Replacement of Gym Floor Due to Sloppy Paint Job is Not Resulting Loss
January 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion for summary judgment finding damage to the gym floor due to a poor paint job was not a resulting loss. Bob Robinson Commercial Flooring, Inc. v. RLI Ins,. Co., 2023 U.S. Dist. LEXIS 196105 (D. Ark. Nov. 1, 2023).
Bob Robinson Commercial Flooring (BRCF) submitted a bid to the general contractor, Nabholz Construction Corporation, to install a vinyl athletic floor and striping at a middle school. The job also included the painting of a "Wildcat" logo the main gym floor. Therefore, BRCF's job was to install floors with proper painting and striping. Robert Liles and Robert Lines Parking Lot Services was the subcontractor hired to do the painting and striping. BRCF did not supervise or inspect Liles' work while it was ongoing.
Nabholz informed BRCF that there were problems with the floor painting, including crooked lines, incorrect markings, misplacement of the three point lines for the basketball surface, drips, smudges, etc. The gym floor was eventually rejected due to the nature of the vinyl flooring, once primer and paint were applied, the paint could not be removed and repainted. BRCF had to hire a new subcontractor to remove the flooring, install new flooring and then paint new lines. The cost for removal and replacement was $134,188.95.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Another Guilty Plea In Nevada Construction Defect Fraud Case
April 25, 2012 —
CDJ STAFFThe eleventh defendant has entered a guilty plea in the ongoing federal investigation of construction defect fraud in the Las Vegas area. Mahin Quintero plead guilty to producing a false authentication feature, a misdemeanor. Ms. Quintero’s part in the scheme was to falsely authenticate signatures on loan documents for straw buyers. Ms. Quintero stated in court that she had been ordered to destroy her notary book three years ago. According to her plea bargain, the straw buyers did not appear in front of her when she notarized their signatures. As part of the scheme, the straw buyers would take control of homeowners associates, sending construction defect complaints and repairs to favored firms.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
How To Lock Disputes Out Of Your Project In Construction
July 22, 2019 —
Anastasios Koutsogiannis – LetsBuildDisputes are seen as one of the main threats for the successful completion of a project in construction. There is a plethora of factors which could lead to a construction dispute (e.g. contracts, behavior, environment) but, strangely enough, the industry seems to invest more attention on the resolution of a conflict instead of its prevention.
Thanks to the progress that digital technologies have witnessed during the last few years, there is a good chance that things in construction will change for the better soon. The ability to exchange crucial updates in real time, while keeping a detailed record of everything that happens on the field adds an extra level of protection to your project and ensures that all agents are on the same page.
In an effort to shed some light on the issue of construction disputes, we present below four tips that could help your team to lock conflicts out of your project:
1. Standardize your processes
Before you kickstart your project, it is of paramount importance that you standardize all your systems and processes. In that way, you will be able to add extra clarity to your workflow and eliminate misunderstandings.
Once you have achieved that, you can replicate the same process to your future projects. The more you manage to repeat the same project structure the better your team will become in completing their tasks without ending up in any kind of conflict.
In that sense, standardization could be a long-term investment for your organization.
2. Go digital
As soon as your processes are defined, it is time for the digital journey to begin. Finding the right tool for your project will result in a streamlined construction process where all the members of the team are on the same page without any room for costly mistakes or disagreements.
Furthermore, with the help of digital solutions it becomes easier for project managers to measure the performance on site and monitor the completion of the set benchmarks. Like that, all payments will be on time and the program of the project will reflect reality.
3. Be extra careful with the contracts
A poorly-written contract can have a big impact on the effort to lock disputes out of your construction project. While putting together a new contract, you should always make sure that you have taken into account all the different scenarios for your project.
Either that is a delay due to weather conditions or an accident on site everything should be described in detail in the contracts and be well understood by those in charge.
In any other case, things can get a bit risky and a costly dispute might wait to happen.
4. Hold regular meetings with all stakeholders
Last but certainly not least, meet regularly with all project stakeholders. The frequent contact with the different members of your team will allow you to discuss and resolve any problematic situations before they grow out of proportion.
What is more, regular meetings will help both your field teams and the people in the office to remain aligned and will eliminate the possibility of having people working on outdated versions of the program.
Of course, these meetings don’t need to be time-consuming or even in person. With the help of technology, you can keep these meetings short and to the point. In that manner, everybody involved will be able to get the most out of them.
Final word
All in all, it becomes clear that locking disputes out of your project in construction requires continuous work and a carefully-elaborated plan. Thankfully, the emergence and progress of digital solutions have made this process much easier contributing significantly to the development of the industry far from disputes and project misunderstandings.
About the author: Anastasios Koutsogiannis is Content Marketing Manager at LetsBuild.
