Lease-Leaseback Battle Continues as First District Court of Appeals Sides with Contractor and School District
August 17, 2017 —
Garret Murai - California Construction Law BlogEarlier, we wrote about Davis v. Fresno United School District (2015) 237 Cal.App.4th 261, a Fifth District California Court of Appeals decision that sent shock waves through the school construction industry and raised questions regarding the use of California’s lease-leaseback method of project delivery (Education Code sections 17400 et seq.).
California’s lease-leaseback method of project delivery provides an alternative project delivery method for public school districts than the usual design-bid-build method of project delivery. Under the lease-leaseback method of project delivery, a school district leases its property to a developer, who in turn builds a school facility on the property and leases it back to the school district. One of the benefits of the lease-leaseback method of project delivery is that school districts do not need to come up with construction funds to build school facilities since they pay for the construction over time through their lease payments to the developer. Critics, however, argue that because lease-leaseback projects do not need to be competitively bid, they are ripe for cronyism between developers and school districts.
In Davis, a taxpayer successfully brought suit against the Fresno Unified School District challenging the propriety of a lease-leaseback project because the entirety of the District’s “lease payments” occurred while the project was being constructed and thus, successfully argued the taxpayer, there was no “true” lease of a facility since it was under construction.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part I
March 22, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Here’s a helpful comparison of and analysis of some important contract sections in the
AIA 201 (2007 and 2017 versions) and
ConsensusDocs (2014 and 2017 versions). While not intended to be all inclusive, this summary comparison of the contract documents will run as a three-part series. Part I covers Financial Assurances, Design Risk, Project Management and Contract Administration. Part II will cover Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR. Part III will cover Insurance and Indemnification and Payment.
FINANCIAL ASSURANCES
- What assurances are there that the owner can pay for the project?
- The Contractor should have the right to request and obtain proof that the Owner has funding sufficient to pay for the Work. The provision should also provide that the Contractor may terminate the Contract if the Owner refuses to allow a review of funding documents, or should the Contractor reasonably determine that the Owner does not have sufficient funds to pay for the Work.
Relevant Sections:
- A201 2007 Section 2.2.1; 2017 Section 2.2.1-2.2.2 A201
- 2014 & 2017 ConsensusDocs 200: Section 4.2
AIA:
- Section 2.2.1 A201 2007 & 2017: Both editions require the Owner, upon Contractor’s written request, to provide, “reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract.” Thereafter, the Contractor may only request such evidence if (1) the Owner fails to make payments; (2) a change in the Work materially changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due. If the Owner does not comply, the Contractor may stop work.
- Additionally, A201 2017 Section 2.2.2 awards costs to the Contractor for demobilization and remobilization.
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Mr. Sams may be contacted at mpsams@KandSlegal.com
Ms. Cox may be contacted at ajcox@KandSlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Essential Business Operations: a High-Stakes Question Under Proliferating “Stay at Home” Orders
April 27, 2020 —
Karen C. Bennett, Katherine I. Funk & Jane C. Luxton - Lewis BrisboisAn ever-expanding number of states and local government authorities are issuing “shelter in place” or “stay at home” orders that restrict the movement of employees of non-essential businesses. These orders have prompted many businesses to question whether they qualify as “essential,” requiring employees to continue working. With substantial differences among the stay at home orders – and even potential conflicts between state and local directives – it is a matter of extreme urgency for businesses to determine whether they fall within the definition of “essential,” particularly as many of these orders include civil and criminal penalties.
Developments are unfolding very quickly, and clients we are advising are encountering law enforcement visits and threats of criminal prosecution as a consequence of decisions to stay open. As these designations are heavily fact-specific, and being revised, advance preparation and advice of counsel are essential.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Katherine I. Funk and
Jane C. Luxton
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Funk may be contacted at Katherine.Funk@LewisBrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Uneven Code Enforcement Seen in Earthquake-Damaged Buildings in Turkey
February 14, 2023 —
Jeff Rubenstone & Neelam Matthews - Engineering News-RecordThe aftermath of the Feb. 6 earthquakes and aftershocks in central Turkey has begun to shift from immediate search-and-rescue efforts to a grim cataloguing of the extent of the destruction, with emergency response teams in Turkey and Syria beginning the work of evaluating the condition of thousands of buildings and infrastructure impacted by the temblors.
Reprinted courtesy of
Jeff Rubenstone, Engineering News-Record and
Neelam Matthews, Engineering News-Record
Mr. Rubenstone may be contacted at rubenstonej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Insurance Commissioner Lacks Authority to Regulate Formula for Estimating Replacement Cost Value
April 15, 2015 —
Valerie A. Moore and Christopher Kendrick – Haight Brown & Bonesteel LLPIn Assn. of Cal. Insurance Companies v. Jones ( No. B248622, filed 4/8/15), a California appeals court held that California’s Insurance Commissioner Dave Jones lacked the authority to promulgate California Code of Regulations, title 10, section 2695.183, which set out specific requirements for estimating replacement cost as part of any application or renewal for homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the wildfires in Southern California in 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Partner Jonathan R. Harwood Obtained Summary Judgment in a Coverage Action Arising out of a Claim for Personal Injury
December 22, 2019 —
Jonathan R. Harwood - Traub Lieberman PerspectivesOn August 16, 2019, Traub Lieberman partner obtained summary judgment in a declaratory judgment action involving a claim for coverage for a personal injury action involving injuries suffered on a construction site. The plaintiff in the underlying action was performing excavation in a basement of a building in Manhattan so the owner could install a pool. During the course of the excavation plaintiff fell 13 feet from a plank, into the excavated pit, suffering serious injuries. Traub Lieberman’s client issued a CGL policy to the building owner and the insured sought coverage for the suit under that policy. The insurer denied coverage based on an endorsement to the policy that stated the insured could only contract directly with a specified general contractor. The plaintiff was an employee of a subcontractor and the insurer believed the insured had contracted directly with that unapproved subcontractor. The insured denied it had done, contending the subcontractor had been hired by the general contractor identified in the endorsement.
Reprinted courtesy of
Jonathan R. Harwood, Traub Lieberman
Mr. Harwood may be contacted at jharwood@tlsslaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Colorado Temporarily Requires Employers to Provide Sick Leave While Awaiting COVID-19 Testing
April 06, 2020 —
Shawna Ruetz - The Grindstone Lewis Brisbois Labor & Employment BlogOn March 11, 2020, the Colorado Department of Labor and Employment (CDLE) issued emergency rules, referred to as Colorado Health Emergency Leave with Pay (Colorado HELP) Rules, requiring employers in certain industries to provide four days of paid sick leave to employees with flu-like symptoms while awaiting test results for COVID-19, or to anyone who is under instructions from a healthcare provider to quarantine or isolate due to a risk of having COVID-19. These rules take effect immediately for 30 days, or longer if the state of emergency declared by Colorado Governor Polis continues.
Which industries are covered by the Colorado HELP Rules?
- Leisure and hospitality;
- Food services;
- Child care;
- Education (including transportation, food service, and related work at educational establishments);
- Home health (if working with elderly, disabled, ill, or otherwise high-risk individuals)
- Nursing homes; and
- Community living facilities; and
- Retail establishments that sell groceries (added March 26).
How much paid sick leave must be provided?
Employers are required to provide up to four days of paid sick leave to employees with flu-like symptoms who are being tested for COVID-19. If the employee tests negative, the leave ends.
Read the court decisionRead the full story...Reprinted courtesy of
Shawna Ruetz, Lewis BrisboisMs. Ruetz may be contacted at
Shawna.Ruetz@lewisbrisbois.com
Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com