Court Rules Planned Development of Banning Ranch May Proceed
June 10, 2015 —
Kristian B. Moriarty and Lawrence S. Zucker II – Haight Brown & Bonesteel, LLPIn Banning Ranch Conservancy v. City of Newport Beach (filed 5/20/2015, No. G049691), the California Court of Appeal, Fourth District, held the Environmental Impact Report prepared by the City of Newport Beach for the partial development of Banning Ranch complied with California environmental protection statutes and local ordinances.
Under the California Environmental Quality Act (“CEQA”), a city desiring to approve or carry out a project that may have significant effect on the environment must prepare an environmental impact report (“EIR”) designed to provide the public with detailed information about the effect which a proposed project will have on the environment. The California Coastal Act of 1976 provides for heightened protection of environmentally sensitive habitat areas (“ESHA”) defined as any “area in which plant or animal life or their habitats are either rare or especially valuable because of their special nature or role in an ecosystem and which could be easily disturbed or degraded by human activities and developments.”
In 2006, the City of Newport Beach adopted a General Plan for the physical development of the city. The plan specifically identifies Banning Ranch as having significant value as a wildlife habitat and open space resource for citizens. The general plan includes a primary goal of complete preservation of Banning Ranch as open space. To the extent the primary goal cannot be achieved, the plan identifies a secondary goal allowing limited development of Banning Ranch “to fund preservation of the majority of the property as open space.” The plan also requires the City to coordinate any development with the state and federal agencies.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com; Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Towers to Be Demolished without Being Finished
October 02, 2013 —
CDJ STAFFEngineering.com looks at why the Harmon Tower in Las Vegas will be coming down at some point in the future. Construction stopped, unfinished in 2008. Taking the building down will cost about $400 million, which the building’s owner feels that the developer should pay.
Inspectors concluded that the building did not meet the earthquake specifications for Las Vegas. The contractor claimed that the fault was due to the design specifications and that the supports were further weakened during destructive testing.
Read the court decisionRead the full story...Reprinted courtesy of
Berkeley Researchers Look to Ancient Rome for Greener Concrete
June 28, 2013 —
CDJ STAFFWhile modern concrete often crumbles after fifty years, some concrete laid down during the Roman Empire is still strong, even after 2,000 years. Researchers at UC Berkeley have been puzzling over the secrets of Roman concrete, using samples from a breakwater near Naples. The breakwater was built about 37 BC, and the concrete is still strong. Unlike modern concrete, the Romans made theirs with a mixture of lime and volcanic ash.
Paulo Monteiro, a professor of civil and environmental engineering at Berkeley, noted that one of the drawbacks of Roman cement was that it hardens more slowly than modern concrete. An advantage is that it is more environmentally friendly, and the researchers are trying to determine if volcanic ash cement would be a good substitute. Professor Montiero hopes that fly ash and volcanic ash cements “could replace 40 percent of the world’s demand for Portland cement.”
Read the court decisionRead the full story...Reprinted courtesy of
Honoring Veterans Under Our Roof & Across the World
November 15, 2017 —
Newmeyer & Dillion, LLPNovember 11, 2017 - In honor of Veterans Day, we would like to take time to acknowledge, honor and thank those who have served in the United States Armed Forces. We are also proud to recognize eleven of our own who have served our great country.
Ben Ammerman – United States Navy
Philip Kopp – United States Air Force
Ryan Manning – United States Marine Corps
Jason Morris – United States Marine Corps
Tyson Nakagawa - United States Marine Corps
Richard Protzmann - United States Marine Corps
Francis Quinlan - United States Marine Corps
Louis “Dutch” Schotemeyer - United States Marine Corps
Christina Soto-Maynez – United States Army
Michael Studenka - United States Marine Corps
Paul Tetzloff - United States Marine Corps
About Us
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
How Robotics Can Improve Construction and Demolition Waste Sorting
September 11, 2023 —
Emily Newton - Construction ExecutiveCommercial construction projects generate a lot of waste. Managing this debris is crucial to minimizing the industry’s environmental impact, but it’s often a time-consuming and error-prone process. Robotic waste sorting provides a better alternative.
Why C&D Waste Management Must Improve
The current state of construction and demolition (C&D) debris management leaves considerable room for improvement. Nearly all C&D waste takes
decades to break down in landfills—and the sector generates hundreds of millions of tons of it annually.