Read the court decisionRead the full story...Reprinted courtesy of
Anastasios Koutsogiannis, LetsBuild
Philadelphia Court Rejects Expert Methodology for Detecting Asbestos
October 11, 2017 —
Christian Singewald, Wesley Payne & Jonathan Woy - White and Williams LLPLawsuits against talcum powder manufacturers have recently made headlines for the multimillion dollar verdicts returned in favor of plaintiffs with ovarian cancer. However, lawsuits brought by individuals with mesothelioma who did not work in occupations traditionally associated with asbestos exposure represent another potential liability for talcum powder manufacturers and retailers. In such cases, expert testimony linking mesothelioma to trace amounts of asbestos in talcum powder should be carefully scrutinized.
Reprinted courtesy of White and Williams LLP attorneys
Christian Singewald,
Wesley Payne and
Jonathan Woy
Mr. Singewald may be contacted at singewaldc@whiteandwilliams.com
Mr. Payne may be contacted at paynew@whiteandwilliams.com
Mr. Woy may be contacted at woyj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Exists for Landlord as Additional Insured
September 03, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Court of Appeals determined the landlord was entitled to coverage as an additional insured under the tenant's policy. Selective Ins. Co. v. Erie Ins. Exch., 2014 Ind. App. LEXIS 365 (Ind. Ct. App. July 30, 2014).
Rangeline, LLC owned a warehouse. Rangeline negotiated a lease with Hammons Storage to store insulation manufactured by Knauf Insulation. Pursuant to requirements in the lease, Hammons secured liability coverage with Erie Insurance naming Rangeline as an additional insured.
After Hammons moved insulation into the warehouse for storage, the pipes of the sprinkler system burst, causing damage to the insulation. The cause of the loss was determined to be water from the system freezing, which led to the cast iron fittings cracking, causing the failure of the sprinkler heads.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
How California’s Construction Industry has dealt with the New Indemnity Law
October 22, 2014 —
Mark S. Himmelstein, Esq. - Newmeyer & DillionIt has been almost two years since the California legislature enacted changes to the state’s indemnity law affecting commercial construction contracts. Although we do not yet have any court opinions analyzing the new statutes, the attorneys at
Newmeyer & Dillion now have real world experience in negotiating such indemnity provisions. It is time to evaluate how the construction community has reacted to the changes. In this article, we examine the practical applications of the new law to various construction agreements.
Enacted on January 1, 2013, the new legislation was the latest in a series of efforts by subcontractors and their insurers to eliminate “Type I” indemnity clauses. Under a Type I provision, a subcontractor has a duty to indemnify the developer or general contractor for the negligence of the developer or general contractor or other subcontractors, in addition to the negligence of the subcontractor itself. In 2006, the law was changed to preclude Type I provisions regarding “For Sale” residential construction defect claims. At that time, there was no such restriction enacted for commercial construction contracts. However, since then, commercial subcontractors have been seeking similar legislation. Their efforts culminated in the 2013 revisions regarding commercial contracts.
Commercial Subcontracts
Pursuant to the new indemnity statute — Civil Code section 2782.05 — we have revised our clients’ commercial subcontracts to:
(a) Eliminate the requirement that the subcontractor indemnify the general contractor for the general contractor’s “active negligence;” and
(b) Include the subcontractor’s options for defending claims for which they have an indemnity obligation.
Many subcontractors have responded: “Hey, wait a minute, the new legislation eliminated Type I indemnity so you (general contractor) cannot still require any indemnification for the general contractor’s negligence”. Well, that might be the rumor in subcontractor circles, but the new statute does not eliminate indemnity for the general contractor’s passive fault. In addition, the Civil Code lists 13 instances where the new indemnity restrictions do not apply.
Residential Subcontracts
The legislature did not make anyone’s job easier by drafting a different indemnity provision for commercial subcontracts than for residential subcontracts. In fact, the residential and commercial statutes are different in several critical respects. First, the restrictions on indemnity in the residential statute apply only to construction defect claims in newly constructed “For Sale” houses. The statute does not preclude Type I indemnity provisions for any other claims arising out of residential subcontracts. In contrast, the indemnity restrictions in the commercial statute apply to all claims arising out of commercial subcontracts. In addition, the commercial statute allows indemnity for the general contractor’s passive fault. Since some subcontractors on “residential” projects perform off-site “commercial” work as well, we have amended even residential subcontracts to address the subcontractors’ various indemnity obligations for different parts of their work (e.g., residential work versus commercial work).
Owner-Contractor Agreements
The January 1, 2013 new indemnity provisions apply not only to subcontracts, but also to owner-contractor agreements. Civil Code section 2782(c)(1) precludes indemnity for an owner’s active negligence. Interestingly, the exclusions contained in Civil Code section 2782.05 for subcontracts do not apply, and the statute does not provide contractors with the option of defending claims set forth in the sections concerning subcontracts. Therefore, we have revised the indemnity provisions in owner-contractor agreements to exclude indemnity for the owner’s active negligence.
