Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Naples, Florida, Is Getting So Expensive That City Workers Can’t Afford It
April 10, 2023 —
Amanda Albright - BloombergThe city of Naples on Florida’s Gulf Coast is paradise on Earth, if you believe those slick websites that rank the best US cities to live in or retire in. But if you talk with the people who work in its hospitals, restaurants and city government, you’ll get another story. They’d like to live in Naples, too, but most of them can’t afford to.
The city of 19,000 is home to the second-richest ZIP code in the US, after Miami Beach. Median household income stood at about $125,000 in 2021, compared with about $62,000 in Florida overall, according to the Census Bureau. Naples landed on a 2022 list of least affordable places for renters compiled by the National Apartment Association.
Amid a dearth of reasonably priced housing, at least 90% of city employees live outside Naples. Job vacancies are going unfilled, leading to chronic staffing shortages. The shortfall among firefighters, police officers and other essential workers in Collier County, which includes Naples, verges on unsafe, according to one local advocate. Private-sector employers have converted a hotel into apartments for workers as a temporary fix.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda Albright, Bloomberg
Prison Time and Restitution for Construction Fraud
February 14, 2013 —
CDJ STAFFFederal prosecutors have obtained prison sentences and fines for the two leaders of a construction kickback scheme. Others are awaiting sentencing. The Chicago Sun-Times reports that John Paderta the former president of Krahl Construction has been sentenced to five years in prison and must pay $10 million in restitution. His executive vice president, Doug Harner will be spending five years in prison and has been ordered to pay $9.6 million in restitution.
Paderta and Harner overbilled two clients on renovation projects, giving kickbacks to employees at the client companies. Two employees of these client companies have pled guilty. A further five employees of the three companies have admitted that they were involved in the fraud. They are yet to be sentenced.
Read the court decisionRead the full story...Reprinted courtesy of
Interpreting Insurance Coverage and Exclusions: When Sudden means Sudden and EIFS means Faulty
June 15, 2020 —
Ben Volpe - Colorado Construction Litigation BlogEIFS, or Exterior Insulation and Finish System, is an integrated exterior insulation and synthetic stucco system, praised for its energy efficiency.[1] However, EIFS has come to be well known in the construction defect world as placing homes at risk due to a lack of a built-in moisture management system. Before long, insurance companies recognized the risk and began explicitly excluding coverage for EIFS-related damage. However, EIFS exclusions have not always been so clearly set forth in some policies, causing insurance coverage litigation.
Recently, a Greenwood Village couple, Mark and Susan Mock, lost this fight.
Built in 1994, the Mocks’ home was constructed with an EIFS system. The Mocks carried a homeowner’s insurance policy through Allstate, which covered “sudden and accidental loss” to property, but excluded coverage for “planning, construction or maintenance” issues. Such “planning, construction or maintenance” exclusions included “faulty, inadequate or defective designs.”
A few months after a hailstorm, the Mocks discovered moisture-related damage to their home’s EIFS system. They reported the damage to Allstate, but Allstate would not cover it, reasoning that the damage to the EIFS system was excluded as a design and/or construction failure, and thus not covered as a “sudden and accidental” loss. The experts who evaluated the damage concluded it was the result of inherent flaws in the EIFS systems common in the 1994 timeframe, which involved long term moisture intrusion behind the cladding and no means for the water to escape.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Volpe, Higgins, Hopkins, McLain & Roswell, LLCMr. Volpe may be contacted at
volpe@hhmrlaw.com
Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
More Reminders that the Specific Contract Terms Matter
January 24, 2022 —
Christopher G. Hill - Construction Law MusingsIf there is a theme I have pounded upon here at Construction Law Musings in the over 13 years of posting, it is that the specific terms of your construction contracts will make a huge difference. While there have been reminders galore, a case from the Eastern District of Virginia presented another wrinkle on this theme. The wrinkle? A factoring company.
In CJM Financial, Inc. v. Leebcor Services, LLC et. al., the Court examined this scenario (though it went into more detail than I will here): Leebcorp hired a subcontractor, Maston Creek Services to provide certain construction services under two separate contracts. Maston then hired CJM, a factoring company, and assigned CJM its receivables and the right to collect those receivables. We wouldn’t be discussing this case if all had worked out as planned, so you likely anticipate at least some of what came next. The short story is that Matson failed to pay some of its suppliers and Leebcorp exercised its termination rights under those contracts when Matson refused to cure. In the interim, CJM had paid part of certain payment applications to Matson in compliance with the factoring agreement. When Leebcorp failed to pay CJM for Matson’s work, CJM exercised its assigned rights to collect the receivables and sued Leebcorp for breach of contract. In response, Leebcorp counterclaimed for, among other counts including civil conspiracy, breach of contract based on Matson’s failure to perform. CJM moved to dismiss the counterclaims.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What to Do Before OSHA Comes Knocking
December 19, 2018 —
Parker Rains - Construction ExecutiveEvery year, the U.S. Occupational Safety and Health Administration (OSHA) inspects workplaces around the country for safety and occupational hazards. In 2017 alone, OSHA conducted 32,408 inspections – more than half of which were unprogrammed inspections.
There are six reasons OSHA might come knocking on the door. They are (in order of priority):
- imminent danger situations;
- severe injuries and illnesses;
- worker complaints;
- referrals;
- targeted inspections; and
- follow-up inspections.
Reprinted courtesy of
Parker Rains, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rains may be contacted at
prains@fbbins.com
No Damages for Delay May Not Be Enforceable in Virginia
January 08, 2024 —
Christopher G. Hill - Construction Law MusingsAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia. Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work. However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment. This left open the question as to which types of “diminishment” would be barred by the statute.
The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at