building in New York City across from Madison Square Park, Habitat reported. Plaintiff’s Simon and Ludmilla Lorne have brought upon three lawsuits in a legal battle lasting a decade.
The first came in 2007, two years after the Lorne’s purchased their $3 million seventh-floor apartment. At that time, the sponsor offered to repair the concrete slab under the hardwood floors that had not been properly leveled. However, the Lorne’s and the condo board disagreed about who and how the repairs would be accomplished. The second lawsuit wherein the court ruled that repairing the construction defects was the responsibility of the sponsor occurred in 2009. However, the Lorne’s sued the board yet again in 2015, citing failure to maintain and repair the building. Since the 2015 suit was based on the same allegations as the 2007 suit, it was dismissed by the judge.
Read the court decisionRead the full story...Reprinted courtesy of
San Diego Developer Strikes Out on “Disguised Taking” Claim
October 26, 2017 —
Michael C. Parme – Haight Brown & Bonesteel LLPIn Dryden Oaks, LLC v. San Diego County Regional Airport Authority et al.(D068161, filed 9/26/17, publication order 10/19/17), the California Court of Appeal, Fourth Appellate District held that the County of San Diego (County) and the San Diego Regional Airport Authority (Authority) were entitled to summary judgment on a developer’s “disguised taking” theory of inverse condemnation.
In 2001, the developer purchased two large lots (designated Lot 24 and Lot 25) adjacent to the end of a runway at the Palomar Airport in Carlsbad. Plaintiff obtained the necessary permits from the City of Carlsbad and successfully completed construction of an industrial building on Lot 24 in 2005. However, the plaintiff never began development of Lot 25 and the building permit for the property expired in 2012. The developer was then unable to renew the building permit because the Authority had adopted the Airport Land Use Compatibility Plan (ALUCP) in the interim period, which reclassified the Lots as part of a Runway Protection Zone (RPZ). The developer received a letter explaining that “despite the earlier approval the proposed development was no longer feasible because the ALUCP was more restrictive than the prior compatibility plan and the application's proposed use of ‘research and development’ was not permissible.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael C. Parme, Haight Brown & Bonesteel LLPMr. Parme may be contacted at
mparme@hbblaw.com
Owner Bankruptcy: What’s a Contractor to Do?
February 28, 2018 —
Troy R. Covington and Stephen M. Parham - Construction Executive MagazineBankruptcy of the owner or developer of a real estate construction project can be very unsettling to contractors. But a declaration of bankruptcy by the developer, in and of itself, does not constitute a breach of contract such that the contractor can stop working. Contract provisions providing that the contract is terminated if a party becomes insolvent or files for bankruptcy are generally unenforceable.
Partially-performed construction contracts are executory contracts, meaning that the obligations of the parties to the contract have not yet been fully performed. The Bankruptcy Code allows a bankruptcy trustee (in a Chapter 7 dissolution case) or the debtor-in-possession (in a Chapter 11 reorganization case) either to assume or to reject an executory contract. A debtor-in-possession has until the time of the confirmation of its plan of reorganization to decide if it will assume or reject the contract. The contractor may ask the bankruptcy court to require the debtor-in-possession to make a decision on the contract sooner, but the court will most likely give the debtor-in-possession a fair amount of time to make the decision.
Reprinted courtesy of
Troy R. Covington and
Stephen M. Parham, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Covington may be contacted at sparham@bloomparham.com
Mr. Parham may be contacted at tcovington@bloom-law.com
Read the court decisionRead the full story...Reprinted courtesy of
Better Building Rules Would Help U.K.'s Flooding Woes, CEP Says
January 06, 2016 —
Jill Ward – BloombergTighter construction restrictions and incentives to build outside flood-prone areas would minimize damage to the U.K. economy from heavy rain and rising water levels, according to the Centre for Economic Performance.
Thousands of families across northern England and Scotland have evacuated their homes or been left without power in recent weeks, while KPMG LLP estimated the economic loss in December was more than 5 billion pounds ($7.3 billion). While low-lying areas are more likely to be hit by large-scale floods, businesses and homes don’t tend to move to safer locations, according to the CEP’s analysis of data from 2003 to 2008.
Read the court decisionRead the full story...Reprinted courtesy of
Jill Ward, Bloomberg
Court of Appeals Finds Arbitration Provision Incorporated by Reference Unenforceable
September 20, 2021 —
Garret Murai - California Construction Law BlogSubcontractors have gotten accustomed to incorporation clauses in their contracts. While an incorporation clause can incorporate any document, most typically, it’s the prime contract between the general contractor and the project owner. Subcontractors will sometimes even accept these documents sight unseen which can be a recipe for disaster. But not in the next case.
In Remedial Construction Services, LP v. AECOM, Inc., Case No. B303797 (June 15, 2021), the 2nd District Court of Appeal examined whether a subcontractor was bound to an arbitration provision contained in a prime contract that was incorporated by reference into the subcontractor’s contract. In this case, it was the prime contractor who was in for a surprise.
The Remedial Construction Case
In 2015, Shell Oil Products US, LLC entered into a prime contract with AECOM Technical Services, Inc. for the demolition, remediation and restoration of the Gaviota oil terminal in Goleta, California. AECOM in turn entered into a subcontract with Remedial Construction Services, LP to perform portions of the work. When AECOM refused to pay Remedial for delay costs asserted by Remedial, Remedial filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at