Construction Litigation Roundup: “Wrap Music to an Insurer’s Ears?”
February 05, 2024 —
Daniel Lund III - LexologyThe general contractor on a New Orleans condominium construction project obtained a Contractor Controlled Insurance Program/CCIP policy or "Wrap-Up" policy for the job.
An accident occurred on the job when a construction elevator/hoist fell, injuring several workers. The elevator/hoist was provided by a subcontractor, pursuant to a rental agreement and related subcontract with the general contractor. Contained within the subcontract was a provision which states that the general contractor "has arranged for the Project to be insured under a controlled insurance program (the "CCIP" or "WrapUp"),” and that the CCIP shall provide "commercial general liability insurance and excess liability insurance, in connection with the performance of the Work at the Project site."
A third-party administrator for the wrap-up policy had been in communication with the subcontractor prior to the commencement of the work, “specifically advising that insurance coverage was not automatic” and providing the subcontractor with an enrollment form for the CCIP. Ultimately, the subcontractor “declined to comply with the request,” stating that the subcontractor would "not participate in paying any wrap insurance premiums" – because the subcontractor had its own insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
New York’s Second Department Holds That Carrier Must Pay Judgment Obtained by Plaintiff as Carrier Did Not Meet Burden to Prove Willful Non-Cooperation
November 23, 2020 —
Craig Rokuson - Traub LiebermanIn the recent case of DeLuca v. RLI Insurance Company, 2020 WL 5931054 (October 7, 2020), the Supreme Court, Appellate Division, Second Department held that RLI had a duty to pay a judgment obtained by an underlying plaintiff against RLI’s insured, MLSC. The underlying plaintiff brought the action directly against the carrier after obtaining a judgment against MLSC, and when the judgment remained unsatisfied, serving RLI with the judgment. As an initial matter, the court found that the direct action by the plaintiff was proper under New York Insurance Law 3420(a), which allows for an injured plaintiff to maintain a direct action against a carrier if a judgment against that carrier’s insured remains unsatisfied for a period of 30 days and the carrier is served with that judgment. In that event, the plaintiff steps into the shoes of the insured and is entitled to the rights of the insured (and is also subject to the carrier’s coverage defenses).
Reprinted courtesy of
Craig Rokuson, Traub Lieberman
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Special CDJ Thanksgiving Edition
November 21, 2017 —
Beverley BevenFlorez-CDJ STAFFWelcome to the Construction Defect Journal’s special Thanksgiving edition. The CDJ staff has compiled the most important and interesting stories so far from 2017. From Supreme Court decisions to state construction defect law shake ups, this week’s edition showcases significant construction defect industry changes. With a mug of hot spiced cider in hand, relax and reflect on what has happened in our industry so far in 2017.
CDJ wishes to give thanks to its amazing contributors and readers. It’s due to your efforts and support that CDJ is able to present a weekly summary of what is happening in the construction defect industry. We hope you enjoy this special edition, and wish you and your family a fun and festive Thanksgiving holiday.
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
When is Construction Put to Its “Intended Use”?
July 31, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCDefining words and phrases in the law can be a tricky proposition. In everyday life one would presume to know what the phrase “intended use” would mean, but when it comes to litigation, oftentimes the definitions become much more nuanced.
On March 12, 2013, in the Bituminous Cas. Corp. v. Hartford Cas. Ins. Co. v. Canal Ins. Co., WL 950800 (D. Colo. 2013) case, Senior District Court Judge Wiley Y. Daniel denied Third-Party Defendant Canal Insurance Company’s (“Canal”) motion to dismiss Third-Party Plaintiff Hartford Casualty Insurance Company’s (“Hartford”) third-party complaint. The case arose out of a liability insurance coverage dispute related to an underlying construction defect lawsuit. In the construction defect suit, a plaintiff homeowner’s association brought a suit against a developer and a general contractor (“GC”) among others. While the underlying action was settled, a dispute remained between Bituminous Casualty Corporation, which insured the GC, and Hartford, which insured the developer.
Hartford asserted third-party claims against Canal seeking a declaration of Canal’s obligations and contribution in the event Hartford owed any defense or indemnity obligations to the GC. Hartford’s claims are based on the premise that Canal owed a duty to defend and/or indemnify the GC in the underlying action.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Lis Pendens – Recordation and Dissolution
July 28, 2016 —
David Adelstein – Florida Construction Legal UpdatesWhen you file a construction lien foreclosure lawsuit, you must also record a lis pendens in the official (public) records against the property. This lis pendens serves as written notice that there is a lawsuit concerning the real property, and more specifically, title relating to that real property. If the property is then sold or rented, the buyer or tenant will ultimately be bound by a final determination relating to the lawsuit concerning title to the property. This is the value in recording a lis pendens and why it is a MUST in any foreclosure lawsuit. (This is the same value in any mortgage foreclosure lawsuit and why lis pendens are recorded in these lawsuits too.) A lis pendens will show up in a title report. In most instances, title companies will not issue a title policy if there is a lis pendens or may require a certain amount of money escrowed as a result of the lis pendens and pending action in order to issue a title policy. Also, a buyer, in particular, and a tenant are not going to want to invest in property where the title to that property is at-issue in a lawsuit. Hence, the lis pendens impacts the sale and potential re-financing of the property.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
What You Need to Know About CARB’s In-Use Off-Road Diesel Regulations
May 20, 2024 —
Garret Murai - California Construction Law BlogIn November 2022, the California Air Resources Board (CARB) approved amendments to . . . wait for it . . . its “In-Use Off-Road Diesel-Fueled Fleet” regulations – that enough hyphens for you – which took effect on January 1, 2024. The purpose of the regulations is to reduce emissions from off-road equipment, many of which are used by construction contractors, such as forklifts, bulldozers, cranes and excavators.
Are these new regulations?
Yes and no. CARB has regulated in-use off-road diesel-fueled vehicles since 2008 and has periodically amended these regulations. The most recent amendments take effect on January 1, 2024.
What vehicles do the regulations apply to?
The regulations apply to two classes of vehicles (1) self-propelled off-road diesel-fueled vehicles of 25 horsepower (hp) or more; and (2) two-engine vehicles other than on-road two-engine sweepers. The regulations apply to both owned as well as rented and leased vehicles. As used in this article, the term “vehicle(s)” refers to these two classes of vehicles.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Couple Claims Poor Installation of Home Caused Defects
December 30, 2013 —
CDJ STAFFRobert and Tracy Samosky of Spanishburg, West Virginia have filed a lawsuit claiming that the improper delivery of their modular home caused defects and damages, preventing them from actually using their home. The couple purchased a modular home from J&M Quality Construction for a home designed and built by Mod-U-Kraf Homes. They are suing the two firms for $50,000 in damages, reports the West Virginia Record.
Read the court decisionRead the full story...Reprinted courtesy of