Construction Upturn in Silicon Valley
August 17, 2011 —
CDJ STAFFWork resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.
A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
An Interesting Look at Mechanic’s Lien Priority and Necessary Parties
May 13, 2019 —
Christopher G. Hill - Construction Law MusingsAs regular readers of Construction Law Musings are well aware, I like to discuss mechanic’s liens. Whether it is their picky nature, the way court’s treat them or the soon to take effect changes in the form, mechanic’s liens are a topic near and dear to my heart as a construction attorney.
This past month the Fairfax Circuit Court took on the intersection of mechanic’s lien priority under Virginia Code section 43-21 (the lien priority statute) and what constitute necessary parties that must be named in any enforcement suit. In Marines Plumbing, LLC v. Durbin, et al., the Court discussed an all too typical scenario. Marines Plumbing performed repair work on the defendants’ property and the defendants did not pay for the work. Marines Plumbing recorded a memorandum of lien and subsequently sued to enforce that lien. In filing its suit, Marines Plumbing failed to name the trustees and lender on a deed of trust securing the loan on the property. Needless to say, the Defendants moved to dismiss the action for failure to name necessary parties (lender and trustees).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
CGL Insurer’s Duty to Defend Insured During Pre-Suit 558 Process: Maybe?
December 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesIn earlier postings, I discussed the issue of whether Florida Statutes Chapter 558′s pre-suit construction defects process triggers a CGL insurer’s duty to defend. The issue was whether Florida’s 558 pre-suit notice of a construction defect and repair process met the definition of “suit” within a standard CGL policy.
A standard CGL policy defines the term “suit” as:
“Suit” means a civil proceeding in which damages because of “bodily injury,” “property damage” or “personal and advertising injury” to which this insurance applies are alleged. “Suit” includes:
a. An arbitration proceeding in which such damages are claimed and to which the insured must submit or does submit with our consent; or
b. Any other alternative dispute resolution proceeding in which such damages are claimed and to which the insured submits with our consent.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Toll Brothers Faces Construction Defect Lawsuit in New Jersey
October 10, 2013 —
CDJ STAFFToll Brothers is facing a construction defect lawsuit from homeowners in West Windsor, New Jersey. The homebuilding company had a lengthy battle with the town over its intention to build the community they named the Estates at Princeton Junction, now its residents are alleging defects in the construction of their homes and the common infrastructure. The community is close to Princeton University, parts of which are also in West Windsor.
Toll Brothers states that they are “working very closely with the HOA Board to investigate the claims that have been alleged in the lawsuit.” Andrea Marushack, the spokesperson for Toll Brothers would not elaborate due to the lawsuit. Among the allegations are claims that the townhomes in the development are prone to water intrusion. The complaint also claims that there were defects in the construction of sidewalks, roads, and other common features.
Read the court decisionRead the full story...Reprinted courtesy of
Endorsements Preclude Coverage for Alleged Faulty Workmanship
December 30, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court found coverage for alleged faulty workmanship was barred by the Combination Construction Related Endorsement and Roofing Endorsement. Evanston Ins. Co. v. A&S Roofing, 2019 U.S. Dist. LEXIS 142828 (W.D. Okla. Aug. 22, 2019).
In 2010, A&S entered into a subcontract with the contractor to replace roofs on three buildings owned by Oklahoma Property Investors (OPI). Eagle was a subcontractor of A&S that installed the roofing. After the roofs were replaced, OPI filed suit against A&S, alleging that A&S provided 15-year warranties for the roofing work performed on the three buildings and that A&S breached each warranty by performing the work in a poor manner, resulting in failures to each of the roofs. OPI sought monetary relief including damages to its properties, of its tenants, and costs of repairs to its properties.
A&S's insurer, Evanston, denied coverage. Evanston pointed to the"legally obligated to pay" language of the CGL policy and argued coverage only extended to tort-based claims. Evanston argued the OPI lawsuit did not allege any tort claims, only warranty claims arising from contract. Second, Evanston contended the alleged "poor craftsmanship" giving rise to the claims in the OPI lawsuit that did not constitute an "occurrence" under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
As California Faces Mandatory Water Use Reductions How Will the Construction Industry be Impacted?
May 07, 2015 —
Garret Murai – California Construction Law BlogEarlier this month, Governor Jerry Brown issued Executive Order B-29-15, which imposes mandatory water use reductions for the first time in the history of California.
The Executive Order, issued as the state enters its fourth year of severe to exceptional drought, directs the State Water Resources Control Board (“State Water Board”) to impose a 25% reduction on the state’s 400 local water supply agencies which serve 90% of California residents, over the coming year.
The State Water Board has already issued proposed regulations based on informal comments received from the public, and in a “Fact Sheet” issued this weekend, has indicated that it is seeking additional informal comments no later than April 22, 2015, with final proposed emergency regulations to be released on April 28, 2015, which will then be considered by the State Water Board at its meetings on May 5 and 6, 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Canadian Developer Faces Charges After Massive Fire on Construction Site
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFA fire leveled an apartment construction site in Canada last December, which resulted in almost two dozen charges relating to fire safety precautions and lack of cooperation with the Ministry of Labour’s investigation, according to CKWS TV. The Ministry of Labour has recently “laid 22 charges against three individuals and two companies—Jay Patry Enterprises Inc. and Steimach Property Management Inc.”
CKWS TV reported that “[c]harges include failing to provide adequate space for workers to evacuate during an emergency, failing to protect the health and safety of workers and failing to inspect every fire extinguisher for defects or deterioration.” Jason Patry, Nathan Patry and Troy Stelmach have been charged with “obstructing and providing false information to a ministry of labour inspector, as well as failing to make the inspection process an easy one.”
Read the court decisionRead the full story...Reprinted courtesy of
Retroactive Application of a Construction Subcontract Containing a Merger Clause? Florida’s Fifth District Court of Appeal Answers in the Affirmative
September 07, 2017 —
Sanjo S. Shatley - Florida Construction Law NewsFlorida’s Fifth District Court of Appeal recently addressed the issue of retroactive application of a construction subcontract on the basis of a merger clause in Don Facciobene, Inc. v. Hough Roofing, Inc.[1]
In the case, in late 2010, Don Facciobene, Inc. (“DFI”), a licensed general contractor, contracted with Digiacinto Holdings, LLC, an owner of a home built in 1905 in Melbourne, Florida, known as the Nannie Lee House or the Strawberry Mansion, to perform various renovations in preparation for a restaurant to be opened on the premises. One of the renovations included a new roof. DFI subcontracted the roofing work to Hough Roofing, Inc. (“HRI”), a licensed roofing subcontractor. In mid-March 2011, HRI submitted an estimate and proposed statement of work to DFI. DFI’s project manager signed HRI’s proposal on April 5, 2011, as well as an additional expanded proposal six days later. According to the proposals, payment was due on completion. HRI began work on the roof on April 15, 2011, without a signed subcontract. However, DFI and HRI ultimately executed a subcontract on June 8, 2011, even though HRI had mostly finished its work by the end of May.
Read the court decisionRead the full story...Reprinted courtesy of
Sanjo S. Shatley, Cole, Scott & Kissane, P.A.Mr. Shatley may be contacted at
sanjo.shatley@csklegal.com