Design Professional Agreements
The 2007 revisions with respect to “For Sale” residential contracts (discussed above), and the 2013 revisions for commercial contracts do not apply to design professionals. The new indemnity statute concerning commercial subcontracts specifically excludes design professionals from the “anti-indemnity” benefits provided to subcontractors. Therefore, Type I indemnity provisions are fair game and can still be included in design professional contracts.
Conclusion
In sum, Civil Code sections 2782 et seq. now contain an increasingly complex framework for indemnity rules in construction contracts. For example, there is one set of rules for “For Sale” residential construction defect claims (no indemnity for the developer’s active or passive negligence), another for any other claims arising out of residential construction (Type I indemnity is permitted), another for commercial subcontracts (no indemnity for the general contractor’s active negligence, but indemnity for the general contractor’s passive negligence unless any of the exceptions apply, in which case Type I indemnity is permitted), and yet another for commercial owner contractor agreements (no indemnity for the owner’s active negligence, but indemnity for the owner’s passive negligence with no exceptions).
California’s indemnity laws are complex, and rumors as to the impact of the new legislation have made it even more difficult to negotiate these provisions. It is imperative that indemnity clauses in construction contracts clearly delineate the obligations for the specific type or types of work contemplated by the contract. The legislature’s attempt to simplify indemnity obligations has actually made such provisions lengthier and more cumbersome. As experienced construction attorneys, our task is to draft indemnity provisions that comply with the laws, address potential claims, and are understandable.
Mr. Himmelstein is a partner in the Newport Beach office of Newmeyer & Dillion and practices in the areas of construction, real estate, business and insurance litigation. He also specializes in drafting and negotiating construction and real estate contracts. Mark can be reached at mark.himmelstein@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Reminder: Pay if Paid Not All Encompassing (but Could it be?)
December 09, 2019 —
Christopher G. Hill - Construction Law MusingsOn numerous occasions, I have discussed the need to be careful with so called “pay if paid” clauses in construction contracts. While such clauses are enforceable in Virginia (when phrased correctly), there are exceptions and limitations (for instance in the Miller Act context).
One such exception (that I frankly would have thought to be obvious) is that such clauses do not protect a general contractor from paying all subcontractors. Such a clause only protects a general contractor from payment to those subs for whose work the general contractor has not been paid. In other words, if a general contractor has been paid by an owner for a particular subcontractors work, it cannot use the pay if paid clause to deny payment even in the event that other subcontractors were deficient in their work or the owner has failed to pay the general contractor in full.
In Precision Contractors Inc. v. Masterbuilt Companies Inc. (PDF) the Fairfax, VA Circuit Court reiterated this principal stating that nothing in the contract suggests that either party to the lawsuit had any intention to shift the risk of non-payment by the owner or non-performance of other subcontractors to the plaintiff (Precision).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Draft Federal Legislation Reinforces Advice to Promptly Notify Insurers of COVID-19 Losses
April 20, 2020 —
James Hultz - Newmeyer DillionInsurers across the country are nearly universally denying claims for business interruption stemming from the COVID-19 pandemic. Those denials have in turn been met with swift litigation and potential legislative action. The first business interruption coverage lawsuit related to COVID-19 was filed in New Orleans on March 16. There are now no less than 13 such cases nationwide and many more are likely to follow. Further, legislatures in at least seven states are considering legislation that would, to varying degrees, mandate business interruption coverage for COVID-19 losses, notwithstanding any seemingly contrary policy provisions.
From the early stages of the pandemic, we have consistently advised our clients to promptly notify their insurers of all COVID-19 related losses, even where coverage appeared uncertain. The deluge of coverage litigation and contemplated legislation could drastically alter how insurers handle COVID-19 claims. But policyholders who have failed to satisfy policy notice requirements could miss out on the benefits of those changes. Therefore, policyholders would be ill-advised to sit on the sidelines and wait it out.
Now, draft Federal legislation appears to add further impetus to instructions to “tender early.” The contemplated “Pandemic Risk Insurance Act of 2020” would reportedly devote billions of dollars of federal funds through a Department of Treasury administered reinsurance program designed to offset losses sustained by insurers who actually pay business interruption losses. The legislation is still taking shape but would reportedly create “a Federal program that provides for a transparent system of shared public and private compensation for business interruption losses resulting from a pandemic or outbreak of communicable disease.” President Trump is also reportedly pressuring insurers to provide business interruption coverage. The massive influx of federal funds and pressure from the White House could encourage insurers to reconsider denials of COVID-19 business interruption claims.
Read the court decisionRead the full story...Reprinted courtesy of
James Hultz, Newmeyer DillionMr. Hultz may be contacted at
james.hultz@ndlf.com