Contractors May be Entitled to Both Prompt Payment Act Relief and Prejudgment Interest for a Cumulative 24%!
August 22, 2022 —
Margarita Kutsin - Ahlers Cressman & SleightThe Washington Prompt Payment Act, in Ch. 39.76 RCW and in RCW 39.04.250, ensures that contractors and subcontractors are promptly paid for their performance on public works contracts. Where a government entity or a prime contractor wrongfully withholds undisputed amounts due, that government entity or prime contractor must pay interest at a rate of 12% per annum.
Separately, prejudgment interest is awarded “based on the principle that a defendant ‘who retains money which he ought to pay to another should be charged interest upon it.’” Hansen v. Rothaus, 107 Wn.2d 468, 472, 730 P.2d 662 (1986) (quoting Prier v. Refrigeration Eng’g Co., 74 Wn.2d 25, 34, 442 P.2d 621 (1968)). The purpose is to “compensate the plaintiff for the use value of the money representing liquidated or determinable damages.” Id.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
California Supreme Court Upholds Insurance Commissioner’s Authority to Regulate Replacement Cost Estimates
January 26, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPn Assn. of Cal. Insurance Companies v. Jones ( No. S226529, filed 1/23/17), the California Supreme Court reversed trial and appellate court decisions to hold that California’s Insurance Commissioner Dave Jones had the authority to promulgate California Code of Regulations, title 10, section 2695.183, which sets out specific requirements for estimating replacement cost as part of any application for or renewal of homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the Southern California wildfires of 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Risks and Rewards of Sustainable Building Design
July 25, 2021 —
Caroline A. Harcourt & Adam Weaver - Gravel2GavelThe shift towards a “greener” environment has resulted in cities and states implementing electrification mandates, which will have a major impact on both current and future building design. Currently, most commercial and residential end users are already all-electric. However, there are some exceptions, such as space and water heating, that use a significant amount of energy. Several states, including California and New York, have cities that have introduced legislation requiring new construction to be all-electric. This means, for example, using electricity for heating rather than fossil fuels such as natural gas. Mandate or not, building owners and developers should consider the risks and rewards of an all-electric design.
General Rewards
- Reaching Climate Goals: As part of the Clean Energy Plan, as described in a previous post, President Biden has created a goal for the United States of achieving a carbon pollution-free American utility sector by 2035. Because residential and commercial building account for 40 percent of energy consumption in the United States, all-electric building designs will help governments and businesses reach the ambitious climate goals that have been set for the coming years.
Reprinted courtesy of
Caroline A. Harcourt, Pillsbury and
Adam Weaver, Pillsbury
Ms. Harcourt may be contacted at caroline.harcourt@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
For Whom Additional Insured Coverage Applies in New York
November 11, 2024 —
Bill Wilson - Construction Law ZoneSimply including a requirement in a contract to add certain parties as additional insureds under a commercial general liability insurance (CGL) policy may not be enough to ensure such coverage is provided in New York. In New York City Hous. Auth. v. Harleysville Worcester Ins. Co., 226 A.D.3d 804 (2024), the New York Supreme Court Appellate Division – Second Department ruled that the language in an insurance endorsement required privity of contract with the insured party subcontractor to obtain additional insured status and denied coverage to others despite a provision in a subcontract requiring such additional insured coverage.
In this case, an owner entered into a contract with a general contractor for construction services. The general contractor entered into a subcontract with a subcontractor. The subcontractor agreed to procure and maintain a CGL policy naming the owner, the general contractor, and another related party as additional insureds thereunder. An employee of the subcontractor was injured on the project and sued the three additional insureds and several other parties. Subcontractor’s insurance company refused to defend and indemnify any party other than the general contractor. All the parties sued by the subcontractor’s employee brought an action against the subcontractor’s insurance company, seeking coverage for defense and indemnification as additional insureds under the subcontractor’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Congratulations to Las Vegas Team on Their Successful Motion for Summary Judgment!
May 06, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPThis case arose from an alleged trip and fall on an uneven surface in a parking lot outside of BWBO’s client’s restaurant. Plaintiff alleged more than $385,000 in past medical specials (with high potential for future care and treatment) with exposure in excess of $1,000,000.00. The Plaintiff named as Defendants BWBO’s client as well as several entities related to their landlord.
Early in the case, Las Vegas Partner Jeffrey W. Saab and Senior Associate D. Ryan Efros moved for summary judgment based on terms of the restaurant’s lease. They argued that based on the lease, the duty to maintain the surface of the parking lot fell exclusively to the landlord, rather than the restaurant’s client. Plaintiff opposed the motion arguing that the prevailing case law held that any agreement between a tenant and its landlord does not preclude a plaintiff from asserting either or both defendants breached their duties of care. Jeff and Ryan distinguished that case and successfully persuaded the Court that there could be no contractual duty and no common law duty to maintain the parking surface, clearing the way for the court to grant summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Bremer Whyte’s Newport Beach Team Prevails on a Motion for Summary Judgment in a Wrongful Death Case!
September 02, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations on another win to Orange County Partners
Jonathan Cothran and
Rachel Mihai for prevailing on a Motion for Summary Judgment in a wrongful death case!
Plaintiffs filed a wrongful death lawsuit alleging negligence and vicarious liability against BWB&O’s client, a licensed electrical contractor. BWB&O’s client installed a solar system at the Plaintiffs’ home in January 2018. In October 2018, an electrical fire broke out at the home in an upstairs bedroom. Tragically, the family’s father perished in the fire when he entered the home after the fire started. Plaintiffs alleged that BWB&O’s client was liable for the fire and Plaintiffs’ resulting injuries due to its electrical work on the solar system at the home.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Rather Than Limit Decision to "That Particular Part" of Developer's Policy Necessary to Bar Coverage, 10th Circuit Renders Questionable Decision on Exclusion j(6)
September 06, 2021 —
William S. Bennett - Saxe Doernberger & Vita, P.C. The 10th Circuit Court of Appeals, applying Colorado law, recently extended Colorado’s broad application of the phrase “arising out of” in insurance interpretation, barring an insured real estate developer from receiving a defense to a suit alleging liability for construction of a defective retaining wall and associated resulting damage.1 The decision also included a questionable analysis of the commercial general liability (“CGL”) policy’s exclusion j(6), contradicting both the plain meaning of the exclusion as well as existing 10th Circuit case law.
The underlying dispute concerned a land developer, HT Services, LLC, who was sued by the homeowner’s association (“HOA”) of one of its developments. The HOA alleged that HT Services negligently designed and constructed a retaining wall in the community. HT Services had CGL policies from Western Heritage Insurance Company in place from 2010 to 2013 that insured it for liability associated with four acres of land that the community was built upon.
HT Services tendered the HOA’s lawsuit to Western Heritage, which declined to defend and indemnify HT Services. After that matter settled, HT Services sued Western Heritage, alleging breach of contract and bad faith. Western Heritage moved for summary judgment, asserting two exclusions, and the District Court granted the motion in Western Heritage’s favor. In upholding the District Court’s decision, the 10th Circuit discussed two exclusions that the District Court determined precluded coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Musk Says ‘Chicago Express’ Tunnel Project Could Start Work in Months
August 14, 2018 —
Jeff Yoders – Engineering News-RecordTechnology guru Elon Musk beat three other construction proposals on June 14 to win the exclusive right to negotiate a design-build-operate-maintain contract with the City of Chicago to provide a high-speed underground passenger transport system between the downtown Loop area and O’Hare Airport. He proposes a one-way trip of about 12 minutes at 150 mph compared with the current 40-minute average by rail or car.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at