Terminating Contracts for Convenience — “Just Because”
June 28, 2021 —
David Adelstein - Florida Construction Legal UpdatesTermination for convenience provisions are important provisions to include in construction contracts. These are provisions that allow a party to terminate the contract for ANY REASON. No cause is needed to exercise the termination for convenience provision. In other words, the terminating party does not have to demonstrate the other party breached the contract. A termination for convenience can be exercised “just because.”
Typically, the party providing the service should not get to terminate for convenience. However, the party receiving the service will want to be afforded this contractual right.
For example, an owner (receiving a service) will want to include a termination for convenience provision with its prime contractor (providing a service). And, a general contractor (receiving a service) will want to include a termination for convenience provision in its subcontract with its subcontractor (providing a service). However, a general contractor providing a service for an owner, or a subcontractor providing a service to a general contractor, should not be able to terminate the contract for their convenience “just because” a better opportunity comes along.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Upturn in Silicon Valley
August 17, 2011 —
CDJ STAFFWork resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.
A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Three Kahana Feld Attorneys Recognized in The Best Lawyers in America® 2025
September 23, 2024 —
Linda Carter - Kahana FeldNEW YORK – Sep. 4, 2025 – Kahana Feld is pleased to announce that Eric Bernhardt and Kraig Kilger were included in the 2025 edition of The Best Lawyers in America® and Alice A. Trueman was included in Best Lawyers: Ones to Watch® in America.
Eric Bernhardt was awarded for his work in Litigation – Insurance. Bernhardt is a partner in the firm’s Buffalo, NY office, admitted in New York and California, and a member of Kahana Feld’s national appellate practice group. His practice encompasses multiple types of litigation including the defense of New York Labor Law, construction, product liability, trucking, professional and medical malpractice, automobile accident, and general negligence cases.
Kraig Kilger was recognized in the areas of Bankruptcy and Creditor Debtor Rights/Insolvency and Reorganization Law, Litigation – Real Estate, and Real Estate Law. Kilger is a partner in Kahana Feld’s Irvine, CA office. His experience spans all phases of residential and commercial real estate development, including acquisitions, financing, planning, entitlement, development, construction, leasing, and sales.
Alice Trueman was recognized by Best Lawyers: Ones to Watch in the field of Personal Injury Litigation – Defendants. She is a litigation attorney in the firm’s Buffalo, NY office who focuses her practice on general liability defense and insurance defense. Ones to Watch recipients typically have been in practice for 5-9 years and are selected for their outstanding professional excellence in private practice.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Release Of “Unknown” Claim Does Not Bar Release Of “Unaccrued” Claim: Fair Or Unfair?
July 15, 2019 —
David Adelstein - Florida Construction Legal UpdatesA general release of “unknown” claims through the effective date of the release does NOT bar “unaccrued” claims. This is especially important when it comes to fraud claims where the facts giving rise to the fraud may have occurred prior to the effective date in the release, but a party did not learn of the fraud until well after the effective date in the release. A recent opinion maintained that a general release that bars unknown claims does NOT mean a fraud claim will be barred since the last element to prove a fraud had not occurred, and thus, the fraud claim had not accrued until after the effective date in the release. See Falsetto v. Liss, Fla. L. Weekly D1340D (Fla. 3d DCA 2019) (“The 2014 [Settlement] Agreement’s plain language released the parties only from “known or unknown” claims, not future or unaccrued claims. Because there is a genuine issue of material fact as to whether the fraud claim had accrued — that is, whether Falsetto [party to Settlement Agreement] knew or through the exercise of due diligence should have known about the alleged fraud at the time the 2014 Agreement was executed — the trial court erred in granting summary judgment on those fraud claims.”).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 —
CDJ STAFFOne June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Use It or Lose It: California Court of Appeal Addresses Statutes of Limitations for Latent Construction Defects and Damage to Real Property
August 02, 2017 —
Omar Parra & Jesse M. Sullivan - Haight Brown & Bonesteel LLPThe First Appellate District of the California Court of Appeal recently confirmed California’s latent defect statute of limitations, codified in California Code of Civil Procedure section 337.15, bars only claims based on construction defects. Estuary Owners Association v. Shell Oil Company, No. A145516, (Cal. Ct. App. July 26, 2017). The Court also reemphasized that under California’s three-year statute of limitations for damage to real property, delineated in California Code of Civil Procedure section 338(b), the actual and constructive knowledge of the prior landowner is imputed to the current landowner.
Estuary Owners Association concerned the development and construction of a 100-unit condominium by Signature at the Estuary, LLC (“Signature”) on land Shell Oil Company (“Shell”) previously used as a fuel distribution terminal. Construction of the condominiums was completed in 2006. In 2008, it was discovered that residual concentrations of petroleum related chemicals remained in the soil, soil gas, and groundwater beneath the development. Later that year, Signature revealed that the condominiums had been constructed with moisture barriers beneath the building slabs instead of the vapor/gas barriers called for in the corrective action plan.
Reprinted courtesy of
Omar Parra, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Parra may be contacted at oparra@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What is the Effect of an Untimely Challenge to the Timeliness of a Trustee’s Sale?
April 13, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogEver wonder what happens if a person challenges the timeliness of a trustee’s sale after the sale already occurred? Waiver of the argument of course! And, in the case of Wells Fargo Bank, N.A. v. Waltner, the affirmance of an eviction judgment.
In the Waltner case, Wells Fargo Bank, N.A., as Trustee for WaMu Mortgage Pass-Through Certificates, Series 2005-PR4 Trust (the “Bank”), purchased a residential property at a trustee’s sale in September 2015. The Bank gave the occupant of the house, Sarah Waltner (“Waltner”), notice to vacate the property, but she did not do so. Accordingly, the Bank filed a summary action to evict Waltner, which the trial court ultimately granted.
After the trial court granted the Bank relief, Waltner filed a motion to dismiss and a motion to vacate the eviction judgment arguing, among other things, that the judgment was void because the Bank conducted the trustee’s sale after the statute of limitations expired. Both motions were denied, and Waltner appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
The Moving Finish Line: Statutes of Limitation and Repose Are Not Always What They Seem
June 01, 2020 —
Kenneth E. Rubinstein & Nathan Fennessy - Construction ExecutiveHaving an end date for risk is important to construction professionals who need to know when they can close their books and destroy files relating to old projects. While professionals typically look to the statute of limitations and repose, these deadlines can sometimes be harder to determine than one might think.
State Laws Prohibiting Alteration of Statutes of Limitation
Many contractors seek to control the extent of their risk by negotiating the length of their liability period. In some instances, contractors may seek to shorten the statute of limitations to protect against stale claims. While in other instances, owners periodically negotiate for longer periods to ensure that they will not be time barred from pursuing valid claims. While the majority of states enforce such contractual provision, a number of states hold such clauses unenforceable. In these instances, the state’s original statute of limitations will apply regardless of what the contract says.
Reprinted courtesy of
Kenneth E. Rubinstein & Nathan Fennessy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Rubenstein may be contacted at krubinstein@preti.com
Mr. Fennessy may be contacted at nfennessy@Preti.com
Read the court decisionRead the full story...Reprinted courtesy of