More efficient debris management would help firms protect the environment and their bottom line. Poor waste management practices also take an economic toll. Recycling extends materials’ useful life, helping minimize resource costs. Inefficient waste sorting may additionally lead to unnecessarily high workforce expenses and incur lost business from firms’ lack of sustainability.
Reprinted courtesy of
Emily Newton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Transition Study a Condo Board’s First Defense against Construction Defects
December 04, 2013 —
CDJ STAFFAccording to the advice provided by T. Allen Mott and Nicholas D. Cowie, condominium boards would be well advised to “hire an engineer or architect to perform a transition study,” since it would be preferable to repair any problems while warranties are still in effect. They also caution that the board must “determine whether the developer-created budget and reserve fund are adequate to cover the cost of maintaining the condominium’s construction over time.”
They note that discovered in time, some problems are easy to fix, but left unrepaired, they can result in “extensive, hidden property damage requiring associations to borrow money and assess unit owners to cover the entire cost of repairing the developer’s construction defects and resulting property damage. The goal, as they point out, is “an amicable repair resolution.”
Read the court decisionRead the full story...Reprinted courtesy of
Parks and Degradation: The Mess at Yosemite
September 09, 2024 —
Laura Bliss - BloombergA couple of miles past the western entrance to Yosemite National Park, visitors pass from California into a postcard. The road opens to a majestic view of
Half Dome, El Capitan and Cathedral Rocks—celebrity peaks if ever there were—which form the towering walls of Yosemite Valley. On the pine-scented floor of John Muir’s mountain mansion, the Merced River flows gently by the side of the road as signs point toward trailheads and tourist destinations. Not far from
Curry Village, a cluster of tent cabins and eateries at the eastern end of the road, is a section of employee housing known as the Stables. It was there that Erin Rau found herself wrapped in a sleeping bag one broiling afternoon last summer, wondering whether she was about to die.
Rau was a little over a month into a seasonal job selling goods in the village’s general store. Almost as soon as she arrived from Michigan, she recalls, she got the sense this wouldn’t be the carefree, post-college summer gig she’d imagined. In the evenings, she was left alone to manage a bunch of fellow early-twentysomethings making the same sixteenish bucks an hour until the shop closed at 10. At night a family of ringtail possums would crawl down from the rafters to tear into a display of baked goods, a long-standing issue she says her bosses did nothing to resolve, apart from throwing away half-eaten muffins in the morning. Similarly, deer mice kept leaving droppings on the pillows and sheets in the cabin Rau shared with three other women. When one of her roommates complained, she says, management supplied a Ziploc with a couple of mouse traps, a mask, gloves and some hand wipes, leaving the employees to sort out the rest.
Read the court decisionRead the full story...Reprinted courtesy of
Laura Bliss, Bloomberg
Pennsylvania Supreme Court Adopts New Rule in Breach-of-the-Consent-to-Settle-Clause Cases
August 19, 2015 —
Sean Mahoney – White and Williams LLPIn Babcock & Wilcox Company, et al. v. America Nuclear Insurers, et al., the Pennsylvania Supreme Court recently held that where a liability insurer has agreed to provide a defense to its insured in an underlying tort action subject to a reservation of rights but refuses to consent to a settlement in that action, the insured may nevertheless accept the settlement over the insurer’s objection where the settlement is “fair, reasonable, and non-collusive” from the perspective of a reasonably prudent person in the insured’s position in light of the totality of the circumstances and is covered. Babcock & Wilcox Company v. America Nuclear Insurers, No. 2 WAP 2014, 2015 WL 4430352 (Pa. Jul. 21, 2015). This decision fills an important gap in Pennsylvania precedent addressing the rules applicable when an insurer refuses to consent to an insured’s settlement of a lawsuit.
In Babcock, the underlying plaintiffs sued Babcock & Wilcox Company and Atlantic Richfield Company (“the Insureds”) alleging that the Insured’s nuclear facilities caused bodily injury and property damage. The Insureds’ liability insurers agreed to defend the Insureds subject to a reservation of rights. The insurers later refused to consent to an offer to settle the underlying action for a total of $80 million because they believed the Insureds were likely to succeed on the merits. Nevertheless, in 2009, the Insureds accepted that offer and settled the underlying action for $80 million, notwithstanding the insurer’s refusal. The Insureds then sought reimbursement of the $80 million settlement from their insurers, who rejected that request on the ground that the Insureds had breached the consent-to-settlement/cooperation provisions of the implicated policies.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Mahoney, White and Williams LLPMr. Mahoney may be contacted at
mahoneys@whiteandwilliams.com